Progress through the various stage of consultation was noted and the proposed amendments to the ‘Preferred Option’ for the Master Plan as set out in section 3 of the report in response to comments made by local people and stakeholders during the consultation held during February and March 2009 were endorsed. The master plan document, attached as Annex C to the report, was approved as informal planning guidance for the comprehensive development of the land mostly to the east of Sapley Square . The principles of implementation set out in section 5 of the report were endorsed.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
SAPLEY EAST PREFERRED OPTIONS PUBLIC CONSULTATION AND COMMUNITY ENTERPRISE CENTRE
(Heads of Planning and Financial Services )
1. INTRODUCTION
1.1The Council has been working with local people and stakeholders to prepare a master plan on land mainly to the east of Sapley Square including the legal and funding arrangements for a Community Enterprise Centre. Members are asked to note the work that has taken place over the last 6 months in working towards a masterplan and to consider its approval as informal planning guidance
2. SUPPORTING/BACKGROUND INFORMATION
2.1The master plan area covers open land at Oak Drive adjacent to the Oak Tree Centre, and land bounded by Nene Road, Coneygear Road and the Medway Centre. The area comprises managed green space, footpaths, under-developed land and six buildings: the Medway Christian Centre; Kingdom Hall; Golden Knight PH; Medway Court; St Barnabas Church and the Medway Centre.
2.2The Council has undertaken two rounds of consultation: ‘Issues and Options’ and a ‘Preferred Option’. On 18th December 2008, Cabinet received a report on the ‘Issues and Options’ consultation and a proposal by EEDA to part fund a Community Enterprise Centre within the area.
3. PUBLIC CONSULTATION PROCESS Issues and Options stage
3.1Under the ‘Issues and Options’ consultation, the Council presented a plan of the area as it stands together with three alternative development options, all of which offered the potential to develop:
v up to 60 homes, including the upgrading and reconfiguration of housing for the elderly; v new faith buildings; v a Community Enterprise Centre for small scale employment, skills development and learning opportunities to meet community needs such as long term unemployment; v safer routes through the area; v more usable open space.
3.2Through the ‘Issues and Options’ consultation held at various locations between 9th September and 21st October 2008, over 300 local people gave their general support for the principle of development but raised concerns about proposals which could directly affect their homes and interests, most notably in relation to faith buildings. 3.3 These messages from local people and stakeholders informed and shaped the design of the ‘Preferred Option’ in the following ways:
i) Faith Buildings: - St Barnabas Church: shows the retention of the church with the opportunity for expansion of faith facilities and or residential use - Kingdom Hall: identifies a possible relocation site in Medway Road - Medway Christian Centre: identifies possible relocation sites – one as an extension of the Medway Centre, the other on the site of the St Barnabas Learning Centre
ii) Community Enterprise Centre: - identifies a site for the centre in two phases, and including the possible relocation of the St Barnabas Learning Centre
iii) Family and Supported Housing: - identifies housing with one group having access off Nene Road and a second housing group with access off Medway Road
iv) Access and Car Parking: - removes the proposal to link Medway Road with Nene Road; and - retains the footbridge across Nene Road.
v) Oak Drive: - proposes improved landscaping and footpath linkages
vi) Open Space and Play Area: - proposes a linear park to provide safer routes through the area to Medway Road and the ‘Courts’ and - designs out a former play area adjacent to Medway Court
vii) Pub: proposes the removal of the existing pub with no site for its relocation.
Preferred option stage 3.4 The consultation on the ‘Preferred Option’ involved over 140 local people and stakeholders held at various locations between 3rd February and 4th March 2009. The programme, which included events dedicated for those most affected by the proposals, is listed in Annex A. The comments of those who wrote in at this stage are listed in Annex B.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.