London Borough of Hounslow
Audit and Governance Committee, Tuesday 3 February 2026 at 7.00pm

Risk Management

Noted Finance 2 papers

AI summaryHounslow's Audit and Governance Committee noted the updated Corporate Risk Register covering December 2025, which now lists two separate climate risks on extreme weather and the Council's 2030 Net Zero target.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted amended Corporate Risk Register at Appendix 1
MoneyNot stated
What happens nextNot stated
Who it affectsCouncil services and operationsRisks cover wide ranging Council functions including climate and equalities

What was decided

The committee noted the amended Corporate Risk Register at Appendix 1, covering risks as at December 2025. Report 14.1, 12.1

Why

The Council has a duty under regulation 3 of the Accounts and Audit Regulations 2015 to maintain a sound system of internal control that includes effective risk management arrangements. Report 7.1, P4, P5, P6

The Council's Constitution gives the Audit and Governance Committee responsibility to monitor the development and operation of risk management in the Council. Report P24

The register is the main tool for tracking the most significant risks facing the Council and managing exposure to their impacts. Report 7.2

What happens next

No implementation plan is set out; the report is a routine quarterly review of the Corporate Risk Register for Q3 2025/26. Report 12.1, P18

Any costs arising from risk management activity must be met from approved service or programme budgets or the capital programme. Report 6.2, 13.2

Implications

  • Legal: Risk management duties arise under the Accounts and Audit Regulations 2015 and the Council's Constitution, and embedded risk practice is described as part of the Council's governance arrangements. Report 7.1, P4, P5, P6, 14.2, P24
  • Climate: Two climate related risks are recorded separately: C&S0002A on responding to immediate climate risks and effects on the Borough, and C&S0002B on achieving Net Zero by 2030 from Council operations. Report P12, P13, 9.1
  • Financial: No direct financial implications; any actions to manage risk that affect the Budget are subject to separate decisions. Report 6.1, 6.2, 13.1, 13.2
  • Equalities: No direct communities, equalities and health implications, though several register risks do have such implications and are evaluated for impact on specific groups. Report 8.1, 8.2
  • Other: Effective risk management alongside financial and performance management is said to support the Council's value for money ambitions. Report 6.1, 11.1, 13.3

Who and where

  • London Borough of Hounslow and the services it delivers Report 7.2, 8.2

Timeline

  • 21st October 2025: Risk Management Framework referenced as background Report 16.1
  • December 2025: Position of the Corporate Risk Register reported, end of Q3 2025/26 Report 12.1
  • 2026-02-03: Audit and Governance Committee meeting where the register was noted

Plain English for the jargon

  • Corporate Risk Register (CRR): The Council's record of its most significant risks, with causes, consequences, existing mitigations and current controls.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

That the Audit & Governance Committee noted the amended Corporate Risk register at Appendix 1.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Audit and Governance Committee, 7 pages

Report for: INFORMATION

Contains Confidential or N Exempt Information

Cabinet Key Decision N

Report Title Quarterly Monitoring of Corporate Risk Register

Leader of the Council and Portfolio holder for Strategy, Member Reporting Resources and External Affairs

Sarah Filby, Director Strategy, Performance & Contact Details Commissioning [email protected]

For Consideration By Audit and Governance Committee

Date to be Considered Tuesday, 3 February 2026

Deadline for call-in N/A - report for information, not subject to call-in

Implementation Date N/A (if not called in)

Affected Wards (All Wards);

Approved by

1. Details of Recommendations

Audit and Governance Committee is asked to:

1. Note the amended Corporate Risk Register (CRR) at Appendix 1. 2. Report Summary

2.1This report deals with the quarterly review of the Corporate Risk Register (CRR). Appendix 1 details corporate risks as at December 2025 (i.e. end of Quarter 3, 2025/26).

2.2The Council’s Risk Management Framework determines that the CRR is owned and monitored by the Corporate Leadership Team (CLT), and monitoring reports are submitted to Audit & Governance (A&G) Committee.

2.3No corporate risks have been added or removed since the Committee last considered the CRR (at the end of Quarter 2 2025/26).

2.4Appendix 1 describes how corporate risks are being treated – current controls and mitigations in place – and identifies any further action (where necessary) to manage these risks.

2.5Audit & Governance Committee is asked to note the amended CRR at Appendix 1 – changes to the nature of risks, mitigations/ controls and risk scores.

3. Background and links to Corporate Priorities

3.1Risk management supports the London Borough of Hounslow’s ambition to be an outstanding Council serving an outstanding borough. It is at the heart of good management and corporate governance. Risk management is essential to the Council’s ability to deliver public services and to act as a custodian of public money. The Authority is legally required to have risk management arrangements in place.

3.2Cabinet approved the refreshed Risk Management Framework on 21 October 2025. The framework determines that the Corporate Risk Register (CRR) is owned and monitored by the Corporate Leadership Team (CLT), and regular monitoring reports are submitted to Audit & Governance Committee.

4. Corporate Risk Register (December 2025)

4.1The Corporate Risk Register (CRR) contains corporate risks. Corporate risks are those which cut across the delivery of all services, key programmes and projects and those that will affect the delivery of the Council’s objectives.

4.2Operational risks are those where the potential impact is limited to one part of the Council’s business – owned by directorates and reviewed at management team meetings on a regular basis. They are not usually on the CRR as they are on divisional/ departmental risk registers. However, any risks from operational risk registers can be escalated to the CRR if identified as being sufficiently important.

4.3The Council’s senior leaders are regularly asked to review the CRR and consider:

a) the current risks and their scores – do any scores need to be increased or can any be reduced? b) whether any risks should be amended, either because the nature of the risk has changed, or the risk context has changed – have any new mitigating actions been identified?

c) whether there are any new risks that should be included.

d) whether there are any risks that should be removed.

4.4Risks are scored according to the likelihood of their happening, from one being very unlikely, to five being very likely. They are also scored according to their potential impact, from one being negligible, to five being severe. These likelihood and impact scores are combined to give a total risk score. Four total risk scores have changed this quarter (Quarter 3 2025/26), with one increasing and three decreasing, see table below:

Current (Residual DoT (from Risk Description Risk) previous Q) Score

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk Register Update_FinalAppendix 1 4 pages Download
PDF
Risk ManagementReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Risk ManagementThis decision
  2. Risk ManagementNoted
  3. Risk ManagementNoted
  4. Risk ManagementNoted
  5. CEX621 Risk Management Strategy 2022-2024Approved
  6. Draft Risk Management StrategyNoted

More from Hounslow Audit and Governance Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for absence, declarations of interest or any other communication from MembersThere were no apologies for absence, declarations of interest or other communications. Decided Open
8 Sep 2026 Minutes of the meeting held on 3 February 2026The minutes of the meeting held on 3 February 2026 were agreed as an accurate record. Agreed Open
8 Sep 2026 Matters arising from the minutesThere were no matters arising from the minutes. Decided Open
8 Sep 2026 Quarterly Monitoring of Corporate Risk Register (Q1, 2026-27)Please see the report by Sarah Filby, Director Strategy, Performance & Commissioning (agenda item 4) The report was p... Decided Open
8 Sep 2026 Treasury Management Annual Report 2025/26Please see the report by Jake Bacchus, Executive Director of Finance and Resources (agenda item 5) The report was pre... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies