i. Considered and commented on progress made against Key Activities and Corporate Indicators in the Corporate Plan and current projects, as summarised in Appendix A and detailed in Appendices B and C of the Officer’s report; ii. Considered and commented on the Council’s 2015/16 provisional outturn. iii. Approves the: § deletion of 21 Earmarked Reserves as detailed in paragraph 4.14.1 of the Officer’s report; § formation of 9 Earmarked Reserves as detailed in paragraph 4.14.2 of the Officer’s report; § transfer of £0.244m from the Budget Surplus Reserve to the Collection Fund Reserve, and § transfer of £0.561m from the Budget Surplus Reserve to finance the Democratic and Organisational Governance and Efficiency initiatives.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
The purpose of this report is to brief Members on progress against the Key Activities and Corporate Indicators listed in the Council’s Corporate Plan for 2015/16 for the period 1 January 2016 to 31 March 2016. The report also incorporates progress reporting for current projects being undertaken at the Council and details of the 2015/16 provisional outturn for revenue and capital spend.
An update on the Commercial Investment Strategy includes details of the investments to date and the level of returns these are expected to generate.
Recommendations
Cabinet are recommended to consider and comment on progress made against Key Activities and Corporate Indicators in the Corporate Plan and current projects, as summarised in Appendix A and detailed in Appendices B and C.
Cabinet are recommended to consider and comment on the Council’s 2015/16 provisional outturn.
Cabinet are also asked to approve the: i. deletion of 21 Earmarked Reserves (paragraph 4.11.1), ii. formation of 9 Earmarked Reserves (paragraph 4.11.2), iii. transfer of £0.244m from the Budget Surplus Reserve to the Collection Fund Reserve, and iv. transfer of £0.561m from the Budget Surplus Reserve to finance the Democratic & Organisational Governance and Efficiency initiatives. 1. PURPOSE
1.1The purpose of this report is to present performance management information on the Council’s Corporate Plan for 2015/16 and updates on current projects.
Background
2.1The Council’s Corporate Plan 2014-16 was adopted as a two-year plan in 2014, with an update approved in April 2015 setting out what the Council aimed to achieve in addition to its core statutory services during 2015/16. The information in the summary at Appendix A and the performance report at Appendix B relates to the Key Actions and Corporate Indicators listed for 2015/16. Following approval of a refreshed Corporate Plan for 2016-18 in March 2016, a new set of Key Actions and Corporate Indicators will be included in quarterly reports on performance during 2016/17.
2.2As recommended by the Project Management Select Committee, project updates are included in this performance report at Appendix C. There are currently 24 open, pending approval or pending closure projects and 7 closed projects logged on the SharePoint site across all programmes. This report covers all of these projects, including all Capital Projects.
2.3This report also incorporates financial performance to the end of March. Performance is summarised in section 4 below and details are listed in the Financial Performance Monitoring Suite at Appendix D.
3. PERFORMANCE MANAGEMENT
3.1Members of the Overview and Scrutiny (Performance and Customers) Panel have an important role in the Council’s Performance Management Framework and a process of regular review of performance data has been established. The focus is on the strategic priorities and associated objectives to enable Scrutiny to maintain a strategic overview.
3.2Progress against Corporate Plan objectives is reported quarterly. The report at Appendix B includes performance data in the form of a narrative of achievement and a RAG (Red/Amber/Green) status against each Key Action in the Corporate Plan and results for each Corporate Indicator. Appendix C gives a breakdown of projects including the purpose of the project and comments from the Programme Office as to the current status of each project’s SharePoint site as part of the new governance arrangements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.