Resolved
Notes the financial performance to date.
Cabinet decided this item on Thursday 16 July 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Notes the financial performance to date.
Budget Monitoring 2015/16
Attached at Appendix 1 is the May Financial Performance Monitoring Suite, the highlights from this report are:
Revenue Forecast Outturn
The net 2015/16 revenue budget that was approved by Council in February 2015 was £18.881m. After £0.262m carry forwards from 2014/15 were approved by the Cabinet in June 2015; this has resulted in an updated budget of £19.143m. As at the end of May, the year-end forecast outturn is some £0.681m less than planned.
Capital Forecast Outturn
The 2015/16 capital programme of £11.065m was approved by the Cabinet in April 2015 and this resulted in a net budget of £9.637m. As a consequence of budget carry-forwards of £0.274m, the updated capital budget for 2015/16 is £9.363m. To date little has been spent of the capital programme.
General Fund Reserve
The 2015/16 Medium Term Financial Strategy (MTFS) anticipated that the general fund balance at the end of 2015/16 would be £9.334m, this included a budgeted contribution to reserves of £0.797m. At this time, the forecast outturn is predicting a contribution of £1.216m to the general fund reserve. The potential estimated balance at the end of the year would be £10.503m.
New Homes Bonus
The New Homes Bonus calculation is based on data collected over the twelve months between October and September each year. The target housing growth to the end of May 2015 was 560. Currently the position shows 374, a decrease of 186 properties resulting in an estimated reduction in New Homes Bonus of £0.244m. Recommendation(s):
The Cabinet is requested to note the financial performance to date and comment as it considers necessary. 1. PURPOSE
1.1To update Members, in line with best practice and agreed budget monitoring reporting cycles, on the revenue and capital forecast outturn for 2015/16 based on information available at the end of May 2015.
2.1Budget Monitoring
2.1Since December 2013, Members have been receiving the Financial Performance Monitoring Suite (FPMS), which incorporates the Financial Dashboard.
2.2This report updates Members on the 2015/16 revenue and capital forecast outturn; including a forecast outturn for the General Fund. Detailed commentary is shown in the Financial Performance Monitoring Suite for the period April to May 2015/16.
3. REVENUE AND CAPITAL OUTTURN FORECASTS
Variations in Revenue Spend
3.1As a consequence of Accountancy concentrating on the production of the Annual Financial Report, detailed budget monitoring has not started in earnest for 2015/16. However, it is opportune to report to Members the early strategic variances to budget and the resulting forecast outturn.
3.2The net revenue budget approved in February 2015 was £18.881m. In June 2015 the Cabinet approved carry forwards of £0.262m from 2014/15 which resulted in an updated budget of £19.143m. At this time, the predicted net revenue forecast outturn is £18.462m, £0.681m lower than planned.
Variations in Capital Spend
3.3The Council approved the 2015/16 capital programme of £11.065m in February 2015. In April 2015 the Cabinet approved the Finance Governance Board’s (FGB) recommendations that the capital programme be reduced by £1.428m after further scrutiny and challenge. Together with the approved carry forwards of £0.274m the updated capital budget for 2015/16 is £9.363m as detailed in the table below.
Capital Summary £'000
Original Approved Budget 11,065 Approved reductions by FGB 1,428 Approved carry forwards from 2014/15 274 Updated Capital Programme 9,363
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BUDGET MONITORING 2015/16 (REVENUE AND CAPITAL)Report | 358 KB | DownloadRead as text |
PDF |
Budget Monitoring 2015.16 AppendixAppendix | 759 KB | Download |
PDF |
Overview and Scrutiny Economic Comments: 9 July 2015Report | 239 KB | Download |
Follow Cabinet at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... | Noted | Open |
| 17 Nov 2026 | Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... | Deferred | Open |
| 17 Nov 2026 | Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... | Approved | Open |
| 17 Nov 2026 | Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... | Approved | Open |
| 17 Nov 2026 | Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.