Resolved
RESOLVED that the information set out in the report, and the proposed next steps, be noted, with thanks.
Policy and Resources Cabinet Committee noted this item on Tuesday 13 July 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the information set out in the report, and the proposed next steps, be noted, with thanks.
From: Peter Oakford, Deputy Leader and Cabinet Member for Finance, Corporate and Traded Services
Rebecca Spore – Director of Infrastructure
To: Policy and Resources Cabinet Committee – 13th July 2021
Subject: Construction Partnership Framework Commission
Classification: Unrestricted
Future Pathway of Paper: Policy and Resources Cabinet Committee
Previous Pathway of Paper: Policy and Resources Cabinet Committee – 14 Jan 21
Electoral Division: Countywide
Summary: The Council’s Principal Contractors Framework for construction projects expires in October 2021. Further to the report presented on 14th January 2021 to the Policy and Resources Cabinet Committee, further market engagement has taken place in preparation for the Construction Partnership.
This paper sets out the four options that have been considered and the next steps.
Recommendation(s):
The Policy and Resources Cabinet Committee is asked to Note and report and the proposed next steps.
1. Introduction
1.1On 14 January 2021, a report presented at Policy and Resources Cabinet Committee set out the expiry of the current framework to deliver capital projects in the Council and the need to establish a replacement framework to deliver new construction schemes. Options were considered and a new delivery model was proposed to allow future schemes to be procured expediently and efficiently in line with modern best practice. The Committee supported the further exploration and market engagement to scope further the Construction Partnership Approach.
1.2The proposed construction partnership is an approach whereby, a framework is established with a small number of Contractors to deliver the pipeline of work based on a rotation approach rather than individual mini competitions. If adopted, this will lead to significant change in the way that the Council delivers its construction projects.
1.3Overheads, profit margin and key rates are agreed prior to the implementation of the framework. This will reduce resource duplication across all parties and streamline the route to market compared to the current position. There will be an opportunity to work directly with the reduced supply chain in a partnership approach to deliver against the Council’s outcomes.
1.4There is no workload guarantee in the framework agreement. All schemes awarded to contractors will incorporate their own contract and projects will need to be taken through the appropriate governance process as they are now, where appropriate.
2. Market Engagement
2.1Market engagement was progressed with a number of contractors to explore the following:
Award of work Value for Money Key Performance Indicators (KPI) Contract terms Social Value Risks
2.2Key themes from the market soundings were:
2.2.1. Tendering process with mini competitions can be costly. These take time and can cost up to £50k per procurement exclusive of the Council’s own resources. Opportunities to negate this cost would result in better value schemes, but they identified there could still be a need to compete larger complex schemes.
2.2.2. Any costs evaluated at the Framework tender process should be locked into future work to ensure that Contractors are held to their submitted costs.
2.2.3. All contractors were keen that a robust evaluation process was implemented to measure performance based on time/quality/cost/carbon emissions/social value. A contractor not meeting the required performance level would lose the opportunity to be awarded work, unless they are able to demonstrate and meet an improvement plan to resolve any outstanding issues.
2.2.4. The majority of contractors were supportive to use the New Engineering Contract (NEC) terms which will allow for greater collaboration with the Council. Utilising the options within this suite of documents would allow flexibility dependent on the complexity of the individual scheme.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Construction Partnership Framework CommissionReport | 6 pages | DownloadRead as text |
Follow Policy and Resources Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of the meeting held on 6 May 2026RESOLVED that the minutes of the meeting held on 6 May 2026 were a correct record and that they be signed by the Chai... | Decided | Open |
| 2 Jul 2026 | Local Outcomes FrameworkRESOLVED that the report be noted. | Noted | Open |
| 2 Jul 2026 | Budget Planning Process 2027-28 and Medium-Term Financial Plan (MTFP) UpdateRESOLVED that the report be noted. | Noted | Open |
| 2 Jul 2026 | 26/00032 - Adoption of the KCC Winning for Kent: Procurement with Purpose Policy 2026-2028RESOLVED that the Cabinet Committee endorses the proposed decision to: (a) Approve the adoption and implementation of... | Approved | Open |
| 2 Jul 2026 | Work ProgrammeRESOLVED that the work programme be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.