Cabinet, Tuesday 20 January 2026 at 6.00pm

QUARTER 2 - 2025-2026 - PERFORMANCE MANAGEMENT

Agreed Executive 1 paper

AI summaryKing's Lynn and West Norfolk Cabinet reviewed Q2 2025-26 performance: 78% of corporate strategy projects on track, with the growth and prosperity priority at 62% on target. Several major projects are flagged amber, including West Winch housing road and Southgates Masterplan.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreed78% of projects on track, 22% with minor issues, one completed
MoneyNo direct financial implicationsDelivered through existing budgets and programmes [5.1]
What happens nextQ3 actions in progress across prioritiesDetailed actions listed for each project in the report
Who it affectsResidents, council staff and partnersWest Norfolk borough area, four corporate priorities

What was decided

Cabinet reviewed the Q2 2025-2026 Performance Management Report and commented on delivery against the 2023-2027 Corporate Strategy. Report 1.1, 2.1

Cabinet noted the position of each priority: Support our communities 100% on target, Protect our environment 92%, Efficient and effective services 70%, and Promoting growth and prosperity 62%. Report P9, P10, P11, P12

Cabinet noted the position of the key performance indicators, with Protect our environment 100% on target, Support our communities 85%, Efficient and effective delivery 83%, and Promoting growth and prosperity 77%. Report P14, P15, P16

Why

Cabinet must use the management report to review progress on agreed actions and indicators and satisfy itself that performance is at an acceptable level.

Where progress is behind schedule, members can seek additional information to explain variances from targets.

The Corporate Strategy is the council's primary policy document and all other plans must take account of it. Report 4.1

What happens next

Q3 actions are set out for each project, including progressing the West Winch Housing Access Road, completing the Hunstanton Masterplan, and considering the Climate Change Strategy and Action Plan at the 20 January 2026 Cabinet meeting. Report P75, P80, P96

Q2 budget monitoring will be reported to Cabinet on 11 November 2025 with a further update on the savings and efficiency plan. Report P156

Discussions continue on local government reorganisation, with a government decision expected in March or April 2026, and a readiness programme is in development. Report P151

Options considered

  • Chosen: No options considered Report 3.1

Implications

  • Financial: No direct financial implications; delivered through existing services, programmes and budget provisions already in place. Report 5.1
  • Legal: No statutory considerations identified for this report. Report 8.1
  • Equalities: No direct equality considerations, though each project or workstream being reported on has had an EqIA completed. Report 9.1
  • Climate: The strategy includes a priority on protecting the environment and tackling climate change, to be progressed through the climate change strategy and emerging Local Plan. Report 7.1
  • Risk: Progress with corporate strategy actions provides an input for risk management and may identify emerging risks for the corporate, directorate and project risk registers. Report 10.1
  • Staffing: No personnel implications identified. Report 6.1

Who and where

  • Residents of the borough of West Norfolk Report 1.1, 1.2
  • Council staff, including 661 permanent employees Report P191
  • Partner organisations, including Norfolk County Council, the Environment Agency and Anglian Water Report P120, P147
  • Local businesses and SMEs receiving council contracts Report P178
  • Care leavers, equalities groups and users of leisure and culture facilities Report P162, P188

Timeline

  • 23 November 2023: Council approved the 2023-2027 Corporate Strategy Report 1.1
  • 1 April 2025: Transformation Programme launched Report 1.4
  • July 2025: Cabinet adopted the new 2025-2027 Action Plan Report 1.1
  • Q2 2025-2026 (up to 30 September 2025): Performance period being reported on Report 2.2
  • 11 November 2025: Q2 budget monitoring report to Cabinet Report P156
  • 20 January 2026: Cabinet meeting reviewing this performance report and to consider Climate Change Strategy and Action Plan Report P96
  • March/April 2026: Expected government decision on Local Government Reorganisation Report P151

Plain English for the jargon

  • AQMA: Air Quality Management Area
  • CIL: Community Infrastructure Levy
  • EOT: Extension of Time for planning applications
  • EqIA: Equality Impact Assessment
  • IDB: Internal Drainage Board
  • KLEP: King's Lynn Enterprise Park
  • LGR: Local Government Reorganisation
  • MCCA: Mayoral Combined County Authority
  • MTFS: Medium Term Financial Strategy
  • RAG: Red, Amber, Green status indicators used to rate projects and performance
  • REPF: Rural England Prosperity Fund
  • UKSPF: UK Shared Prosperity Fund
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB106

Resolved

The Cabinet reviewed the Performance Management Report and commented on the delivery against the Corporate Strategy. REASON FOR DECISION: Cabinet should use the information within the management report to review progress on the agreed actions and indicators and satisfy themselves that performance is at an acceptable level. Where progress is behind schedule members can seek additional information to explain variances. The Cabinet reviewed the Performance Management Report and commented on the delivery against the Corporate Strategy. REASON FOR DECISION: Cabinet should use the information within the management report to review progress on the agreed actions and indicators and satisfy themselves that performance is at an acceptable level. Where progress is behind schedule members can seek additional information to explain variances.
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Cabinet

Background

1.1The Council’s 2023-2027 Corporate Strategy was approved by Council on 23 November 2023, it sets out the broad framework for the period of the administrative term 2023-2027. In July 2025, Cabinet adopted the new 2025- 2027 Action Plan covering the final period of the Corporate Strategy. It outlines how key activities have been prioritised to deliver our Corporate Strategy and meet the needs of the residents of the borough.

1.2The priority areas are: • Promote growth and prosperity to benefit West Norfolk • Protect our environment • Efficient and effective delivery of our services • Support our communities

1.3These priorities are further defined in 37 objectives and 55 actions that are reflected in the new Executive Team Plans. These actions define what the council will do to achieve the high-level aspirations set out within the corporate strategy.

1.4In addition to the corporate priorities, the Transformation Programme launched on 1st April 2025 will be an additional key area to monitor over the next two years. A quarterly update is included in the Performance Management Report and will cover: • Organisational development • Service innovation and digital transformation • Enterprising our assets

2. Management Report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
QUARTER 2: 2025-2026: PERFORMANCE MANAGEMENTReport 579 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
AB
Councillor Alistair BealesChair, apologies
MD
Councillor Michael de WhalleyCommittee Member, present
AK
Councillor Alexandra KempPresent Under standing Order 34, present
SL
Councillor Susanne LinternCommittee Member, present
JM
Councillor Jim MoriartyCommittee Member, present
CM
Councillor Chris MorleyCommittee Member, present
SR
Councillor Simon RingVice-Chair, present
JR
Councillor Jo RustCommittee Member, present
SS
Councillor Sandra SquireCommittee Member, apologies

On this subject at King's Lynn and West Norfolk

Search all
  1. QUARTER 2 - 2025-2026 - PERFORMANCE MANAGEMENTThis decision
  2. Corporate performance monitoring quarter 2Decided
  3. Cabinet Report - Corporate Performance Monitoring Quarter 2Decided
  4. Corporate performance monitoring - quarter 1 2026-2027Agreed
  5. Cabinet Report - Corporate Performance Monitoring Quarter 1Decided
  6. Quarter 3 performance management reportAgreed

More from King's Lynn and West Norfolk Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 ApologiesAn apology for absence was received from Councillor Moriarty. Decided Open
17 Nov 2026 MINUTESThe minutes from the previous meeting were agreed as a correct record. The minutes from the previous meeting were agr... Agreed Open
17 Nov 2026 Urgent businessNone. Decided Open
17 Nov 2026 Declarations of interestNone. Decided Open
17 Nov 2026 Chair's correspondenceNone. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies