· endorsed the application for grant support from the East of England Development Agency’s Investing in Communities Programme for the construction of a community enterprise centre in the Sapley East area; · reaffirmed the previous decision to reinvest the proceeds of the disposal of land in this regeneration scheme to produce future community benefits; · supported the principle of establishing a community interest company which will own and manage the proposed community enterprise centre and other assets if opportunities arise; · authorised the Director of Environmental & Community Services to – o obtain agreement in principle from appropriate organisations to form a community interest company; and o work with those organisations to prepare a robust business plan to demonstrate the viability of the community enterprise centre; · considered and noted a Master Plan for the regeneration of the Sapley East area and a business plan for the community enterprise centre before final decisions are made in March/April 2009.and · requested further discussions on the governance arrangements for the company being set up.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
COMMUNITY ENTERPRISE CENTRE – SAPLEY EAST (Report by the Directors of Environmental & Community Services and of Central Services)
1. BACKGROUND AND PURPOSE
1.1The Oxmoor area of Huntingdon has been the focus of sustained urban regeneration. The Oxmoor Opportunities Partnership (OOP), in which this Council was a key player, aimed to meet a five point plan proposed by the Oxmoor Community Action Group. The Partnership made a successful bid for Single Regeneration Budget (SRB) funding from the Government through which programmes were managed and funded between 2000 and 2007.
1.2The five point strategy was:
• To create a safe place to live • Support families • Focus on young people • Promote greater access to services and information • Improve the local environment.
1.3Considerable change has come about as a result of this work and there are notable achievements outlined in the SRB Evaluation Report. However, the report concluded as follows:
“The success of the OOP so far is fragile. Much of what is required is to continue the work that has been done so far and which requires longer than the SRB term to achieve. Two main changes are needed to make this success permanent:
• OOP should concentrate on capacity building to allow the community to take the lead; • Employment should be one of the key elements of that work.”
1.4The Council, with its partners Luminus and the County Council, has made arrangements for the regeneration work to be continued through a Neighbourhood Management Approach (also being established in Eynesbury and Ramsey). 2. PHYSICAL REGENERATION
2.1A key ingredient of the SRB programme was to improve the physical condition of the area and to make provision, through a plan, for necessary facilities and infrastructure. These aspects were brought together in the Oxmoor Action Plan, drawn up after a ‘Planning for Real’ exercise, with local people. Critical to the Plan was a new “Heart for Oxmoor”, whereby a new centre on the site of the former Sapley Square would be created. Phase 1 of the centre, which included the Oak Tree Health Centre, the Maple Centre and shops, has radically transformed the facilities and the environment. Phase 2 on the site of the eastern part of the former Sapley Square and surrounding land provides an opportunity to add much needed facilities and investment to address outstanding issues from the original plans.
2.2An extensive consultation exercise has recently been carried out offering different options for the redevelopment of the eastern part of the former Sapley Square together with other adjacent used and unused/underused land, with the objective of drawing up a Master Plan. The result of this consultation is summarised in paragraph 4 below.
2.3To follow up the employment and capacity issues identified in the SRB Evaluation Report, Luminus, on behalf of the Partnership, were awarded a Bursary by EEDA to examine the feasibility of the development of a local enterprise centre and to develop an application capital grant. This feasibility work involved key stakeholders and the local community and has identified a vision for and the scope of a scheme, an appropriate legal status (a Community Interest Company (CIC)), capital grant and revenue potential. As a result, a significant grant of £600k has been identified in EEDA’s Investing in Communities Programme.
2.4The Council has previously agreed that any sums it receives from land sales on the Oxmoor will be reinvested to provide community benefits and regeneration.
2.5This report proposes that Council should be a key partner in setting up a CIC to deliver a Community Enterprise Centre (and potentially other community assets) within the Sapley Square East development area in accordance with the emerging Master Plan.
3. THE CONSULTATION PROCESS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.