RESOLVED that the proposed approach, the emerging content of the corporate risk register and the strategy for the future development of risk management be noted.
Corporate Governance Committee noted this item on Wednesday 29 January 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the proposed approach, the emerging content of the corporate risk register and the strategy for the future development of risk management be noted.
This report sets out the work done since the last meeting of the Committee where the Corporate Director gave an oral update about the proposed work to review and revise the Corporate Risk Register facilitated by RSM.
The Committee is
RECOMMENDED
To consider the approach proposed, the emerging content of the corporate risk register and the strategy for the future development of risk management. 1. PURPOSE OF THE REPORT
1.1This report informs the committee of the approach and work undertaken on the Corporate Risk Register.
2. WHY IS THIS REPORT NECESSARY
2.1Effective Risk Management is a critical part of the organisation’s governance. The Risk Register identifies those areas where the Council should take action to mitigate its exposure and informs the annual plan for Internal Audit.
2.2Presenting the Risk Register to each meeting of the Committee is an integral part of the overall governance process as set out in the Council's Risk Management Strategy
3. ANALYSIS
3.1Prior to the current Corporate Director (S151 Officer) joining the Council in October 2024, the Committee was advised at its meeting in July that she would take a fresh look at corporate risk, the register and how this is presented to the Committee in a meaningful way.
3.2At the November meeting, the Corporate Director advised orally that following an unsuccessful recruitment exercise to replace the Risk Officer, she had taken the decision to engage support from RSM UK Risk Assurance Services LLP, the firm that provides the risk management software system (4Risk) used by the Council.
3.3The initial assessment from RSM was that the software in use needed to be updated and that the existing corporate risk register consisting of 109 risks, many of which did not have mitigating actions, did not constitute a meaningful corporate risk register.
3.4As part of the work facilitated by RSM, work has been done with Management Team to assess the current significant risk for the Council. These are summarised in Appendix 2 for the Committee to comment on for SLT to take account of when looking at the mitigation.
4. KEY IMPACTS
4.1An up to date corporate risk register enables the organisation to ensure it is focusing on the key risks and that the work of internal audit is informed by the register. The ensures that internal audit activity can give sound assurance and adds value to the organisation and its corporate governance.
5. WHAT ACTIONS WILL BE TAKEN/TIMETABLE FOR IMPLEMENTATION
5.1Attached as an Appendix is the approach and timeline that RSM are facilitating to bring our approach up to date and ensure that there is a robust and realistic approach to risk management. 6. LINK TO THE CORPORATE PLAN, STRATEGIC PRIORITIES AND/OR CORPORATE OBJECTIVES
6.1Ensuring we are a customer focused and service led Council – to become more business-like and efficient in the way we deliver services. Effective management of corporate risks is a demonstrate of this approach.
7. RESOURCE IMPLICATIONS
7.1RSM are providing capacity and facilitation to support this activity and during the first quarter of 2025/26, the Corporate Director will assess the resource requirements for this activity and the use of the Risk & Controls Officer post.
8. LIST OF APPENDICES INCLUDED
Appendix 1 – RSM Risk Management Development Plan Appendix 2 - Emerging Risk Themes
CONTACT OFFICER
Name/Job Title: Suzanne Jones, Corporate Director – Finance and Resources Telephone: 01480 388214 Email: [email protected]
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CORPORATE RISK REGISTERReport | 77 KB | DownloadRead as text |
PDF |
Item 6: Corporate Risk Register Appendix 1Appendix | 607 KB | Download |
PDF |
Item 6: Corporate Risk Register Appendix 2Appendix | 66 KB | Download |
Follow Corporate Governance Committee at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Jun 2026 | Approval for Publication of Draft 2025/26 Statement of AccountsRESOLVED that the Committee (1) considered and approved the Annual Governance Statement (Appendix 1); (2) considered ... | Approved | Open |
| 17 Jun 2026 | External Audit PlanRESOLVED that the Committee commented and noted the External Auditor’s Annual Planning Report, set out at Appendix 1. | Noted | Open |
| 17 Jun 2026 | Corporate Risk RegisterRESOLVED that the Committee commented on the reports in the appendices and progress with risk management and noted th... | Noted | Open |
| 17 Jun 2026 | Internal Audit Progress ReportRESOLVED that the Committee commented on and noted the update on work undertaken by Internal Audit to date. | Noted | Open |
| 17 Jun 2026 | Internal Audit Actions UpdateRESOLVED that the Committee commented on and noted the current position regarding actions arising from internal audit... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.