RESOLVED that:- 1. t he Education Cabinet Committee endorses the Expansion Proposals listed below: a) Consult on the significant enlargement of Lower Halstow Primary School from September 2014 through adding 10 places per year group, expanding the school to 1 FE b) Support the Swale Academy Trust’s consultation on the significant enlargement of The Westlands Primary School to permanently expand the school from 2 FE to 3 FE c) Commence the process of commissioning additional Primary education capacity to serve Thistle Hill on the Isle of Sheppey d) The temporary expansion of Eastchurch CE Primary School by increasing the admission number from 60 to 90 for September 2013 and 2014; and 2. the Education Cabinet Committee notes that the decision to issue a public notice on the permanent expansion of Ethelbert Road Primary School would need to be taken outside the Education Cabinet Committee meeting cycle, which was due to time constraints attached to work on the buildings that would need to take place before the 2013 summer holiday period to ensure that the school had the accommodation in place for September 2014.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
By: Patrick Leeson, Corporate Director for Education, Learning and Skills
To: Education Cabinet Committee, 19 March 2013
Subject Primary Commissioning – Swale District
Classification: Unrestricted
Summary: This report updates Members of arrangements in place to ensure sufficient school places are available in Swale, and seek the views of the Education Committee on proposals to commission additional provision.
Recommendations: The Education Committee is asked to endorse the following expansion proposals 1) a) Consult on the significant enlargement of Lower Halstow Primary School from September 2014 through adding 10 places per year group, expanding the school to 1 FE b) Support the Swale Academy Trust’s consultation on the significant enlargement of The Westlands Primary School to permanently expand the school from 2 FE to 3 FE c) Commence the process of commissioning additional Primary education capacity to serve Thistle Hill on the Isle of Sheppey d) The temporary expansion of Eastchurch CE Primary School by increasing the admission number from 60 to 90 for September 2013 and 2014.
2) Members to note that the decision to issue a public notice on the permanent expansion of Ethelbert Road Primary School will need to be taken outside of Education Cabinet Committee. This is due to time constraints attached to work on the buildings that will need to take place before the 2013 summer holiday period to ensure that the school has the accommodation in place for September 2014.
1. Introduction
1.1The Swale section of Kent’s “Commissioning Plan for Education Provision 2012-2017” indicates a need to add a significant number of school places for Swale to manage the increase in numbers of children predicted to come forward.
1.2The pressure on places was managed through temporary expansion for September 2012, adding 110 Year R places across Swale. Permanent expansion of some schools as outlined in the 12 September 2012 report to Education Cabinet Committee is going forward for September 2014. 1.3 A temporary expansion of Eastchurch CE Primary School is being proposed to accommodate two bulge years increasing the intake into Year R from 60 to 90 for September 2013 and 2014.
2. Proposals 2.1 Lower Halstow Primary School
It is proposed to permanently expand Lower Halstow Primary School adding 10 places in Year R from September 2014.
a. Capital: Accommodation will need to be provided for September 2014 with an estimated cost of £275k.
b. Revenue: The school will receive Growth funding for a maximum of three years to provide protection on the increased Year R admission number of 30 should pupil numbers fall short of this. The school will receive £6k for each additional class opened as a result of the expansion towards the cost of the non-staffing resources needed to set the class room up.
c. Human: The school will appoint additional teaching and support staff at the appropriate time.
2.2The Westlands Primary School
The Swale Academies Trust is proposing permanent expansion of The Westlands Primary School from September 2013 increasing the PAN from 60 to 90.
a. Capital: Further discussions have taken place on the permanent expansion of the school by a full 1 FE. The Swale Academies Trust has agreed to take forward the permanent expansion of the school to 3 FE with the EFA. The LA will support the public consultation process. The school has been successful in its bid to the Government’s Priority Schools Building Programme for funding to refurbish the current 2 FE school. Basic Need funding for an extension to the building to provide 3 classrooms as the first phase for September 2013 estimated at £450k.
b. Revenue: As an academy the school receives its funding directly from the government.
c. Human: The school will appoint additional staff.
2.3Eastchurch CE Primary School
A two-year temporary expansion is being proposed for Eastchurch CE Primary School from 2 FE to 3 FE to provide sufficient Year R places for the Eastchurch/Warden Bay locality for September 2013 and 2014.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.