CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Huntingdonshire District Council
Cabinet, Tuesday 15 September 2026 at 7.00pm

Finance Performance Report Quarter 1

Approved Executive 5 papers

AI summaryCabinet reviewed the Q1 finance report showing a £2.762m revenue underspend and £8.249m capital overspend, approved funding for the Priory Centre and wider regeneration schemes, and approved delivering the One Leisure St Ives outdoor pitch directly without Football Foundation funding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved
Money£2.762m underspend revenue, £8.249m overspend capital
What happens nextOngoing monitoringQuarterly monitoring reports will update any changes to financial resources
Who it affectsNot stated

What was decided

Cabinet considered and commented on the revenue financial performance for 2026/27 Q1, with forecast net expenditure of £27.569m against a current budget of £28.151m, resulting in a forecast underspend of £2.762m. Report P18

Cabinet approved the funding proposals for the Priory Centre and wider regeneration schemes, with additional expenditure of £3,891,000 funded from grants, CIL reserve, St Neots Town Council, and legacy Cambridgeshire Horizons funding. Report P26

Cabinet approved Option 3 for the One Leisure St Ives Outdoor Pitch, withdrawing from the Football Foundation funding offer and delivering the project directly through the Council's capital programme at an estimated cost of £836,883. Report P27, P28

Why

The majority of the capital overspend has an identified funding source including grants, CIL and reserves, so does not represent equivalent additional pressure on the Council. Report P19

Option 3 for the outdoor pitch enables the Council to retain greater control over procurement, pricing, programming, booking arrangements, operating income and future pitch replacement arrangements, while avoiding long-term grant conditions and compliance requirements. Report P28

Effective budget monitoring is a requirement of the Council's constitution and financial regulations, and a key component in identifying developing financial issues. Report P48

What happens next

The outturn position and impact of variations will be incorporated within the Medium-Term Financial Strategy. Report P17

Quarterly monitoring reports will update any changes to financial resources for future years. Report P55

Risk is managed by individual service risk registers. Report P61

The money

  • £28.151m Current revenue budget (original £28.057m plus £0.094m brought forward) Report P18
  • £27.569m Forecast net revenue expenditure Report P18
  • £2.762m Forecast revenue underspend Report P18, P8
  • £35.214m Current capital budget (approved £29.457m plus £5.757m additional rephasing) Report P19, P25
  • £43.463m Forecast capital expenditure Report P19, P25
  • £8.249m Capital in-year overspend Report P8, P19, P25
  • £3,891,000 Additional Priory Centre and market towns expenditure Report P26, P33
  • £836,883 Revised One Leisure St Ives outdoor pitch total project cost Report P27
  • £2,841,500 Remaining legacy Cambridgeshire Horizons funding proposed for Priory Centre overspend Report P26

Options considered

  • Rejected: Football Foundation funding for One Leisure St Ives outdoor pitch. The Football Foundation offered only 25.92% of costs compared to originally anticipated external funding, would require 74.08% council contribution, and carries long-term operational, financial, land, monitoring and governance conditions. Report P27
  • Chosen: Option 3 - withdraw from Football Foundation and deliver directly through capital programme. Enables greater control over procurement, pricing, programming, booking arrangements, operating income and future pitch replacement, while avoiding long-term grant conditions. Report P28

Implications

  • Financial: Forecast revenue underspend of £2.762m, capital overspend of £8.249m with most variance having identified funding sources. Report P18, P19
  • Financial: Commercial Investment Strategy forecast net contribution of £3.961m against budget of £4.087m, adverse variance of £0.126m primarily due to lower property rental income. Report P41
  • Legal: Effective budget monitoring is a requirement of the Council's constitution and financial regulations. Report P48
  • Environment: Environment and climate change impacts from expenditure in climate and environment related budgets, particularly in Parks service. Report P52
  • Risk: Risk is managed by individual service risk registers. Report P61

Who and where

  • Housing and Regeneration team (Priory Centre and market towns schemes) Report P26, P33
  • Leisure and Health services (One Leisure St Ives) Report P27, P28
  • All council services through revenue and capital variances Report P20, P22

Timeline

  • February 2026: Revenue budget and MTFS for 2026/27 approved with net expenditure budget of £28.057m Report 2.1
  • End of 2025/26: Total capital rephasing of £11.694m confirmed, increasing capital budget to £35.214m Report P19, P25
  • 30th June 2026: Debtor analysis date for Q1 Report P39
  • End of Q1 2026/27: Council Tax collection rate 28.31%, Business Rates collection rate 32.43% Report 4.4

Plain English for the jargon

  • MTFS: Medium-Term Financial Strategy
  • CIL: Community Infrastructure Levy
  • LGR: Local Government Reorganisation
  • RSG: Revenue Support Grant
  • PPA: Planning Performance Agreement
  • CIS: Commercial Investment Strategy
  • TCMG: Treasury and Capital Management Group
  • HDC: Huntingdonshire District Council
  • 3G: Third Generation (artificial grass pitch)
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

The Cabinet has (1) considered and commented on the revenue financial performance for the financial year 2026/27 Q1, as detailed in Appendix 1 and Appendix 2; (2) considered and commented on the capital financial performance for 2026/27 Q1, as detailed in Appendix 3; (3) approved the funding proposals relating to the Priory Centre and wider regeneration schemes (Housing and Regeneration team), and One Leisure St Ives Outdoor Pitch funding (Option 3) (Leisure and Health). An explanation of the funding proposals can be found in the comments against these projects within the capital programme (Appendix 3) and within section 4.3 of the report; and (4) considered and commented on the Treasury Management 2026/27 Q1 Report attached as Appendix 4.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Cabinet

Cabinet – 15th September 2026

Report by: Head of Finance

Lead Cllr: Cllr J E Harvey Executive Councillor for Finance and Resources

Wards Open / Exempt Key Decision? ALL wards Open No

2026/27 Finance Performance Report – Forecast at Quarter 1 Executive Summary:

This report sets out the forecast outturn for the financial year 2026/27 for both revenue and capital as forecast at the end of quarter 1.

REVENUE FORECAST

The current net revenue budget for 2026/27 is £28.151m (original budget £28.057m plus brought forward budgets of £0.094m). Forecast net expenditure is £27.569m, with forecast use of reserves of £2.180m, resulting in a forecast underspend of £2.762m. The main favourable variances are within Finance (£1.583m), Operations (£0.936m), Communities & Operational Housing (£0.477m), Planning (£0.221m), Human Resources (£0.138m), Democratic Services (£0.125m) and Digital & Information (£0.131m). These are partly offset by pressures within Customer Services & Revenues & Benefits (£0.395m), Property & Facilities (£0.296m), Leisure, Health & Environment (£0.127m) and other smaller pressures. The Finance position includes £0.880m of centrally held pay rectification and incremental budgets now charged to services; this is a budget allocation adjustment rather than a genuine Council-wide saving.

The variations that contribute to the forecast are as follows:

REVENUE FORECAST UNDERSPENDS

Chief Digital and Information Officer – Underspend £0.131m – The forecast underspend is mainly due to licence rationalisation (£86k), salary vacancies (£28k) and reduced agency costs (£17k). This is partly offset by lower partner recharge income as shared-service costs reduce, together with the cost of additional out-of- hours work for Cambridge City Council. The out-of-hours costs are fully recoverable through the partner recharge. Head of Economy, Regeneration and Housing – Underspend £0.051m – The forecast underspend is mainly due to additional income from St Neots Market and evening events, salary savings and lower business rates costs, partly offset by lower car park income and additional project expenditure. Grant-funded expenditure is matched by the associated grant income and therefore does not create an unfunded pressure.

Head of Planning, Infrastructure and Public Protection – Underspend £0.221m – The forecast underspend is mainly due to increased planning application income, New Burdens grant funding and salary savings, partly offset by lower Planning Performance Agreement and CIL administration income and higher agency and consultancy costs.

Head of Operations – Underspend £0.936m – The forecast underspend is mainly driven by additional income from CCTV service level agreements, Grounds Maintenance, Street Cleansing and waste services, together with savings on Street Cleansing subcontractors and vacant posts

Head of Human Resources and Officer Development – Underspend £0.138m – The forecast underspend is mainly due to additional recharge income and savings on in-house training and salaries, partly offset by additional legal and consultancy costs. Reserve funding supports Workforce Strategy activity.

Head of Finance – Underspend £1.583m – The forecast underspend is primarily due to additional investment income and savings on borrowing, salaries and audit costs, partly offset by temporary resources for LGR, accounts closedown and budget setting and other reserve-funded activity. The position also includes £0.880m of centrally held pay rectification and incremental budgets. These costs were held centrally when the 2026/27 budget was set because the affected staff and services were not yet known and have subsequently been allocated to services. The corresponding £0.880m underspend in Finance is therefore a budget allocation adjustment rather than a Council-wide saving.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Tables for Monitoring Q1 UpdateAppendix 1 270 KB Download
PDF
Tables for Monitoring Q1 UpdateAppendix 2 343 KB Download
PDF
Capital Monitoring Table Q1 UpdateAppendix 3 534 KB Download
PDF
TM Quarter 1 2026-27Appendix 4 424 KB Download
PDF
Finance Performance Report Quarter 1Report 357 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 9 attended
SC
Councillor Stephen ClaffeyMember, apologies
SJ
Councillor Sarah Joanne ConboyChair, present
LD
Councillor Liam Dewey-BeckettMember, present
JE
Councillor Joanna Elizabeth HarveyMember, apologies
NJ
Councillor Nathan James HuntMember, present
JE
Councillor Julie Elizabeth KerrMember, present
BA
Councillor Brett Alistair MickelburghVice-Chair, present
DL
Councillor Debbie Lydia MickelburghMember, present
TS
Councillor Tom SandersonMember, apologies

On this subject at Huntingdonshire

Search all
  1. Finance Performance Report Quarter 1This decision
  2. Finance Performance Report Q2Approved
  3. 2025/26 Finance Performance Report - Provisional OutturnDecided
  4. 2025/26 Finance Performance Report - Forecast at Quarter 3Decided
  5. 2025/26 Finance Performance Report - Forecast at Quarter 2Decided
  6. Finance Performance Report 2025/26 (Quarter 1)Decided

More from Huntingdonshire Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Report in Response to Overview and Scrutiny Panel RequestThe Cabinet has (1) noted the resolution of the Overview and Scrutiny (Performance and Growth) Panel made on 4th Nove... Noted Open
17 Nov 2026 Council Tax Support 2027/28The Cabinet has deferred the report to the 15th December 2026 Cabinet meeting, to allow sufficient time for Officers ... Deferred Open
17 Nov 2026 Homelessness & Rough Sleeping Strategy 2026-2031The Cabinet has 1.1. approved the Homelessness & Rough Sleeping Strategy 2026-2031 as a consultation draft; and 1.2. ... Approved Open
17 Nov 2026 Safeguarding Children, Young People and Adults at Risk of Harm Policy ReviewThe Cabinet has (a) approved the updated Safeguarding Children, Young People and Adults at Risk of Harm Policy; and (... Approved Open
17 Nov 2026 Finance Performance Report Q2The Cabinet has (1) considered and commented on the General Fund revenue budget’s financial performance in quarter tw... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies