OVERVIEW AND SCRUTINY PANEL (SERVICE DELIVERY) 3RD JULY 2007
CABINET 19TH JULY 2007
REVIEW OF SMALL SCALE ENVIRONMENTAL IMPROVEMENTS GRANT SCHEME (Report by the Working Group)
1. INTRODUCTION
1.1The Overview and Scrutiny Panel at their meeting on 2nd January 2007 established a Working Group comprising Councillors [name removed], R W J Eaton, D A Giles, P G Mitchell and J S Watt to undertake a study into various aspects of the Council’s Small Scale Environmental Improvements grant scheme. Councillor Mrs Banerjee was elected Chairman of the Working Group.
1.2The Working Group was specifically tasked with examining the following:
• the purpose of the funding having regard to the Council’s corporate objectives and community aims contained in Growing Success; • arrangements for inviting town and parish councils to propose projects for funding; • the criteria for evaluating individual projects proposed for funding; • the extent to which the criteria should have regard, if any, to the size of the town or parish council promoting the project; • differential levels of financial contribution by the town or parish council promoting the project; and • the involvement of Members in the evaluation process
These are discussed in detail below.
2. WORKING GROUP ACTIVITIES
2.1The Working Group first met on 13th February 2007, when the Executive Councillors for Finance and for Planning Strategy, Environment and Transport outlined their concerns relating to the existing scheme, which had prompted them to suggest a review. These are addressed in the following paragraphs.
2.2The Working Group, at this meeting, discussed various aspects of the Scheme and its administration. Members, however, decided that their deliberations should be informed by practical experience of the Scheme in operation. Site visits were, therefore, held at 12 locations where applications for funding had been made for various scales of projects some of which were successful and some not. The visits took place on 2nd April 2007. The next section summarises the Working Group’s findings. 3. FINDINGS
(a) The Council’s Corporate Objectives and Community Aims
3.1The Working Group has been acquainted with the outcome of an exercise by Officers to link the Scheme's aims to the Council's corporate objectives and community aims. The relevant ones are A Clean, ‘Green’ and Attractive Place; Safe, Vibrant and Inclusive Communities; Access to Services and Transport and A Strong, Diverse Economy. Members have concluded that all the existing scoring criteria have links to the Council's Corporate Plan “Growing Success”.
(b) Arrangements for inviting Town and Parish Councils to Propose Projects for Funding
3.2The Working Group has identified a number of areas where improvements might be made to the bidding process. Although all clerks receive full details of the Scheme, its criteria and the bidding process, a frequent comment made by town and parish councillors is that they are unaware of it. It appears that the latter are not receiving this communication. In order to avoid such situations occurring in the future, the Working Group recommends that copies of the correspondence to clerks are sent to all Members, which will enable them to raise it at meetings and answer queries.
3.3The previous recommendation is aimed at raising public awareness of the Scheme. With this in mind the Working Group also recommends that details of all the Council’s grants schemes are published in a single location on the website in such a way that members of the public will be clear which scheme is the most appropriate for their purposes. This will increase awareness amongst the public and encourage individuals to raise schemes at parish level. A further recommendation intended to achieve this aim is that the timing of bidding processes for the funding schemes referred to in paragraph 3.5 (and 3.15) are harmonized in conjunction with the County Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.