The Cabinet has noted progress on all the projects within the Market Towns Programme and specifically the following: (a) The appointment of a contractor to deliver the St Neots Town Centre Improvements (Market Square and adjacent highways/junctions) and commencements of works in October 2023. (b) Progression of the Priory Centre improvement project including the appointment of a multi-disciplinary team to develop proposals and support delivery. (c) Commencement of delivery of the Huntingdon & St Ives works, including roll out of the Shop Front Improvement Grant scheme. (d) Delivery of the Digital Information Screens project in Huntingdon, St Neots, St Ives and Ramsey.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
This report provides the 2023/2024 Q2 update on the Market Towns Programme (MTP).
The MTP is funded through a combination of external funding from the Department for Levelling Up, Housing & Communities (DLUHC), Cambridgeshire and Peterborough Combined Authority (CPCA), Huntingdonshire District Council (HDC) Community Infrastructure Levy (CIL) and National Highways.
RECOMMENDATION UPDATED
Cabinet is asked to:
Note progress on all the projects within the Market Towns Programme and specifically the following:
(a) The appointment of a contractor to deliver the St Neots Town Centre Improvements (Market Square and adjacent highways/junctions) and commencement of works in October 2023.
(b) Progression of the Priory Centre improvement project including the appointment of a multi-disciplinary team to develop proposals and support delivery.
(c) Commencement of delivery of the Huntingdon & St Ives works, including roll out of the Shop Front Improvement Grant scheme.
(d) Delivery of the Digital Information Screens project in Huntingdon, St Neots, St Ives, and Ramsey.
1. PURPOSE OF THIS REPORT 1.1 To provide an update on activity across the strands of the Market Town Programme, with specific regard to the progress of projects highlighted above.
2. UPDATE ON MARKET TOWNS PROGRAMME
ST NEOTS PROGRAMME:
Town Centre Improvements (Transport Projects)
2.1The Town Centre Improvements project is scheduled to begin delivery during October 2023. This follows the successful completion of the contractor procurement process carried out, utilising the Eastern Highways Framework, in partnership with Cambridgeshire County Council. The successful tender was submitted by the contractor Eurovia, and we are now in the process of finalising contracts to enable the works to begin in October.
2.2The most significant risk to this project was the impact of high levels of inflation on the construction cost and, consequently, the ability of the Council to deliver the scheme within our current resources. Considerable work was undertaken in developing the detailed designs and specifications with scheme partners and contractors to mitigate this risk.
2.3This work, which included consulting with contractors during the design process, helped to ensure that the value of both tenders received were broadly in line with cost expectations, and resources available. At a time when construction inflation is having a significant impact on the delivery of major infrastructure projects across the country, this is a considerable achievement.
2.4Now that the procurement process is complete, work is turning towards the contractors starting on site, preparation and phasing of works in the Market Square and adjacent highways or junctions, which are due to be improved. The start of the main works within the Market Square itself is scheduled for January. This will help to ensure that there will be minimal impact on Christmas celebrations, including the Christmas lights switch on, which is a very popular event in the town.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.