Approved a supplementary capital estimate of £60,000 to cover the capital cost of replacement cables. An additional £20,000 from the revenue contingency also has been approved to cover the cost of works already carried out, to provide temporary power supplies and to identify the source of the fault.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
1.1To advise Cabinet of the failure of the electricity supply to the mobile home site, the steps taken to rectify the problem, and to seek approval of a supplementary capital estimate and the expenditure of revenue contingency for the necessary urgent replacement works.
2. BACKGROUND INFORMATION
2.1The mobile home site in St Neots is owned by the Council and managed by HHP under a management agreement. Residents on the site own their mobile home and pay a ground rent for the pitch. There are 50 pitches on the site.
2.2The utility company provides electricity to a meter on the site and supplies are provided to each mobile home through cables owned by the Council.
2.3On 31 August the electricity supply to some of the mobile homes failed. HHP arranged for an emergency inspection by the utility company who confirmed that the problem lie within the Council’s cables and not with the supply to the their meter.
2.4As power could not be restored immediately, two generators were brought in to restore temporary power to each mobile home. In the following days, contractors were used to identify and rectify the fault. As the cause of the fault could not be identified, and to limit escalating costs, a quotation for the replacement of the cables has been sought.
3. IMPLICATIONS
3.1The estimated capital costs for replacement of the cables and for HHP to manage the project are £60k.
3.2The estimated revenue cost to cover works already carried out to provide temporary power supplies together with aborted attempts to identify the fault plus continuing to provide generators until the works are completed is £20k.
4. CONCLUSIONS
4.1The cause of the fault could not be cost effectively identified and the cables supplying electricity therefore have to be replaced. Temporary power is being supplied to each mobile home during this period and residents are being kept informed of progress. 5. RECOMMENDATION
It is recommended that Cabinet:
a) agree a supplementary capital estimate of £60,000 to enable the renewal of the electricity cables, and
b) approve £20,000 expenditure from the revenue contingency.
BACKGROUND INFORMATION
Contact Officer: Steve Plant, Head of Housing (01480) 388240
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.