Agreed to release the relevant funding for the following schemes and projects within the Council’s MTP:- ¨ Car Parks: Environmental Improvements Phase 5; ¨ AJC Small Scale Schemes: District Wide; ¨ Local Transport Plan 2004/05; ¨ Safe Cycle Routes: Creation of new routes to schools; ¨ St Neots Transport Strategy; ¨ Huntingdon Transport Strategy; ¨ Views Common: Cycle Route; ¨ Huntingdon Town Centre Environmental Improvements Phase 2; ¨ Oxmoor Environmental Schemes; ¨ Huntingdon town centre development; ¨ Market town centre developments; ¨ Heart of Oxmoor; ¨ Safe cycle storage racks; ¨ Rural bus stop provision; ¨ Railway stations: improvements; ¨ Accessibility Improvements/signage; ¨ Leisure Centres: future maintenance; ¨ Sawtry Leisure Centre: Extension to facilities; ¨ Ramsey Leisure Centre: fitness studio expansion; ¨ Ramsey Leisure Centre: crèche/storage/office extension; ¨ Additional Council Tax Clerk; ¨ Discretionary repair grants; ¨ Disabled facilities grants; ¨ Fenstanton car park:Church Lane; and ¨ Customer First: contact centre. Agreed also to release funding for Crime and Disorder – lighting improvements; and Bus shelters – extra provision subject to the Executive Councillors for the Environment and for Resources & Welfare and Information Technology being advised of the sites identified Approved the funding for the additional homelessness officer subject to the appointment being for a trial period of 2 years Requested the Corporate Director, Commerce and Technology to report to a future meeting on the progress being made to produce a corporate contract for the future maintenance needs of the District’s Leisure Centres; and Requested a presentation by the Director of Operational Services and the Corporate Director, Commerce and Technology to a future meeting on the staffing/establishment arrangements for the Customer First Contact Centre.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
2.1The Council considered the draft budget and MTP report at its December meeting and agreed that, having regard to the implications for future spending and Council Tax levels, Directors review with appropriate Executive Councillors the need for schemes/projects included in the MTP but not yet started and that specific prior approval be sought and obtained from the Cabinet before such schemes/projects are implemented.
2.2Officers have considered which schemes have wholly or partly started with reference to the following definitions:
STARTED • The staff have been appointed and/or a legally binding contract is in place for all aspects. • Some of the staff have been appointed or a legally binding contract is in place for part of the scheme and there is no sensible option to avoid or defer those elements that are not yet legally committed. • The scheme is based on a partnership and all constituent projects have been agreed with those partners and they have reserved funding for them in the current year.
PARTIAL START • Some of the staff have been appointed or a legally binding contract is in place for part of the expenditure and there is a practical cost- effective option to not carry out the full scheme at this time. • The scheme is based on a partnership and some individual projects have been agreed with those partners and they have reserved funding for them in the current year.
2.3Officers have subsequently identified which schemes that they wish Cabinet to consider releasing further funding for and have discussed them with the relevant Executive Councillor.
2.4Annex A summarises and Annexes B to AC detail the schemes where release of funds is now requested. There are also schemes where subsidiary detailed approval is proposed or required. 3. RECOMMENDATION
3.1The Cabinet is recommended to release the funds shown in Annex A.
ACCESS TO INFORMATION ACT 1985 None
Contact Officer: Steve Couper Head of Financial Services 01480 388103 ANNEX A SUMMARY Net Revenue Impact £000 Net Capital £000 2003/ 2004/ 2005/ 2006/ 2007/ 2008/ 2003/ 2004/ 2005/ 2006/ 2007/ 2008/ Annex 2004 2005 2006 2007 2008 2009 2004 2005 2006 2007 2008 2009 B Car Parks – Environmental Improvements 1 2 3 3 3 3 20 31 Phase 5 C AJC Small Scale Schemes – District Wide 2 5 5 5 5 103 D Local Transport Plan 2004/05 2 5 5 5 5 94 E Safe Cycle Routes – creation of new routes to 2 5 5 5 5 105 schools F St Neots Transport Strategy 2 4 4 4 4 72 G Huntingdon Transport Strategy 1 3 3 3 3 70 H Views Common – Cycle Route 2 3 3 3 3 50 I Huntingdon Town Centre Environmental 1 2 2 2 2 30 Improvements Phase 2 J Oxmoor Environmental Schemes 2 5 5 5 5 100 K Huntingdon Town Centre Development 1 2 2 2 2 50 L Town Centre Developments 2 3 3 3 3 62 M Heart of Oxmoor 6 13 13 13 13 250 N Crime and Disorder - Lighting Improvements 1 1 1 1 1 21 O Safe Cycle Storage Racks 1 1 1 1 1 15 P Bus Shelters – extra provision 2 3 3 3 3 33 Q Rural Bus Stop Provision 1 6 6 6 6 25 R Railway Stations – Improvements – Partnership 1 1 1 1 15 with Rail S Accessibility Improvements / Signage 2 3 3 3 3 60 T Homelessness Officer 34 31 31 31 31 U Leisure Centres - Future Maintenance 20 40 40 40 40 803 V Sawtry LC - Extension to Facilities 2 11 29 12 4 4 46 444 W Ramsey LC - Impressions Expansion 2 -11 -11 -11 -11 100 X Ramsey LC - Creche/Storage/Office Extension 12 -3 -3 -3 -3 100 Y Council Tax Clerk – growth in number of 14 houses Z Discretionary repair grants 6 12 12 12 12 247 AA Disabled Facilities Grants 3 6 6 6 6 126 AB Fenstanton Car Park 2 3 3 3 3 22 AC Customer First 8 36 72 85 85 85 402 Total amount for which release now 11 172 247 243 235 235 66 3,430 requested ANNEX B
014 Car Parks – Environmental Improvements Phase 5 Chris Allen – Project and Assets Manager
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.