Agreed to release £749,000 of capital funding for the extension of facilities at Sawtry Leisure Centre and approved a transfer of £59,000 from the Leisure’s Capital Programme to fund a shortfall in the scheme and agreed to an additional supplementary capital estimate of £160,000 towards the cost of fitness equipment. Also noted a reduction in net revenue costs for the scheme over the next 8 years.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
1.1The original concept of increasing the leisure provision at Sawtry was made in 1998. Plans for expansion included a fitness studio, multi- purpose aerobics studio, crèche, new changing facilities, reception and car parking. To supplement Huntingdonshire District Council funds, a bid submission to Sport England for £206k, around 26% of the anticipated total cost, was subsequently made.
1.2Progress to the current day has been beset with problems. Issues regarding parking, planning and the failure of the original Lottery bid have all contributed to delays. Officers have submitted an enhanced Lottery bid, negotiated and renegotiated parking arrangements and addressed planning concerns, and the project is now ready to proceed.
1.3The programme came to tender stage in March 2005. Four tenders were returned with the lowest totalling £891k.
2 CURRENT POSITION
2.1Assuming Lottery acceptance – decision pending 12 July – the available funds leave a deficit of £54k on capital expenditure of £1,065k, a shortfall of 5%.
2.2In addition, it is proposed that we purchase the fitness equipment for the centre rather than lease it, as was assumed in the original MTP bid. This results in an additional capital requirement of £160k.
2.3However, as the attached Appendix shows, the overall revenue impact of the scheme compared to the current MTP funding is a cost reduction from 2006/7 onwards of an average of £10k p a over the next 8 years.
2.4Cabinet is also asked to note that expenditure to date on the project – fees to consultants / designers, planning etc – already total £60k, plus the significant officer time spent over the last four years in progressing it.
2.5The estimated time to complete the project will be 34 weeks from commencement. This does not include the creation of a hard play area for the College (to replace the one they will lose) which will take place in advance of any work. 3 CONCLUSION
3.1Completion of the proposed scheme will finalise the provision of core facilities at all the Leisure Centres and bring Sawtry into line with the other Centres in the District. Demand for this facility is high and, while there will inevitably be a shift of some custom from other Centres to Sawtry, such is the popularity of Impressions and Advantage membership that there is still expected to be a substantial overall increase in income.
3.2The Capital Monitoring Report elsewhere on the Agenda identifies savings on various schemes. The additional capital cost of £54k could be met from these savings.
Recommendations
4.1Cabinet are requested to:
a. approve a capital budget transfer of £54k from identified savings
b. a supplementary capital estimate of £160k for fitness equipment.
c. note the reduction in net revenue costs of the project.
d. approve the release of funds for MTP bid 262/B.
BACKGROUND INFORMATION
Click and insert background documents
Contact Officer: Simon Bell – Leisure Centres Co-ordinator 01480 388049
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.