2025/26 Finance Performance Report - Provisional Outturn

Decided Executive 5 papers

AI summaryHuntingdonshire Cabinet noted a provisional revenue underspend of £4.372m and a capital in-year underspend of £9.460m for 2025/26, with £13.160m of capital budgets to be rephased into 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedRevenue and capital positions for 2025/26 considered
Money£4.372m revenue underspend, £9.460m capital underspendPlus £13.160m capital rephased to 2026/27
What happens nextFeed into MTFS and quarterly reportsVariations to be incorporated in Medium Term Financial Strategy
Who it affectsCouncil finances and servicesRevenue, capital, council tax and business rates collection

What was decided

Cabinet considered the provisional revenue outturn for 2025/26, which showed net expenditure of £22.306m against a current budget of £26.678m, giving an underspend of £4.372m after £1.094m of reserve contributions. Report 1.1, P18

Cabinet considered the provisional capital outturn, with a current gross budget of £27.687m and an in-year underspend of £9.460m. Report 1.2, 2.2, P23

Cabinet considered the request to rephase £13.160m of capital budgets from 2025/26 into 2026/27. Report 1.3, 2.2, P23

Why

The report is part of the council's routine budget monitoring, which is required by the constitution and financial regulations and supports sound financial management. Report P37, P44

Variations need to be incorporated into the Medium Term Financial Strategy so that future budgets reflect the outturn position. Report P17, P44

What happens next

Officers will incorporate the 2025/26 variations into the MTFS and report changes through future quarterly monitoring and budget setting. Report P17, P44

Overview and Scrutiny comments will be added to the report before Cabinet considers it further. Report 3.1, P13

The money

  • £4.372m Revenue provisional outturn underspend for 2025/26 Report P8, P18
  • £9.460m Capital provisional in-year underspend for 2025/26 Report P8, P23
  • £26.678m Current revenue budget for 2025/26 Report P18
  • £22.306m Provisional revenue outturn net expenditure Report P18
  • £1.094m Contributions from reserves on revenue Report P18
  • £14.527m Approved gross capital programme for 2025/26 Report 2.2, P23
  • £13.160m Additional capital rephasing from 2025/26 into 2026/27 Report 2.2, P23
  • £27.687m Total current capital budget after rephasing Report 2.2, P23

Options considered

  • Chosen: Note the 2025/26 revenue and capital provisional outturn and the requested capital rephasing. The decision wording covers consideration and comment on these items; no alternative options were put to Cabinet. Report 1.1, 1.2, 1.3

Implications

  • Financial: The £4.372m revenue underspend and £9.460m capital in-year underspend will be reflected in the MTFS and future quarterly monitoring. Report P8, P17, P44
  • Legal: Effective budget monitoring is required by the council's constitution and financial regulations. Report P37
  • Risk: Risk is managed through individual service risk registers. Report P50
  • Other: Local Government Reorganisation: the report is retrospective and has limited LGR impact. Report P49

Who and where

  • Huntingdonshire District Council services and budget managers Report P21, P20
  • Council Tax payers in Huntingdonshire Report P25, P26
  • Business Rate payers in Huntingdonshire Report P25
  • Working age and pensioner Council Tax Support claimants Report P26
  • Overview and Scrutiny Panel members Report 3.1, P13

Timeline

  • February 2025: Revenue budget and MTFS for 2025/26 approved at net expenditure of £26.464m Report 2.1
  • 31st March 2026: End of 2025/26 financial year; debtor analysis dated this point Report P27
  • Quarter 4 2025/26: Council Tax collection rate 98.05% and Business Rates 98.25% recorded Report P25
  • 14 July 2026: Cabinet considers provisional outturn report

Plain English for the jargon

  • MTFS: Medium Term Financial Strategy, the council's multi-year financial planning document
  • Provisional outturn: Estimated final spending and income position for the year, before accounts are closed
  • Rephasing: Moving budgeted spending from one financial year into a later one
  • CIS: Commercial Investment Strategy, the council's approach to investing in property and cash to generate income
  • PWLB: Public Works Loan Board, a UK government source of long-term loans for local authorities
  • LGR: Local Government Reorganisation, the restructuring of local authority boundaries and functions
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

The Cabinet has (1) considered and commented on the revenue financial performance for the financial year 2025/26, as detailed in Appendix 1 and Appendix 2; (2) considered and commented on the capital financial performance for 2025/26, as detailed in Appendix 3; and (3) considered and commented on the requested rephasing of capital budgets from 2025 /26 to 2026/27 as detailed in Appendix 3.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Cabinet

Overview and Scrutiny Panel (P&G) – 1st July 2026 Cabinet – 16th July 2026 Council – 16th December 2026

Report by: Head of Finance

Lead Cllr: Cllr J E Harvey Executive Councillor for Finance and Resources

Wards Open / Exempt Key Decision? ALL wards Open No

2025/26 Finance Performance Report – Provisional Outturn Executive Summary:

This report sets out the provisional outturn for the financial year 2025/26 for both revenue and capital.

REVENUE PROVISIONAL OUTTURN

The current net revenue budget for 2025/26 is £26.678m (Original budget of £26.464m plus brought forward budgets of £0.308m, less carried forward budgets of £0.094m). The provisional net outturn expenditure for 2025/26 is £22.306m, this is a provisional outturn underspend of £4.372m.

The significant variations that contribute to the provisional are as follows:

REVENUE UNDERSPENDS

The significant variations that contribute to the provisional are as follows:

Chief Digital and Information Officer - underspend of £0.07m, as a result of: staff saving due to delayed restructure, offset by lower income from partners.

Head of Planning, Infrastructure and Public Protection - underspend of £1.6m, as a result of: Additional income from Planning Performance Agreements, planning fees, licencing fees and grant income. Additional expenditure on agency staff, but savings from currently vacant posts, electricity costs and less empty homes expenditure. Head of Environmental Services - underspend of £1.1m, as a result of: Significant increase in income from recycling credits, Green Waste subscriptions, Bulky Waste collections, Street Cleansing and Grounds Maintenance works. There have been increased costs of agency staff, vehicle hire, weekend working and riverbank works, but savings from vacant posts, sewer ditch works and St Ives Park.

Head of Human Resources and Officer Development – underspend of £0.06m, as a result of: Additional income from partners

Head of Finance - underspend of £2.5m, as a result of: Investment income is above budget because interest rates are remaining higher for longer than expected and a reduction in the Minimum Revenue Provision as a result of rephased schemes in the capital programme. Offset by overtime, LGR reserve contribution and collection fund support.

Customer Change Director - underspend of £0.9m as a result of: Additional income from Housing Benefit subsidy and Homelessness grants. Also, reduction in benefits paid and salary savings, additional costs as a result of rough sleeping post and bed and breakfast costs.

Head of Policy, Performance and Emergency Planning – underspend of £0.07m as a result of: Additional income from joint funding, saving from work not yet commenced and vacant posts.

REVENUE OVERSPENDS

Chief Executive Officer overspend of £0.4m, as a result of: Costs relating to pay bargaining and s151 Officer interim cover.

Head of Economy, Regeneration and Housing – overspend of £0.04m, as a result of: Lower income from car parks and markets. There were also savings on business rates, salaries and partner payments.

Head of Leisure, Health and Environment – overspend of £0.3m as a result of: Lower income at One Leisure sites, additional employee costs, offset by additional Active Lifestyles income, lower expenditure on utilities, vacant posts and climate projects.

Head of Property and Facilities - overspend of £0.8m, as a result of: Reduced rental income due to vacant properties but increase in feed in tariffs. Savings on utilities, and repairs, but increased costs of consultants and business rates.

Head of Democratic Services and Monitoring Officer - overspend of £0.4m, as a result of: Additional expenditure as a result of new posts, legal costs, election costs and costs to cover vacant posts. There has been additional income to cover elections.

Head of Communications. Engagement and Public Affairs overspend of £0.1m as a result of: Additional expenditure on corporate campaigns, on standby allowances, staff equipment and print costs. CAPITAL PROVISONAL OUTTURN

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 Finance Performance Report: Provisional OutturnReport 407 KB DownloadRead as text
PDF
Capital Provisional Outturn: Appendix 3Appendix 146 KB Download
PDF
Finance Performance Report: Appendix 1Appendix 88 KB Download
PDF
Finance Performance report: Appendix 2Appendix 159 KB Download
PDF
O&S Comments for July Cabinet-Financial PerformanceReport 58 KB Download

At this meeting

Whole meeting

Who was there

9 of 9 attended
SJ
Councillor Sarah Joanne ConboyChair, present
LD
Councillor Lara Davenport-RayMember, present
LD
Councillor Liam Dewey-BeckettMember, present
JE
Councillor Joanna Elizabeth HarveyMember, present
NJ
Councillor Nathan James HuntMember, present
JE
Councillor Julie Elizabeth KerrMember, present
BA
Councillor Brett Alistair MickelburghVice-Chair, present
DL
Councillor Debbie Lydia MickelburghMember, present
TS
Councillor Tom SandersonMember, present

On this subject at Huntingdonshire

Search all
  1. 2025/26 Finance Performance Report - Provisional OutturnThis decision
  2. Finance Performance Report Q2Approved
  3. Finance Performance Report Quarter 1Approved
  4. 2025/26 Finance Performance Report - Forecast at Quarter 3Decided
  5. 2025/26 Finance Performance Report - Forecast at Quarter 2Decided
  6. Finance Performance Report 2025/26 (Quarter 1)Decided

More from Huntingdonshire Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... Noted Open
17 Nov 2026 Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... Deferred Open
17 Nov 2026 Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... Approved Open
17 Nov 2026 Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... Approved Open
17 Nov 2026 Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies