Resolved
Noted the capital schemes monitoring report and spending variations and approved the use of virement to fund the sum of £63,000 for the Shop Mobility Scheme in Huntingdon.
Cabinet noted this item on Thursday 19 July 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Noted the capital schemes monitoring report and spending variations and approved the use of virement to fund the sum of £63,000 for the Shop Mobility Scheme in Huntingdon.
CABINET 19 JULY 2007
CAPITAL MONITORING 2006/07 OUTTURN and 2007/08 BUDGET (Report by the Head of Financial Services)
1. PURPOSE
1.1This report highlights the out-turn position for 2006/07, seeks approval to any adjustments required and adjusts the 2007/08 approved Capital Programme for deferrals. It also highlights any variations that are already forecast in the 2007/08 programme.
2. OUT-TURN 2006/07
2.1The Budget approved in February 2006 and subsequent adjustments are shown below:-
2006/07 Capital Expenditure Gross External Net Budget Contributions Budget £000 £000 £000 Approved Budget (February 2006) 20,389 5,924 14,465 MTP Variations -1,498 -1,719 221 Approved Medium Term Plan – February 2007 18,891 4,205 14,686
Forecast Variations in April Report -1,942 -2,949 1,007 Variations now identified -350 506 -856 Total Variations -2,292 -2,443 151 OUT-TURN 16,599 1,762 14,837 2.2 Annex B provides comments about individual schemes. If more information on specific schemes is required it can be obtained from the relevant Head of Service.
2.3As the outturn position results in a number of variations to the changes already forecast in April it is more meaningful to analyse the combined variations. These fall into the following categories and more information is provided at Annex A:
2006/07 Capital Expenditure Gross External Net Budget Contributions Budget £000 £000 £000 Changes in total cost of schemes -562 51 -613 Changes in scheme costs matched by changes in partner -6 -6 0 contributions Transfers from revenue to capital funding 187 0 187 Correction re 2005/06 capital receipt 0 -1,414 +1,414 Timing Changes -1,911 -1,074 -837 Total -2,292 -2,443 151 2.4 Within the figures in Annex A is the sum of £63k regarding the Shop Mobility Scheme in Huntingdon. This scheme was funded from the capital grants to voluntary organisations and the accessibility budget held by Technical Services
2.5The assumption included in the MTP review that there would be a further £1.5m of deferrals from 2006/07 to 2007/08 identified between the autumn and the end of the year masks the fact that the total deferrals in this period amounted to £2.3m (Annex A).
3 MONITORING OF THE 2007/08 PROGRAMME 2007/08 Capital Expenditure Gross External Net Budget Contributions Budget £000 £000 £000 Approved Capital Programme (February 2007) 20,202 4,924 15,278 Add deferrals from 2006/07 (in addition to £1.5m provision 1,911 1,074 837 included in MTP) 22,113 5,998 16,115 Forecast Variations Disabled Facilities Grants – forecast saving (Para 3.2) -453 87 -540 Non-reclaimable VAT – forecast saving -214 0 -214 Net Variations -667 87 -754 Current Forecast 21,446 6,085 15,361
Forecast Deferrals Provision included in MTP 1,000 0 1,000 Social Housing Grant – forecast revision to programme -563 0 -563 Remaining provision 437 0 437
3.1The approved programme requires adjustment as follows:
3.2The Government has now increased the amount the Council will receive in Grant for Disabled Facilities by £87k. It is also estimated that the spend on Grants in the year will be £453k lower as a result of the PCT’s continued recruitment and retention problems with Occupational Therapists.
3.3At the start of each year the Social Housing Grant programme is reviewed to reflect latest knowledge on individual schemes. As a result it is expected that £563k will not be required until 2008/09. This needs to be set against the general provision for deferrals of £1m included in the MTP £513k of this has been allowed for in the MTP.
4 REVENUE IMPLICATIONS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPTIAL MONITORING: 2006/07 OUTTURN AND 2007/08 BUDGETReport | 119 KB | DownloadRead as text |
PDF |
Draft Capital Monitoring Report 19 Jul 2007 annexAppendix | 29 KB | Download |
PDF |
draftJuly 2007 cabinet annexAppendix | 131 KB | Download |
Follow Cabinet at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... | Noted | Open |
| 17 Nov 2026 | Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... | Deferred | Open |
| 17 Nov 2026 | Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... | Approved | Open |
| 17 Nov 2026 | Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... | Approved | Open |
| 17 Nov 2026 | Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.