Cabinet, Thursday 19 June 2014 at 7.00pm

A14 CAMBRIDGE TO HUNTINGDON - RESPONSE TO HIGHWAYS AGENCY DEVELOPMENT CONSENT ORDER PRE-APPLICATION STATUTORY CONSULTATION

Decided Executive 4 papers

Cabinet decided this item on Thursday 19 June 2014. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

Authorised the Head of Development, after consultation with the Executive Councillor for Strategic Planning and Housing and the Executive Leader, to respond to the Highways Agency Consultation on the upgrade of the A14 as outlined in the Annexes to the report, subject to the strengthening of paragraph 4(g) of Annex C to include the words “the District Council reserves its position on matters of detail, such as the mitigation of the impact of the development on affected villages, on which it will negotiate with the Highways Agency”
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Cabinet

Executive summary

This report follows on from the non-Statutory consultation report in October 2013 and is the Council’s planned response to the current Statutory consultation.

The A14 improvement project remains fundamental, to the delivery of the sustainable growth agenda across Huntingdonshire and to address current congestion and safety issues.

The scheme now subject to public consultation, is similar to that reported last October but incorporates some important changes. Firstly, the previously suggested tolling element of the scheme has now been dropped and the proposed alignment of the route in the Brampton area is significantly changed.

The remainder of the proposal continues to contain many features that this Council has been lobbying for over many years, including the proposed off-line A14 route to the south of Huntingdon and Godmanchester, the upgrading of the A1 between Alconbury and the A14 and the removal of the Huntingdon Viaduct.

Recommendation(s):

recommended that Cabinet agrees the response to the Highways Agency, as outlined at Annex B, stating our support for the scheme as proposed, including our reiteration that our approved local financial contribution is conditional on;

 The overall scheme including the removal of Huntingdon Viaduct and the creation of an improved new local road network for Huntingdon; and  That construction works commence by late 2016 1. WHAT IS THIS REPORT ABOUT/PURPOSE?

1.1The purpose of this report is to agree the Council’s response to the current formal consultation by the HA on the proposed A14 Cambridge to Huntingdon Improvement Scheme.

2. WHY IS THIS REPORT NECESSARY/BACKGROUND

2.1The Council remains a key partner in the development of the current proposals and it is vital that we continue to be engaged in order to deliver the best possible solution for Huntingdonshire.

2.2The first major initiative relating to this scheme was the publication of the CHUMMS (Cambridge to Huntingdon Multi-Modal Study) Report in 2001 with subsequent proposals published to provide an ‘Ellington to Fen Ditton Improvement Scheme’.

2.3Various challenges were made to the HA proposals and a Final Proposed Scheme was eventually published. In 2010, as part of the Coalition Government Comprehensive Spending Review, the Scheme was withdrawn as ‘unaffordable’.

2.4The results of the subsequent ‘A14 Challenge’ were reported in November 2012 and in June 2013, as part of the Spending Review, national funding was allocated, including an agreed local contribution of £100m.

2.5Government announced on 4th December 2013 that tolling would no longer form part of the proposed scheme.

3. CURRENT PROPOSAL/ANALYSIS

3.1The proposed off-line section of the route to the south of Huntingdon remains fundamentally the same as the previous scheme with the exception of the altered alignment of the A1/A14 corridor west of Brampton.

3.2For a detailed description of the route, please refer to Sec. 2b at Annex C.

4. COMMENTS OF OVERVIEW & SCRUTINY PANEL

4.1To be reported verbally

5. KEY IMPACTS/RISKS? HOW WILL THEY BE ADDRESSED?

5.1The key risk for the Council is a failure of the scheme to proceed. The recommendations included within this report reflect this and a formal response now is crucial to meeting this need. 6. ROLES & RESPONSIBILITIES INC. LEGAL IMPLICATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A14 CAMBRIDGE TO HUNTINGDON: RESPONSE TO HIGHWAYS AGENCY DEVELOPMENT CONSENT ORDER PRE-APPLICATION STATUTORY CONSULTATIONReport 112 KB DownloadRead as text
PDF
Cabinet Report 140619 ANNEX A: Projected Timeline to CommencementAppendix 242 KB Download
PDF
Cabinet Report 140619 ANNEX B: Draft response to HA. Rev 1Appendix 200 KB Download
PDF
Cabinet Report 140619 ANNEX C: Detailed ConsiderationsAppendix 249 KB Download

At this meeting

Whole meeting

Who was there

6 of 7 attended
JD
Councillor Jason David AblewhiteChair, present
BS
Councillor Barry Stephen ChapmanMember, present
DB
Councillor Douglas Bernard DewMember, present
JA
Councillor Jonathan Alexander GrayMember, present
RB
Councillor Robin Beatham HoweVice-Chair, apologies
TD
Councillor Thomas Douglas SandersonMember, present
DM
Councillor Darren Marcus TysoeMember, present

On this subject at Huntingdonshire

Search all
  1. A14 CAMBRIDGE TO HUNTINGDON - RESPONSE TO HIGHWAYS AGENCY DEVELOPMENT CONSENT ORDER PRE-APPLICATION STATUTORY CONSULTATIONThis decision
  2. Priory park, huntingdon road, st neots, cambridgeshire pe19 1rfAgreed
  3. Grange farm, abbots ripton, huntingdon, cambridgeshire, pe28 2phDecided
  4. New Cambridgeshire Housing Adaptations Agreement and refreshed Huntingdonshire Housing Renewal Assistance PolicyAgreed
  5. A14 cambridge to huntingdon improvement schemeApproved
  6. A14 cambridge to huntingdon improvement schemeAgreed

More from Huntingdonshire Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... Noted Open
17 Nov 2026 Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... Deferred Open
17 Nov 2026 Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... Approved Open
17 Nov 2026 Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... Approved Open
17 Nov 2026 Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies