Resolved
Noted the contents of the Hilton Standard of Protection and agreed not to carry out any further investigation work into raising the level of flood protection.
Cabinet noted this item on Thursday 4 March 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Noted the contents of the Hilton Standard of Protection and agreed not to carry out any further investigation work into raising the level of flood protection.
CABINET 4 MARCH 2004
WATERCOURSES – STANDARD OF PROTECTION STUDIES GENERAL AND HILTON (Report by Head of Environment & Transport and Head of Planning Services)
1. INTRODUCTION
1.1Following the floods in the District in 1998, various studies have been initiated by the Environment Agency on their Main Rivers. These are called Standard of Protection Studies and are pre-feasibility studies to look at the frequency that flooding is likely to affect properties.
1.2The District Council has permissive land drainage powers on non-Main rivers and has maintenance responsibilities on its riparian watercourses and its Awarded Watercourses. A joint study was commissioned by the Environment Agency and this Council for the Hilton catchment following the flooding in October 2001.
1.3The Council has also engaged consultants, Mott MacDonald, to carry out an overarching Strategic Flood Risk Assessment (SFRA) for the district. This assessment will identify areas that are at risk of flooding(in a more accurate manner than the existing indicative flood plain maps), and detail these factors that are relevant to current and future flood risks. This is a requirement for, and will inform the emerging Local Development Document that will replace the Local Plan.
1.4Also included in the consultants brief is for them to assess the Standard of Protection on HDC watercourses and key locations.
2. PROGRESS TO DATE:
2.1The Environment Agency has produced studies for:
Alconbury & - SoP complete and detailed appraisal now Alconbury Weston being undertaken.
Ellington Brook - SoP complete and design work is progressing on minor bank improvements.
River Great Ouse - Hydraulic Model produced for Earith to St Neots. Standard of Protection Study being carried out.
West Brook/Hall Green - SoP report complete – shows several Brook, Fenstanton houses at risk from under 1 in 25 year floods. Detailed appraisal being undertaken.
Parsons Drove, - SoP report nearing completion. St Ives 2.2 The Hilton Standard of Protection report has now been received from the consultants.
2.3The Stage 1 of the Strategic Flood Risk Assessment has been received from Mott MacDonald.
3. HILTON STANDARD OF PROTECTION REPORT
3.1Hilton was affected by flooding due to the heavy storms of October 2001. There were eight houses flooded due to this storm. These were not flooded in the 1998 floods and there is no record of these flooding on other occasions in the recent past.
3.2The flood event in October 2001 at the West Brook at Hilton has been estimated at a 1 in 100 year return period.
3.3It is estimated that the Standard of Protection offered to Hilton is judged to be in excess of 25 years and towards 1 in 100 years and only a small number of properties are at risk. Therefore the benefits of any improvements would be low and it would be highly unlikely that works could be justified under DEFRA grant aided criteria.
3.4The DEFRA guidelines placed Hilton in land use band B, based on the number of indicative housing units at risk of flooding, and this infers an indicative standard for flood defence of 1 in 25 to 100 years.
3.5The report considered what improvements could be carried out.
1) The watercourse upstream of Graveley Way could have the right bank raised by depositing dredgings on it. This would only work in low return period events of up to 1 in 10 year events and therefore not be very effective. A more substantial engineered embankment would be required to provide protection against more severe flood events. This would not be cost effective and may cause local problems to the farmers in draining their land in normal conditions.
2) The Environment Agency maintain West Brook downstream of Hilton already. No improvements were identified to this watercourse but it is important to ensure that regular maintenance continues.
4. STRATEGIC FLOOD RISK ASSESSMENT
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Water Courses: Standard of Protection Studies General and HiltonReport | 18 KB | DownloadRead as text |
Follow Cabinet at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... | Noted | Open |
| 17 Nov 2026 | Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... | Deferred | Open |
| 17 Nov 2026 | Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... | Approved | Open |
| 17 Nov 2026 | Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... | Approved | Open |
| 17 Nov 2026 | Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.