Noted Executive 1 paper

AI summaryHuntingdonshire Cabinet noted the 21 November 2025 minutes of the Hinchingbrooke Country Park Joint Group, covering the development project starting 28 November, contractor shortlisting, and a large budget underspend.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet received and noted the Joint Group minutes
MoneyLarge underspendCaused by vacancies and revised assumptions, with lower electricity costs
What happens nextNext meeting 17 April 2026Scheduled for 10:00am
Who it affectsCountry Park visitorsTemporary facilities and signage during construction works

What was decided

The Cabinet received and noted the minutes of the Hinchingbrooke Country Park Joint Group meeting held on 21 November 2025.

Why

The minutes were presented to keep Cabinet informed of progress on the Hinchingbrooke Country Park Development Project, finance, and related matters overseen by the Joint Group. Report P2, P11, P19, P20

What happens next

Development works at the park are due to commence on 28 November 2025, with the staffing structure to be revisited once works are complete. Report P13, P20

The next Joint Group meeting is scheduled for 17 April 2026 at 10:00am. Report P22

Options considered

  • Chosen: Two shortlisted contractors (both local) for the development project. Selected from six public tender responses Report P18
  • Chosen: No Christmas events at the Park. Due to planned development works commencing 28 November 2025 Report P13

Implications

  • Risk: Concern expressed about the height of a proposed industrial park on the border of the country park and its potential impact; officers in conversation with planning colleagues. Report P17
  • Staffing: The staffing structure for the park will be revisited following completion of the development. Report P20
  • Other: Future plans aim for a 4 hour visitor dwell time and secondary spend at the onsite café; carparking impact to be reviewed against the business case. Report P15
  • Other: Temporary catering and WC facilities will be located in the current car park during construction, with safe and accessible routes maintained around the site. Report P14

Who and where

  • Visitors to Hinchingbrooke Country Park during the construction phase Report P14
  • Volunteers taking part in tree planting events using nursery stock Report P12
  • Onsite café users and future potential high ropes or water sports users Report P15, P16

Timeline

  • 21 November 2025: Hinchingbrooke Country Park Joint Group meeting held Report P2
  • 28 November 2025: Development works due to commence at the park Report P13
  • 17 April 2026 at 10:00am: Next Joint Group meeting scheduled Report P22

Plain English for the jargon

  • Dwell time: The length of time visitors are expected to stay at the park
  • Biophilic design: A design approach that connects people with nature
  • Joint Group: A cross-party oversight body for Hinchingbrooke Country Park
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item60

Resolved

The Cabinet has received and noted the Minutes of the meeting held on 21 November 2025.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Cabinet

HUNTINGDONSHIRE DISTRICT COUNCIL

MINUTES of the meeting of the HINCHINGBROOKE COUNTRY PARK JOINT GROUP held in Lancaster & Stirling, Civic Suite, Pathfinder House, St Mary's Street, Huntingdon PE29 3TN on Friday, 21 November 2025.

PRESENT: Councillor M L Beuttell – Chair.

Councillors C Lowe and D J Shaw.

APOLOGIES: An apology for absence from the meeting was submitted on behalf of Councillor J E Kerr.

10. MINUTES

The Minutes of the meeting held on 18th July 2025 were approved as a correct record and signed by the Chair.

11. MEMBERS' INTERESTS

No declarations were received.

12. HEAD RANGER'S REPORT

By means of a report and presentation by the Parks and Countryside Development Co-ordinator and the Commercial Manager (copies of which were appended in the Minute Book), the Head Ranger’s report and an update on the Hinchingbrooke Country Park Development Project were presented to the Group.

Following enquiries from Councillors Lowe and Shaw, the Group heard that trees from the nursery were mainly used in tree planting events within the park and that these events were publicised on social media with volunteers being welcome.

It was confirmed, following a question from Councillor Beuttell that there were no Christmas events planned at the Park due to the planned development works, which were due to commence on 28th November 2025.

The Group heard that temporary catering facilities and wc facilities had been sourced and would be located within the current carpark area of the site to allow for the commencement of works and that temporary signage would be in place. Safe and accessible routes would remain open around the site in order to minimise impact to visitors during the construction phase of the development. Following an enquiry from Councillor Shaw about the access route through Bobs Wood, the Group were advised that this was already in hand with an anticipation that a more robust underfooting for visitors would be maintained. The plans for the development were shared and the biophilic design was noted. It was advised that a look and feel identity for the Park was hoped for whilst keeping within the Council’s corporate identity.

The Group were advised that future plans for the Park post development would aim for a dwell time of 4 hours which would also encourage secondary spend within the onsite café. Following an enquiry from Councillor Shaw about the impact of this on the onsite carparking, the Group heard that this would be reviewed in line with the business case and that the team were looking to the future and longevity of the site.

Following an enquiry from Councillor Beuttell, the Group heard that following a competitor analysis, it was hoped that the site would rival local attractions such as Johnsons and Wimpole Home Farm with country parks increasing in popularity. Councillors Lowe and Shaw enquired about the potential to include either a high ropes or water sports offer within the new site with the opportunity to appeal to both children and adults for family activities.

The proposed industrial park on the boarder of the park was discussed and it was noted that officers were in conversation with planning colleagues to better understand the development. Concern was expressed by the Group in relation to the height of the development and the potential impact this could have upon the Park.

Following enquiries from Councillors Beuttell and Lowe, the Group heard that 6 contractors had responded to the public tender for the project and that 2 had been shortlisted, both of whom were local to the region.

13. FINANCE REPORT

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hinchingbrooke Country Park Joint GroupMinutes 67 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
SJ
Councillor Sarah Joanne ConboyChair, present
LD
Councillor Lara Davenport-RayMember, present
SW
Councillor Stephen William FergusonMember, present
JE
Councillor Joanna Elizabeth HarveyMember, apologies
SA
Councillor Sally Ann HowellMember, present
JE
Councillor Julie Elizabeth KerrMember, present
BA
Councillor Brett Alistair MickelburghMember, present
TS
Councillor Tom SandersonVice-Chair, present as substitute
SW
Councillor Sam WakefordMember, apologies

On this subject at Huntingdonshire

Search all
  1. Hinchingbrooke Country Park Joint GroupThis decision
  2. Hinchingbrooke Country Park Minutes / Appointment of 4th MemberNoted
  3. Hinchingbrooke Country Park Joint GroupDecided
  4. Hinchingbrooke Country Park Joint GroupNoted
  5. Hinchingbrooke country park joint group minutesNoted
  6. Hinchingbrooke country park joint groupDecided

More from Huntingdonshire Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... Noted Open
17 Nov 2026 Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... Deferred Open
17 Nov 2026 Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... Approved Open
17 Nov 2026 Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... Approved Open
17 Nov 2026 Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies