Cabinet, Thursday 15 July 2004 at 11.30am

Medium Term Plans - Requests for Release of Funds

Decided Executive 1 paper

Cabinet decided this item on Thursday 15 July 2004. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

The relevant funding is released for the concessionary fares study scheme with the Council’s MTP and for the CCTV – Camera Replacement Scheme subject to the Chairman and Executive Councillor for Public Health and Safety being satisfied as to the content of the report referred to in the report.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Cabinet

Background

2.1The Council considered the draft budget and MTP report at its December meeting and agreed that, having regard to the implications for future spending and Council Tax levels, Directors review with appropriate Executive Councillors the need for schemes/projects included in the MTP but not yet started and that specific prior approval be sought and obtained from the Cabinet before such schemes/projects are implemented.

2.2Officers have considered which schemes have wholly or partly started with reference to the following definitions:

STARTED • The staff have been appointed and/or a legally binding contract is in place for all aspects. • Some of the staff have been appointed or a legally binding contract is in place for part of the scheme and there is no sensible option to avoid or defer those elements that are not yet legally committed. • The scheme is based on a partnership and all constituent projects have been agreed with those partners and they have reserved funding for them in the current year.

PARTIAL START • Some of the staff have been appointed or a legally binding contract is in place for part of the expenditure and there is a practical cost- effective option to not carry out the full scheme at this time. • The scheme is based on a partnership and some individual projects have been agreed with those partners and they have reserved funding for them in the current year.

2.3Officers have subsequently identified which schemes that they wish Cabinet to consider releasing further funding for and have discussed them with the relevant Executive Councillor.

2.4Annex A summarises and Annexes B and C detail the schemes where release of funds is now requested. 3. RECOMMENDATION

3.1The Cabinet is recommended to release the funds shown in Annex A.

ACCESS TO INFORMATION ACT 1985 None

Contact Officer: Steve Couper Head of Financial Services 01480 388103 ANNEX A

SUMMARY Net Revenue Impact £000 Net Capital £000 2003/ 2004/ 2005/ 2006/ 2007/ 2008/ 2003/ 2004/ 2005/ 2006/ 2007/ 2008/ Annex 2004 2005 2006 2007 2008 2009 2004 2005 2006 2007 2008 2009 B Concessionary Fares Study 15 C CCTV _ Camera replacements 148 Total amount for which release now 163 requested ANNEX B

03/399 Concessionary Fares Study Stuart Bell – Transportation Officer

Financial Impact Net Revenue Impact Net Capital 2003/ 2004/ 2005/ 2006/ 2007/ 2008/ 2003/ 2004/ 2005/ 2006/ 2007/ 2008/ 2004 2005 2006 2007 2008 2009 2004 2005 2006 2007 2008 2009 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 Approved Budget 15 Already Committed Amount for 15 which release now requested

Justification The Executive Councillor with responsibility for Planning Strategy has requested that this study now take place. The bid will fund a study to review the options available to the council for supporting the use of public transport, including taxis, to enable groups who are disadvantaged by location etc. to gain access to employment, leisure and other essential services.

Early approval is therefore required so that the work can be carried out . ANNEX :C

20, 460 CCTV _ Camera replacements Sonia Hansen / Chris Allen

Financial Impact Net Revenue Impact Net Capital 2003/ 2004/ 2005/ 2006/ 2007/ 2008/ 2003/ 2004/ 2005/ 2006/ 2007/ 2008/ 2004 2005 2006 2007 2008 2009 2004 2005 2006 2007 2008 2009 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 Approved Budget 74 74 74 74 74 84 Already 0 0 0 0 0 0 Committed Amount for 148 0 0 0 0 which release now requested

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Medium Term Plans: Requests for Release of FundsPlan 27 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
IC
Councillor Ian Cyril BatesMember, present
MJ
Councillor Mrs Jean ChandlerMember, present
RL
Councillor Robert Leonard ClarkeMember, apologies
NG
Councillor Nick GuyattMember, present
DP
Councillor Derek Peter Holley, OBEMember, present
MP
Councillor Mrs Paula Jayne LongfordMember, present
MD
Councillor Mrs Deborah Christine ReynoldsMember, present
TV
Councillor Terence Victor RogersMember, present
LM
Councillor Lawrence Michael Simpson(known as Mike)Member, present

On this subject at Huntingdonshire

Search all
  1. Medium Term Plans - Requests for Release of FundsThis decision
  2. 2025/26 Revenue Budget & Medium Term Financial Strategy (2026/27 to 2029/30); including the Capital ProgrammeApproved
  3. Final 2025/26 budget and medium-term financial strategy (2026/27 to 2029/30) including the capital programmeApproved
  4. 2025/26 revenue budget and medium term financial strategy (2026/27 to 2029/30) including the capital programmeDecided
  5. Final 2024/25 budget and medium-term financial strategy (2025/26 to 2028/29) including capital programmeApproved
  6. Final 2023/24 revenue budget & medium-term financial strategy (2024/25 to 2027/28); including the capital programmeApproved

More from Huntingdonshire Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... Noted Open
17 Nov 2026 Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... Deferred Open
17 Nov 2026 Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... Approved Open
17 Nov 2026 Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... Approved Open
17 Nov 2026 Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies