Resolved
Noted the emerging variations to the approved 2014/15 revenue and capital budgets.
Cabinet noted this item on Thursday 17 July 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Noted the emerging variations to the approved 2014/15 revenue and capital budgets.
Revenue The net revenue budget approved in February 2014 was £20.870m. The variations forecast so far this year total a saving of £0.355m. This includes £0.125m of staff related savings and £0.120m of transport related savings.
£m Approved Budget 20.870 Forecast Variation (0.355) Forecast 20.515
Monitoring of savings, including those associated with “Facing the Future” will commence from the second quarter of 2014/15.
Capital The net capital budget approved in February 2014 was £4.691m, in addition to this £1.945m of slippage from 2013/14 was carried forward to 2014/15. Resulting in a total updated budget of £6.636m.
At this early stage in the year 3 forecast variations have been reported totalling £0.046m of net additional expenditure. This includes £0.050m overspend on the Huntingdon Multi-Storey Car Park, which has resulted from addition requirements being added to the project specification as the build progressed.
£m Approved Budget 4.691 Slippage from 2013/14 1.945 Forecast Variation 0.046 Forecast 6.682
New Homes Bonus Actual and band D equivalent new build are up against the profiled targets suggesting a gain of £168,000 on receipts in 2015/16. However growth for May was unusually high against the average and may not be sustained.
Recommendation(s): To note the forecast variation to the approved budgets detailed in this report. 1. PURPOSE
1.1To update members on any emerging variations to the 2014/15 approved revenue and capital budgets.
Approved Budget
2.1In February 2014 the Council approved the following 2014/15 net expenditure budgets of:
£20.870m for revenue, and £4.691m for capital.
2.2In respect of:
revenue, the Budget Requirement was £19.865m which required a £1.005m contribution from General Reserves that gave an estimated General Fund Balance of £9.027m at the 31st March 2015
capital, this was to be financed from a mix of capital receipts, capital reserves and working capital.
3. REVENUE MONITORING 2014/15
3.1Only limited revenue budget monitoring takes place in April and May due to the priority to complete the final accounts, the need to wait for adjustments for debtors and creditors to be dealt with in the new financial year and the difficulty of making assumptions on very limited evidence.
3.2This first monitoring therefore concentrates on the impact of items that occurred last year plus a few significant ones that are already emerging in the current year and these are illustrated in the table below.
3 Original Forecast Variation REVENUE BUDGETARY CONTROL 2014/15 Budget outturn £000 £000 £000 Approved budget 20,870 20,870 0 Delayed spending from previous years 512 246 (266) Delayed spending to 2014/15 (512) (246) 266
Variations Environmental Health Staff Redundancy (65) (65) Other Staff Savings, street cleaning, engineers etc (46) (46) Pensions Increase Act on-going savings (14) (14) Operations - Transport Savings (based on historic underspending) (120) (120) Additional Grant Receipts (21) (21) Lower Cash Collection Costs – Car Parks (20) (20) Lower Offices & Depots NDR Charges (34) (34) Land Charges: volume change (6) (6) Licence Fees: volume change (9) (9) Other variations (each less than £9,000) (20) (20)
Total variations (355) (355) Forecast net spending 20,870 20,515 (355)
£000 £000 £000 Financed from Government support (12,205) (12,205) 0 Collection fund adjustment (21) (21) 0 Council tax (7,639) (7,639) 0 General Reserves Contribution to delayed projects reserve (512) 246 (266) Use of delayed projects reserve 512 (246) 266 General reserves (1,005) (650) (355) Total use of reserves (1,005) (650) (355) Total (20,870) (20,515) (355)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget Monitoring 2014/15 Revenue and CapitalReport | 600 KB | DownloadRead as text |
Follow Cabinet at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Nov 2026 | Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... | Noted | Open |
| 17 Nov 2026 | Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... | Deferred | Open |
| 17 Nov 2026 | Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... | Approved | Open |
| 17 Nov 2026 | Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... | Approved | Open |
| 17 Nov 2026 | Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.