noted the capital outturn for 2004/05 and the position with regard to individual schemes as set out in Annex A to the report and approved a supplementary estimate of £10,000 for the purchase of a new Ramsey and District Community Bus as outlined in paragraph 3.4.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
MONITORING OF THE CAPITAL PROGRAMME 2004/05 and 2005/06 (Report by the Head of Financial Services)
1. PURPOSE
1.1This report outlines the outturn position for 2004/05 and any variations already identified for the current year.
1.2Annex A provides information on individual schemes and more detailed information on specific schemes can be obtained from the relevant Head of Service.
2. 2004/05 OUTTURN
2.1The revised budget, as approved in February, has been amended as follows:
Gross External Net Cost Contributions Cost Capital £000 £000 £000 Approved (February 2005) 21,968 5,633 16,335 Additional Revenue items charged to capital • previous report 202 202 • additional staff time charged to capital 123 123 schemes Reduction in amount funded from external contributions -214 -214 0 Cabinet approved variations • Air Quality Monitoring Equipment and 89 89 Electricity Works at Mobile Home Park Final Total 22,168 5,419 16,749
Revenue Additional Revenue items charged to capital • previous report -202 -202 • additional staff time charged to capital -123 -123 schemes -325 -325
2.2Actual spending has varied from the budget for the following reasons:
Gross External Net Cost Contributions Cost £000 £000 £000 Capital Budget (as adjusted above) 22,168 5,419 16,749 Actual Spending 15,548 4,421 11,127 Variation -6,620 -998 -5,622
Reasons for variation Net Project delays/Deferrals to 2005/06 • previous report -4,934 -956 -3,978 • additional -826 -124 -702 Savings • previous report -909 -909 • this report (see para 2.3 below) 49 82 -33 2.3 The following net savings have been identified since the last report:
£000 Waste Collection and Recycling – further grant has been received -40 from the Government via the County Council Oxmoor, Kent Road Improvements – extra contributions received -29 from householders Ramsey Tourist Information Point – Grant received from the Greater -18 Cambridge Partnership Mobile Home Park, Electricity Works - saving -8 Huntingdon, Riverside – Bridge Replacements - Extra costs due to 14 high water affecting foundation construction on last bridge and increased costs in previous bridges. Leisure Fitness Equipment - Mainly due to extra costs of removing 13 old equipment (total budget £515k) St Neots, Riverside Car Park – Saving reported last year overlooked 8 retention still to be paid. St Ives Town Centre, Environmental Improvements – extra costs 8 Disabled Facilities Grants – Government Grant reduced 5 CCTV Vehicle – saving now only £5k (revised from previously reported 5 £10k) Hinchingbrooke Phase 2 – extra costs 5 St Ivo Leisure Centre – Sports Changing Rooms refurbishment – 4 extra costs
TOTAL ADDITIONAL NET SAVING -33
3. MONITORING OF THE 2005/06 PROGRAMME
3.1The approved 2005/06 Gross Capital programme of £27,658k has now been increased by £5,760k, as a result of work being delayed/deferred from 2004/05, by £632k for subsequently approved supplementary estimates and by £147k for transfers from revenue, resulting in a gross total of £34,197k.
3.2The following projects have been identified as needing to be deferred for another year:
£000 Pathfinder House Improvements/One Stop Shop 6,304 (£6M previously reported) St Neots Pedestrian Bridge Project 262 St Ives and Ramsey Transport Strategy Schemes 110 Football Improvements Project (part) 100 6,776
3.3It is also anticipated that £141k of the amount allocated for Housing Renovation and Repair Grants in 2005/06 will not now be required.
3.4Ramsey and District Community Bus wish to purchase a new vehicle and there are sufficient funds in the Transportation Grants revenue budget to provide a grant of £10k. As this is a Capital purchase it is necessary to transfer this sum from Revenue to Capital.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.