It was agreed to publish a contract notice in the Official Journal of the European Communities and place an advertisement in the Estates Gazette seeking expressions of interest from suitably qualified developers to procure a new headquarters building and other accommodation. The Chief Executive, after consultation with the Leader of the Council, was authorised to determine a list of not more than six tenderers from the responses to the initial contract notice. The requirement for the Cabinet to approve the output specifications for the new buildings/premises before tenders are issued in June 2005 was noted. The Chief Executive, after consultation with the Leader of the Council, was authorised to develop and approve detailed tender evaluation criteria having regard to the issues listed at paragraph 2.5 to the report submitted. The Chief Executive was authorised to obtain independent valuations of the Pathfinder House/Castle Hill Site and of the Godmanchester Depot site such that realisable values can be used in the tender evaluation exercise. The Chief Executive, after consultation with the Leader of the Council, was authorised to complete an initial evaluation of tenders received and report thereon to the meeting of the Council on 28th September 2005. The intention to submit a request to the September meeting of the Council to take a decision on the project based on an initial evaluation of tenders received was noted. The Chief Executive was authorised to enter post-tender clarifications with two or more tenderers leading to the submission of best and final Officers.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
HEADQUARTERS AND OTHER ACCOMMODATION PROCUREMENT (Report by Head of Environment & Transport)
1. INTRODUCTION
1.1Cabinet at their meeting on 17 March 2005 authorised further investigation to refine the options for the District Council’s replacement headquarters and depot and the provision of a new customer service centre to be based in Huntingdon.
1.2Cabinet also required that further consideration be given to an edge- of-town-centre or edge of town option and that the cost of preferred options be tested competitively.
1.3This report proposes an approach to competition which will satisfy European Union procurement regulations and enable the range of options to be considered and then reduced, based on tenders received. This will allow the meeting of Council on 28 September 2005 to determine if procurement is to proceed and, subject to the decision of Council, negotiations to be completed and a tender accepted before the end of 2005.
2. PROPOSED PROCUREMENT ARRANGEMENTS
2.1The European Union restricted procedure will be used with an initial ‘contract notice’ being placed in the Official Journal of the European Communities on 14 April 2005. This will invite expressions of interest from prospective developers who are interested in tendering for the project. Concurrently an advert will be placed in the Estates Gazette to satisfy the District Council’s Code of Procurement. The text of the proposed advert is reproduced at Annex A.
2.2Following receipt of the expressions of interest the Chief Executive, following consultation with the Leader of the Council will select the prospective tenderers based on their financial, legal and technical capacity and their recent performance in delivering similar projects for other clients.
2.3The level of interest will depend on developers’ ability to identify potential sites and to secure agreement with land owners. It will be helped by the availability of the existing Pathfinder House site. To comply with the District Council’s Code of Procurement a minimum of three potential bidders are required. However, if there is strong interest from suitably qualified developers it is proposed that not more than six tenderers be selected.
2.4It is anticipated that the District Council will be in a position to issue the invitation to selected tenderers by 15 June 2005. The District Council’s consultants are further developing the performance specifications for the new buildings/premises and these will form the basis of the tender documentation. Cabinet will be requested to give their final approval of the specifications prior to their issue as part of the tender documents. 2.5 Tenders will be invited on a design and build basis and will be evaluated against criteria to be developed in respect of the following –
1. Overall cost to the District Council; 2. Confidence in final outturn cost at the time of contract award; 3. Compliance with District Council’s buildings/premises specifications; 4. Compliance with planning policy guidance with regard to site selection; 5. Impact on the location of new buildings and premises on the cost of operating District Council services; and 6. Ongoing operating cost of the new premises.
7. Huntingdon location for Offices and Customer Service Centre.
2.6Tenderers will be invited to propose arrangements for minimising cost uncertainty as part of their tender. Preference will be given to proposals that provide transparent arrangements for the costing and sharing of risks, underpinned by an agreed base price.
2.7Where a tenderer’s proposal results in the Pathfinder House/Castle Hill House site being redundant it is proposed that they may either –
a) opt to develop the site for residential use and then market the properties; or b) demolish Pathfinder House and leave the District Council to market the cleared site and Castle Hill House.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.