A14 CAMBRIDGE TO HUNTINGDON IMPROVEMENT SCHEME

Approved Executive 6 papers

Cabinet approved this item on Thursday 18 June 2015. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

That the Cabinet approve: i) The Joint Local Impact Report of the Council together with other Tier 1 stakeholders, namely Cambridgeshire County Council, Cambridge City Council and South Cambridgeshire District Council, ii) The (Draft) Statement of Common Ground between the Council and Highways England, iii) The Written Representation of the Council to be submitted to the A14 Examination in Public, iv) That, in the interests of expediency, delegated authority be given to the Managing Director and the Executive Councillor for Planning and Housing Strategy relating to the agreement of any required minor amendments to the Joint Local Impact Report, the (Draft) Statement of Common Ground and the Written Representation and other such documents as necessary.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Cabinet

Executive summary

Members will be aware of continuing progress reports in the development of the A14 scheme, including that in June 2014 outlining the outcomes and recommendations of Highways England’s (HE) formal public consultation. This was followed by a further progress report to Members in March 2015 outlining progress with the development and delivery of the scheme, including the proposed timeline to overall delivery and details of the proposed Examination in Public.

The purpose of this report is to provide a further progress report leading into the A14 Examination in Public.

The Development Consent Order (DCO) was submitted by HE to the Planning Inspectorate (PINS) on 31st December 2014. The application was accepted for Examination by PINS on 27th January 2015 and the Preliminary Meeting prior to the formal start of the Examination period was held on 13th May 2015.

The formal Examination in Public commenced on 14th May 2015.

This report includes an update on the Council’s progress in negotiations with HE since the last report considered during March 2015 in our role as a Tier 1 Stakeholder and a statutory consultee in relation to the overall project.

The report also considers 3 key elements that the Council will submit to PINS as part of the Examination process, namely the (Draft) Joint Local Impact Report (Joint LIR), a (Draft) Statement of Common Ground (SoCG) and the Council’s Written Representation. It is important to note that both the (Draft) Joint LIR and the (Draft) SoCG will remain continually evolving documents between now and during the Examination process as matters are negotiated as far as possible towards final agreement during the coming weeks. Updated versions will be submitted to Members where possible during this period. Recommendation(s):

Members are recommended to approve;

i) The (Draft) Joint Local Impact Report of the Council, together with other Tier 1 stakeholders, namely Cambridgeshire County Council, Cambridge City Council and South Cambridgeshire District Council,

ii) The (Draft) Statement of Common Ground between the Council and Highways England,

iii) The Written Representation of the Council to be submitted to the A14 Examination in Public,

iv) That, in the interests of expediency, delegated authority be given to the Managing Director and the Executive Councillor for Planning & Housing Strategy relating to the agreement of any required minor amendments to the (Draft) Joint Local Impact Report, the (Draft) Statement of Common Ground and the Written Representation and other such documents as necessary. 1. WHAT IS THIS REPORT ABOUT/PURPOSE?

1.1This report gives a further update on progress with the development of the A14 Project since the last A14 report was considered during March 2015, matters surrounding the commencement and running of the Examination in Public and the relevant documentation that the Council will submit to the Examination.

Background

2.1Since the original publication of the Cambridge to Huntingdon Multi-Modal Study (CHUMMS) in 2001, the Council has consistently supported calls for the improvement of the A14 between Cambridge and Huntingdon, including the provision of a new off-line route to the south of Huntingdon & Godmanchester and the removal of the current A14 Viaduct within Huntingdon, the downgrading of the existing A14 route and the creation of a new local road network within Huntingdon.

2.2The Council is also a funding partner towards the proposed scheme with an agreed financial package in place to deliver an overall contribution of £5 million towards the project.

2.3A plan of the overall scheme will be available at the meeting.

3. CURRENT POSITION & EXAMINATION IN PUBLIC

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A14 CAMBRIDGE TO HUNTINGDON IMPROVEMENT SCHEMEReport 242 KB DownloadRead as text
PDF
A14 Report: Appendix AAppendix 238 KB Download
PDF
A14 Report: Appendix BAppendix 486 KB Download
PDF
A14 Report: Appendix B.1Appendix 1.4 MB Download
PDF
A14 Report: Appendix CAppendix 194 KB Download
PDF
A14 Report: Appendix DAppendix 2.9 MB Download

At this meeting

Whole meeting

Who was there

8 of 8 attended
JD
Councillor Jason David AblewhiteChair, present
RB
Councillor Robin Beatham HoweVice-Chair, present
RC
Councillor Robin Clive CarterMember, present
SC
Councillor Stephen CawleyMember, present
DB
Councillor Douglas Bernard DewMember, present
RH
Councillor Roger HarrisonMember, present
JA
Councillor Jonathan Alexander GrayMember, present
DM
Councillor Darren Marcus TysoeMember, present

On this subject at Huntingdonshire

Search all
  1. A14 CAMBRIDGE TO HUNTINGDON IMPROVEMENT SCHEMEThis decision
  2. Priory park, huntingdon road, st neots, cambridgeshire pe19 1rfAgreed
  3. Grange farm, abbots ripton, huntingdon, cambridgeshire, pe28 2phDecided
  4. New Cambridgeshire Housing Adaptations Agreement and refreshed Huntingdonshire Housing Renewal Assistance PolicyAgreed
  5. A14 cambridge to huntingdon improvement schemeAgreed
  6. A14 cambridge to huntingdon - response to highways agency development consent order pre-application statutory consultationDecided

More from Huntingdonshire Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... Noted Open
17 Nov 2026 Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... Deferred Open
17 Nov 2026 Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... Approved Open
17 Nov 2026 Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... Approved Open
17 Nov 2026 Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies