1) That the process in place for managing and monitoring Major Projects be approved. 2) That a new Major Projects Member Board is established. The Member Board will consist of 7 elected members as shown at 2.8 within this report and to include Regeneration and Development Panel. Reason for Decision To provide assurance that the council’s major projects programme is run in accordance with the Major Projects (Officer) Board [1] Terms of Reference. [1] An officer Board, consisting of Executive Directors and representatives from Property Services, Legal, Planning and Finance 1) That the process in place for managing and monitoring Major Projects be approved. 2) That a new Major Projects Member Board is established. The Member Board will consist of 7 elected members as shown at 2.9 within this report Reason for Decision To provide assurance that the council’s major projects programme is run in accordance with the Major Projects (Officer) Board Terms of Reference.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
1.1The Borough Council continues to face significant financial pressures due to reductions in Revenue Support Grant along with greater volatility in income streams, particularly business rates.
1.2To help meet these challenges, a decision was taken in 2016, as part of the Financial Sustainability Plan, to focus not only on achieving revenue cost reductions, but also to identify capital investment
1 An officer Board, consisting of Executive Directors and representatives from Property Services, Legal,
Planning and Finance opportunities to maximize the use of the council’s assets and generate a revenue return, in excess of that achieved from traditional banking investments.
1.3The proposed capital investment focus will help to promote new housing and commercial premises development and drive an increased council tax base, new homes bonus, increased business rates and will help promote local economic activity and business growth. Delivery of new and ongoing revenue streams are key in containing costs and generating additional income as the Council moves towards a position of funding based on locally generated resources.
1.4In addition to the above, some of the council’s Major Projects will help bring forward sites for sale and the capital receipts generated will reduce the council’s borrowing position.
1.5The borough council has an existing programme of projects that are identified within the approved Capital Programme. In addition to this, there are many other projects that are being worked on by a variety of officers, some are operational (e.g. replacing boilers) and are largely “internal”, quickly delivered, or do not involve large sums of money. These types of projects are ‘everyday’ in an organization the size of the council.
1.6However, other projects, outside of largely operational scope, need additional focus particularly as one of the council’s main funding sources, Revenue Support Grant (RSG) is being phased out by Central Government by 2021. This report aims to explain what has already been put into place, and proposes a new member group to provide an appropriate level of oversight.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.