Policy and Resources Cabinet Committee decided this item on Thursday 24 March 2022. Below is the council's own wording, with the papers it was decided on.
It was RESOLVED that the decision proposed to be taken by the Deputy Leader and Cabinet Member for Finance, Corporate and Traded Services, to:- a) establish the Kent Construction Partnership Framework, to replace the Kent Contractors framework; and b) to authorise the Director of Infrastructure to enter into the necessary legal documents to establish the framework, be endorsed.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Policy and Resources Cabinet Committee, 1 pages
KENT COUNTY COUNCIL – PROPOSED RECORD OF DECISION
DECISION TO BE TAKEN BY: DECISION NO:
Peter Oakford, Deputy Leader and Cabinet Member for Finance, Corporate and Traded Services
For publication
Key decision - Yes
The decision will result in savings or expenditure which is significant having regard to the budget for the service or function (currently defined by the Council as in excess of £1,000,000). Individual projects procured through the framework will be subject to their own appropriate governance and funding process.
Subject Matter / Title of Decision: Construction Partnership Framework Commission
Proposed Decision: As Deputy Leader and Cabinet Member for Finance, Corporate and Traded Services, I agree to establish the Kent Construction Partnership Framework to replace the Kent Contractors framework and to authorise the Director of Infrastructure to enter into the necessary legal documents to establish the framework. Reason(s) for decision: The Council delivers major property infrastructure development which were delivered through the Property Construction Framework which expired in October 2021. This new framework replaces this framework and allows for future schemes to be procured expediently and efficiently.
Cabinet Committee recommendations and other consultation: To be discussed at the Policy and Resources Cabinet Committee, 24th march 2022.
Any alternatives considered: Three other options have been considered:
Option 1 – Extend the Principal Contractor framework Discounted as maximum extensions already taken
Option 2 – Re-procure framework on a like-for-like basis Discounted as pipeline cannot sustain number of contractors going forward and does not address key operational and commercial issues with respect to current framework
Option 3 – Use alternative frameworks Discounted as unlikely to access Kent based contractors and the Council pays a margin for the use of other frameworks Any interest declared when the decision was taken and any dispensation granted by the Proper Officer: None
......................................................................... .................................................................. Signed date
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.