Resolved
Noted the capital outturn for 2003/04 Approved the additional capital spending of £135,000 Noted the position on individual schemes
Cabinet noted this item on Thursday 23 September 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Noted the capital outturn for 2003/04 Approved the additional capital spending of £135,000 Noted the position on individual schemes
CABINET 23 SEPTEMBER 2004
MONITORING OF THE CAPITAL PROGRAMME 2003/04 and 2004/05 (Report by the Head of Financial Services)
1. PURPOSE
1.1This report outlines the outturn position for 2003/04 and the implications for 2004/05. Progress during the current year is also considered and proposals are made for necessary cost variations.
1.2More detailed information on specific schemes can be obtained from the relevant Head of Service.
2. 2003/04 OUTTURN
2.1The final budget position for 2003/04 is built up as follows :-
Gross External Net Contribs. £000 £000 £000 Capital Budget Approved February 2004 9,712 1,219 8,493 Additional Revenue salaries charged to capital 91 91 Ramsey Roof Funded from R&R Fund 267 267 Country Parks Tractor transfer from revenue 19 19 Additional items funded from external contributions 1,341 1,341 0 Schemes deferred from previous years 266 266 Supplementary approval - Henbrook 48 48 Adjusted Total 11,744 2,560 9,184
Revenue Adjustments Savings • Salaries recharged to Capital -91 -91 • Country Parks Tractor -19 -19 Use of R&R Fund -267 -267
2.2Gross Capital expenditure in 2003/04 amounted to £8,400k compared to an adjusted budget total of £11,744k, as shown below:
Gross External Net Contribn s £000 £000 £000
Capital Budget (as adjusted above) 11,744 2,560 9,184 Actual Capital Spending 8,400 2,560 5,840 Variation -3,344 - -3,344
Reasons for variation Net Project delays/deferrals to 2004/05 --3,038 -3,038 Previously reported savings (May Cabinet) -341 -341 Additional costs (see para. 2.3 below) 135 135 Inflation Allowance (not allocated) -100 -100 2.3 The table below shows the breakdown of the additional scheme costs now reported:-
£000 St Ives Town Centre – Environmental Improvement – This increase 27 is due to extra work needed to complete the scheme and claims from the contractor. There are further outstanding claims with the contractor, which are still being disputed, so this may not be the final figure. CCTV – Extra Cameras New Areas – The extra cost of necessary 21 upgrading of the Control Room to allow for the new cameras to be accommodated has resulted in this overspend. CCTV – Vehicle Mounted Unit – The vehicle has not cost as much as -18 budgeted. Hinchingbrooke Country Park – Phase 2 – This project was reported 15 as an underspend in 2002/03 (-£13k), in error, as the final payment of £15k had not been included. St Ivo Leisure Centre – Fitness Equipment – Replacement of 14 previously leased equipment. Revenue budget will be reduced to meet this cost over three years. Pathfinder House – Lift Upgrade – Contract was finalised with a cost -11 saving Disabled Facilities Grants – Cabinet approved the principle of 90 increasing spending in 2003/04 to maximise the amount eligible for 60% grant before the grant level became cash limited from April 2004. (Gross Cost £225k) Other Minor Savings -3 TOTAL EXTRA COST 135
2.4The net revenue impact of the extra costs will be £6k in 2004/05 and future years. In 2004/05 this will be more than compensated for by the delayed/deferred expenditure.
2.5The additional external contributions were:
£000 New Acorn Oxmoor Project – Grants from ODPM 968 St Neots Leisure Centre Car Park – Work carried out on behalf of the 202 school Disabled Facilities Grants – Extra grant (see above) 126 Contributions towards IT projects – work on behalf of other local 45 authorities TOTAL EXTRA CONTRIBUTIONS/INCOME 1,341
3. MONITORING OF THE 2004/05 PROGRAMME
3.1The approved 2004/05 Gross Capital programme of £15,344k, has been increased by £3,038k, as a result of work being carried over from 2003/04, by £288k through subsequently approved supplementary bids (Kent Road £243k and Server Room £45k) and £147k transfered from revenue resulting in a total of £18,817k. Annex A below shows the individual schemes position with comments from the Project Managers.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MONITORING OF THE CAPITAL PROGRAMME 2003/04 AND 2004/05Report | 63 KB | DownloadRead as text |
Follow Cabinet at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... | Noted | Open |
| 17 Nov 2026 | Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... | Deferred | Open |
| 17 Nov 2026 | Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... | Approved | Open |
| 17 Nov 2026 | Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... | Approved | Open |
| 17 Nov 2026 | Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.