AI summaryHounslow Cabinet approves retendering of adult homecare with net budget of about £15m a year and £120m over eight years, choosing up to 12 providers.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedDelegated authority to Director of Commissioning to award contracts
MoneyNot stated
What happens nextITT to publish from 01/06/2026New service starts 01/11/2026
Who it affectsAdult homecare providers and service usersUp to 12 providers will be appointed
What was decided
Cabinet agreed to start procurement for retendering of adult homecare, with an annual net budget of about £15m and a total estimated eight-year budget of £120m, for a five-year contract with an option to extend by three years.
Cabinet delegated authority to the Director of Commissioning, jointly with the Borough Director of Hounslow NWL ICB and in consultation with the Lead Member for Adult Social Care, Public Health and Health Integration, to set the final service configuration and award the contracts within the approved budget.
Why
The service helps the council meet its assessed care and support duties under the Care Act 2014 and supports the strategy of helping residents stay in their own homes, which is more cost effective than residential or nursing care. Report 7.4, 6.5, 11.4
The contract value exceeds £1m, so under the Contract Procedure Rules it is a key decision requiring competitive tendering and Cabinet approval to commence the procurement. Report 7.3, 14.1
The current contract is ending and a longer-term arrangement is needed to give providers confidence to invest in quality and integration, while maintaining London Living Wage and a 30-minute minimum payment to carers. Report 11.1, 11.2
What happens next
Provider engagement events run between February and April 2026, with Health Watch service user consultation in early 2026 to help shape the final specification. Report 12.2
A two-stage procurement follows: planned procurement notice 21/04/2026 to 22/04/2026, ITT published 01/06/2026, evaluation through to mid August 2026, and a full business case at Gateway 5 in early September 2026. Report P36, P38, P40, P41
Award letters issue on 26/09/2026 after a standstill period, with mobilisation from 28/09/2026 to 31/10/2026 and the new service starting on 01/11/2026. Report P43, P44, P45, P46
The money
£15m Approximate annual net budget for homecare Report 6.3
£120m Total estimated eight-year contract budget
£24.8m Estimated gross annual homecare cost in current financial year Report 6.3
£198.4m Estimated gross spend over the eight-year contract term Report 6.3
approx. £3k per new provider One-off CM2000 implementation cost for newly commissioned providers Report 6.2, 13.4
approx. 4% Anticipated annual growth in homecare demand over contract life Report 6.3, 6.4
c.5% pa Estimated hourly rate inflation assumption Report 6.3, 6.4
£975 Average weekly cost difference between homecare and nursing in 2024/25, around £1,200 now Report 6.5
£175k Extra cost per person on average if moved directly to nursing instead of supported at home for 3.5 years Report 6.5
Options considered
Chosen: Retender adult homecare through a competitive two-stage procurement with up to 12 providers, five-year contract plus three-year extension. Meets Care Act duties, supports living at home strategy, and gives providers investment certainty while keeping LLW and minimum payment conditions Report 8.1, 11.1, 11.2
Implications
Financial: Homecare is funded from the Better Care Fund, client contributions and the General Fund; Integrated Care Board restructuring may risk the grant allocation and will need close monitoring. Report 13.3
Financial: London Living Wage uplifts and inflation of about 5% per year, plus demand growth of about 4% per year, will increase contract costs and must be provided for at annual budget setting. Report 6.4, 13.2
Financial: Self-funded client numbers are rising, making timely collection of client contributions more important. Report 13.3
Legal: The contract is a Light Touch service under the Procurement Act 2023 and must follow competitive tendering procedures and the public benefit objectives in section 12 of that Act. Report 7.1, 7.2
Legal: HB Public Law will provide legal support on the procurement and final contract. Report 7.5
Equalities: Up to 12 providers will be commissioned to offer choice reflecting diverse needs; EDI impact will be monitored and Equalities Impact Assessments reviewed during design and when new requirements arise. Report 8.1, 8.3
Climate: Providers must set out an environmental sustainability plan towards carbon neutrality by 2030, support recycling and energy efficiency, minimise staff travel, and promote local recruitment and sustainable travel. Report 9.1, 9.2, 9.3, 9.4
Staffing: The contract will require payment of the London Living Wage to carers and a 30-minute minimum payment, with monthly contract meetings to enforce these conditions. Report 6.4, 11.2
Risk: Continuing growth in Adult Social Care demand is a local and national risk and contributes to the budget gap in the One Hounslow Financial Strategy; demand will need regular monitoring under the new contract. Report 13.1
Who and where
Adults aged 18 and over in Hounslow assessed as needing homecare and their families Report 8.1
Homecare providers, including newly commissioned providers who will need to implement the CM2000 system Report 6.2, 8.1
Homecare carers, who will continue to be paid at London Living Wage with a 30-minute minimum payment Report 11.2
Health partners, working through a Place Based approach with the council Report 8.2
Joint Commissioning and Adult Social Care staff, who will run the project as business as usual Report 6.1, 12.1
Timeline
31/12/2025 to 20/04/2026: Develop specification and tender pack Report P35
15/01/2026 to 20/01/2026: Project considered at CLT Report P32
29/01/2026 to 10/02/2026: Obtain Cabinet decision Report P33
10/02/2026 to 20/04/2026: Pre-market engagement with providers Report P34
21/04/2026 to 22/04/2026: Planned procurement notice issued Report P36
20/05/2026 to 28/05/2026: ITT approval at Category Board (Gateway 4) Report P37
01/06/2026 to 01/07/2026: Publish Invitation to Tender Report P38
01/07/2026 to 20/08/2026: Evaluate ITT responses Report P38
21/08/2026 to 31/08/2026: Moderation of tender evaluations Report P39
01/09/2026 to 08/09/2026: Complete full business case for Gateway 5 Report P40
08/09/2026 to 15/09/2026: Award approval at SCPB (Gateway 5) Report P41
15/09/2026 to 16/09/2026: Delegated approval Report P42
16/09/2026 to 26/09/2026: Standstill period Report P43
26/09/2026 to 27/09/2026: Award letters issued Report P44
28/09/2026 to 31/10/2026: Mobilisation of new providers Report P45
01/11/2026: New homecare service start day Report P46
Plain English for the jargon
Light Touch (LT) service: A category of service under the Procurement Act 2023, section 9, that is subject to the procurement regime but with more flexibility and exemptions than full contracts.
ECM (Electronic Call Monitoring): A system used to record care visits; CM2000 is the current mandated system in Hounslow, supporting accurate billing and safeguarding evidence.
LLW (London Living Wage): An hourly pay rate set by the Living Wage Foundation, above the national minimum wage, which the homecare contract will require providers to pay carers.
BCF (Better Care Fund): A pooled budget, including the Improved Better Care Fund grant, that funds integrated health and social care services such as homecare.
POC (Packages of Care): The commissioned care arrangements for individual service users, reviewed through monthly contract meetings to ensure correct delivery and billing.
KPI: Key Performance Indicators, monitored using ECM data to check care quality and flag early signs of provider failure or poor practice.
SCPB: Strategic Commissioning and Procurement Board, the council body giving Gateway 5 award approval.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
Resolved : · Cabinet agreed to give authority to officers to commence procurement for the retendering of Adults homecare with an annual net budget of approx. £15m per annum and total estimated eight-year budget of £120m over a contract term of five years with the option to extend by three years (excluding growth and inflation). · Cabinet delegated authority to the Director of Commissioning/ Borough Director Hounslow NWL ICB in consultation with the Lead Member for Adult Social Care, Public Health and Health Integration to: o a) Agree the final configuration of services to be procured in accordance with the Contract Procedure Rules; and b) Take all necessary steps to negotiate, agree the terms of and award the contracts within the approved budget envelope to the successful bidders, including entering into any associated contractual legal documentation.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Implementation Date 19th February 2026 (if not Called In)
Affected Wards (All Wards);
Approved by Martin Waddington 1. Recommendations
Cabinet is asked to:
1. Give authority to officers to commence procurement for the retendering of Adults homecare with an annual net budget of approx. £15m per annum and total estimated eight-year budget of £120m over a contract term of five years with the option to extend by three years (excluding growth and inflation). 2. Delegate authority to the Director of Commissioning/Borough Director Hounslow NWL ICB in consultation with the Lead Member for Adult Social Care, Public Health and Health Integration to: a) Agree the final configuration of services to be procured in accordance with the Contract Procedure Rules; and b) Take all necessary steps to negotiate, agree the terms of and award the contracts within the approved budget envelope to the successful bidders, including entering into any associated contractual legal documentation.
2. Report Summary
2.1Adults Home Care, also called domiciliary care, refers to a range of support services provided to adults 18+ within their own homes. These services are in place to address the assessed needs of individuals and include personal care, domestic and shopping support and medications support. The service supports the individual’s wellbeing while enabling them to remain within their home.
2.2Currently, Adults Homecare is procured through a group of contracted homecare providers operating under the Hounslow Homecare contract terms and conditions. These contracts are due to expire on 31st October 2026, and a re- procurement of this statutory service is required.
2.3Following an evaluation of all procurement options the recommended option is to re-tender for 12 homecare providers to operate under the same T&Cs, receive a flat hourly rate set by the Local Authority, provide a service covering the full borough and supporting ICB requirements such as an out of hours service and medication support level 2. Contracts to commence 1st November 2026 for a period of 8 years (5 years with an option to extend a further 3).
2.4Current spend on Adults homecare is £24.8m, net of BCF funding and client contributions this is approx. £15m from the General Fund. The hourly rate paid to providers is expected to increase over the duration of the contract in line with changes to London Living Wage and inflationary pressures over the contract duration. The volume of care provided within the borough is expected to increase year on year due to an increasing population and an aging population. Although this procurement will not yield cost savings the service is a cost- effective solution when compared to other alternatives such as residential care. 3. Background and links to Corporate Priorities
3.1Adults’ homecare services are in place to address the specific needs of adults 18+ with noncomplex conditions, aiming to enhance their quality of life and promote their wellbeing while enabling them to remain within their own homes, reducing or delaying the need for higher cost residential placements.
3.2In order to provide this statutory service and deliver a robust, good quality care provision as set out in the Care Act 2014, the Local Authority has commissioned and utilises 10 providers to deliver the homecare service in the Hounslow Homecare contract 2018-2026. This contract expires 31st October 2026 and this report sets out the proposed route to market to procure the replacement of this contract.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Delivery Plan Monitoring - Q4 2025/26Resolved : Cabinet agreed to: 1. Note progress to date with the programmes within the People Portfolio as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.