CABINET 11 January 2007 OVERVIEW AND SCRUTINY (SERVICE DELIVERY) 2 January 2007
SMALL SCALE ENVIRONMENTAL IMPROVEMENT SCHEMES 2007 (Report by Head of Technical Services)
1. PURPOSE
1.1This paper reports on the small scale environmental improvement schemes to be completed by March 2007 and proposes a programme of schemes for 2007/08.
2. SELECTION OF SCHEMES
2.1A net budget of £73k is included in the MTP in 2007/08 for “Small Scale Environmental Improvements”. To qualify for funding from this budget a scheme must also attract a minimum of 25% funding from an outside source, such as Parish or Town Council, or Landfill Tax Credit.
2.2Cabinet agreed the criteria for the prioritisation of the schemes in 2002/03 and this has been applied to the selection of schemes for 2007/08.
2.3Town and Parish Councils were asked in October to submit schemes for consideration in this coming year’s programme.
3. 2006/07 SCHEMES
3.1The schemes approved in the 2006/7 programme were as follows:
Description Position
Ramsey TC – Railings around Town Council withdrew scheme war memorial
Ramsey TC – Repairs to church wall Town Council withdrew scheme
St Ives TC – Improvements area of Negotiations still being carried out land to Bridge St
Holme PC – Repairs to church wall Complete
Warboys PC – Repairs to Jubilee Complete - Awaiting if further works Clock required
Catworth PCC – Church wall repairs Complete - Additional works approved 3.2 With the extra work being agreed on the existing schemes, the budget will be completely allocated. 4. 2007/08 Schemes
4.1A total of 38 submissions from Town and Parish Councils schemes were received by the agreed return date.
These were assessed using the scoring criteria (Annex 1) and the highest scoring schemes up to the approved budget (based on preliminary estimates) for 2007/08 are listed below:-
Net Gross Scheme £k £k 1 Somersham PC - Refurb. pedestrian crossing railings 1 2 2 Covington PC - Refurbish church gates 3 4 3 St Neots TC - Improvements to Montague Square 20 25 4 Brampton PC – Light obelisk 1.5 2 5 Godmanchester TC – Improvements to Church access 3 4 6 Alwalton PC – Improvements to gates 1.5 2 7 Waresley PC - Village pump improvements 1.5 2 8 Holywell PC - Repairs to church gates and drive 7.5 10 9 Kimbolton PC - New planters to war memorial 2.5 3 10 Gt Staughton PC - Cemetery lay-by 15 20 11 Holme PC - Church wall repairs 3 4 12 Ellington PC - Church wall repairs 4.5 6 13 Alconbury PC - Enhancement to village pump 6 8 14 Warboys PC – New bus shelter 3 4 Total 73 96
5. CONCLUSIONS
5.1The small scale environmental improvement funding has enabled minor improvements to be carried out in many villages and locations.
5.2There is great interest from town and parish councils in promoting future schemes and the appraisal process has now been shown to work satisfactorily.
5.3Approval is sought for those schemes which are shown in paragraph 4.1 above. In the event that these cannot proceed for any reason during 2007/08 the next schemes in the order of priority will be carried out. Annex 2 identifies the budget allocated for these schemes and includes the Release of Funds form. 6. RECOMMENDATION
6.1It is recommended that the Cabinet:
i) note the schemes committed/completed to date
ii) approves, for completion during 2007/08, the schemes at paragraph 4.1 above and releases the funds from the MTP to facilitate this.
BACKGROUND INFORMATION:
Technical Services Dept. File T7
Contact Officer: C J Allen, Project and Assets Manager (01480) 388380 Annex 1 Town/Parish Council Location Description Gross % Cont. Score Approved Notes Cost
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.