RECOMMENDATIONS FROM CABINET ON 3 FEBRUARY 2026 ON BUDGET ASSOCIATED MATTERS

Agreed Committee 4 papers

AI summaryFull Council approved Cabinet's recommendations on the 2025-2030 capital programme, including new bids, and the 2026/2027 Treasury Management Strategy.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedAmendments and new bids to capital programme 2025-2030, plus Treasury Management Strategy 2026/2027
Money£147,710,250 total capital programme 2025-2030Revised budget to Q2 totals £40,337,890 for 2025/2026
What happens nextProgramme delivery and monitoringReported through monthly monitoring reports
Who it affectsCapital schemes across the boroughCovers housing, regeneration, leisure, operations, ICT and property

What was decided

Council approved amendments to capital schemes and resources for the 2025-2030 capital programme, and the new capital bids listed in Appendix 3 and the exempt report, for inclusion in the programme. Report P34, P35

Council approved the Treasury Management Strategy Statement 2026/2027, including treasury indicators for 2025-2030, the Minimum Revenue Provision Policy Statement and the Annual Investment Strategy 2026/2027.

Why

The financing arrangements for the capital programme are within budget, with rephasing of funding aligned to forecast spend. Report 10.1

Establishment and management of the capital programme align with the Council's Capital, Treasury Management and Investment Strategy. Report P13

Management Team has been consulted on the programme. Report P15

What happens next

Capital programme delivery will be reported through the monthly monitoring report to Members, with any significant scheme variations flagged. Report 11.2

Where rephasing occurs, funding will follow forecast spend, and on-delivery income or cost savings will feed into the revenue budget as achieved. Report 10.1, 10.3

The money

  • £40,337,890 Revised capital budget 2025/2026 to Q2 Report P34
  • £25,383,444 Actual capital spend to December 2025 Report P34
  • £40,337,890 Proposed capital programme 2025/2026 Report P35
  • £70,367,960 Proposed capital programme 2026/2027 Report P35
  • £16,944,630 Proposed capital programme 2027/2028 Report P35
  • £10,690,710 Proposed capital programme 2028/2029 Report P35
  • £9,369,060 Proposed capital programme 2029/2030 Report P35
  • £147,710,250 Grand total proposed capital programme 2025-2030 Report P35

Options considered

  • Chosen: Approve Cabinet recommendations on capital programme and Treasury Management Strategy 2026/2027. Recommendations from Cabinet on 3 February 2026; financing within budget. Report 10.1

Implications

  • Financial: Capital receipts are a high proportion of programme funding; £5m plus £48m from the Major Housing Project is described as a challenging target in current economic conditions, with possible need for additional temporary borrowing if receipts slip. Report P6, P8
  • Risk: Grants funding is medium risk: at 20% of current general fund reserve balance, and depends on annual confirmation from Central Government. Report P5
  • Risk: Major Housing Project is high risk due to market prices and sales pace; a Local Authority Housing Company is in place to hold any surplus units for rent. Report P7
  • Financial: Unsupported borrowing for equipment and vehicles is low risk and will use internal borrowing where financially advantageous. Report P8
  • Risk: Temporary borrowing is medium risk: cost of planned temporary borrowing is included in the revenue budget and confirmed as affordable. Report P8, P9
  • Financial: Reserves contributions are low risk: based on actual balances at 1 April 2025 with budgeted movements. Report P10
  • Risk: Sales values and costs are medium risk: market confidence continues to be impacted by inflation and high interest costs. Report P10

Who and where

  • Residents of the borough, through capital investment in housing, regeneration, leisure facilities, ICT, property and public realm Report P19, P20, P21, P22, P24, P25, P26, P30
  • Council departments delivering the capital schemes, including Regeneration, Housing and Place, Health Wellbeing and Public Protection, Leisure and Culture, Operations and Commercial, Property and Projects, ICT, and Finance Report P19, P20, P21, P22, P24, P25, P26, P27
  • Treasury Management counterparties and external lenders, including PWLB, given the borrowing and investment strategy for 2026/2027 Report P8, P9

Timeline

  • December 2025: Actuals to date on 2025/2026 capital programme: £25,383,444 Report P34
  • 2025/2026 to 2029/2030: Five-year capital programme period covered by the report and approvals Report P35
  • 3 February 2026: Cabinet made recommendations on capital programme and Treasury Management Strategy
  • 26 February 2026: Full Council meeting considering Cabinet recommendations

Plain English for the jargon

  • PWLB: Public Works Loan Board, a UK government body that lends money to local authorities
  • DFG: Disabled Facilities Grants, paid to help adapt homes for disabled occupants
  • Internal borrowing: Use of the council's own short-term cash flows and reserves in place of taking external debt
  • Treasury indicators: Limits and targets set for borrowing, lending and investment activity
  • Minimum Revenue Provision: The minimum amount a council must set aside each year to repay debt
  • S106: Planning obligation payments from developers under Section 106 of the Town and Country Planning Act
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC:104

Resolved

The budget related recommendations from Cabinet held on 3 February 2026 were agreed by Full Council as set out below: CAB121: Capital Programme and Resources 1) Cabinet recommends to Council the amendments to capital schemes and resources for the 2025-2030 capital programme as detailed in the report. 2 2) Cabinet recommends to Council that new capital bids as set out in appendix 3 and the exempt report, are approved to be included in the capital programme 2025-2030 as detailed. CAB122: Treasury Management Strategy, Minimum Revenue Provision Policy Statement and Annual Investment Strategy 2026/2027. Cabinet is asked to recommend that Council approve: · The Treasury Management Strategy Statement 2026/2027, including treasury indicators for 2025-2030. · The Minimum Revenue ... view the full minutes text for item C:104
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Council

REPORT TO CABINET

Partly Exempt Would any decisions proposed: Any Mandatory especially (a) Be entirely within Cabinet’s powers to decide NO affected (b) Need to be recommendations to Council YES Wards None (c) Be partly for recommendations to Council NO and partly within Cabinets powers – Lead Member: Portfolio Holder for Other Cabinet Members consulted: Finance Other Members consulted: E-mail:cllr.chris.morley@west- norfolk.gov.uk Lead Officer: Carl Holland Other Officers consulted: Management Team, E-mail: carl.holland@west- Service Managers norfolk.gov.uk Direct Dial: 01553 616432 Financial Policy/Personnel Statutory Equal Risk Implications Implications Implications Opportunities Management YES YES (incl S.17) Implications Implications NO NO YES If not for publication, the paragraph of Schedule 12A of the 1972 Local Government Act considered to justify that is 16-20.

Date of meeting: 3 February 2026

CAPITAL PROGRAMME AND RESOURCES 2025-2030

Summary This report:  revises the 2025/2026 projections for spending on the Capital Programme  sets out an estimate of capital resources that will be available for 2025-2030  details new capital bids that are recommended to be included in the Capital Programme for the period 2025-2030  outlines provisional figures for capital expenditure for the period 2025-2030

Recommendations It is recommended that: 1) Cabinet recommends to Council the amendments to capital schemes and resources for the 2025-2030 capital programme as detailed in the report. 2) Cabinet recommends to Council that new capital bids as set out in appendix 3 and the exempt report, are approved to be included in the capital programme 2025-2030 as detailed.

Reason for Decision To report amendments, rephasing and resources to the 2025-2030 Capital Programme. 1. Introduction

1.1This report presents the capital programme for the period 2025 to 2030. The Capital Programme forms part of the Council’s longer-term Financial Strategy and is updated as part of the overall budget and council tax setting process.

1.2The Council faces circumstances where capital resources to fund the Capital Programme continue to be limited. There are competing demands for use of these resources, including investment in projects which will deliver revenue savings.

1.3This report sets out a programme for 2025-2030 that can be delivered subject to the outcomes from revised forecasts reflecting continuing changes in costs and capital receipt levels. Certain capital funds come from grants and use of reserves; a large part of funds is to come from anticipated receipts from the Major Housing Development.

1.4The Capital Programme 2025-2030 includes a number of major housing projects, summarised in the table below. The delivery of new homes through this project provides essential funding to support the revenue budget, through increases to the council tax base.

Table 1 – Units to be delivered under Major Housing Schemes.

Units in Current Capital Programme 2025- 2030 Major Housing Lynnsport 1 96 Florence Fields 224 South End Road, Hunstanton 32 352

1.5The Council has set out to deliver as ambitious a Capital Programme as possible to meet its corporate priorities and to deliver new income streams and savings to support the revenue budget and will continue to aim to do so even in these difficult times.

2. Supporting Delivery of the Financial Strategy

2.1The Financial Strategy for 2025-2030 sets out the council’s latest proposed budget over the term of the plan. The Council has previously conducted a deep review of its Earmarked Reserves and Capital Programme to identify any savings. These reviews will continue in future years to identify any opportunities that may arise to help to meet savings targets and/or support the General Fund Reserve. Any revisions will be reported and updated accordingly.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CapitalEstimatesReport20252030 :104Report 886 KB DownloadRead as text
PDF
RECOMMENDATIONS FROM CABINET ON 3 FEBRUARY 2026 ON BUDGET ASSOCIATED MATTERSReport 799 KB Download
PDF
RECOMMENDATIONS TO FULL COUNCIL 26 FEBRUARY 2026 FROM THE CABINET MEETING HELD ON 3 FEBRUARY 2026 :104Report 216 KB Download
PDF
Treasury Strategy 2026-27 Council :104Report 1.4 MB Download

At this meeting

Whole meeting
C:103THE BUDGET, FINANCIAL STRATEGY AND COUNCIL TAX RESOLUTIONOn the agenda
C:104RECOMMENDATIONS FROM CABINET ON 3 FEBRUARY 2026 ON BUDGET ASSOCIATED MATTERSThis decision

Who was there

49 of 55 attended
BA
Councillor Bal AnotaCommittee Member, apologies
BA
Councillor Barry AyresCommittee Member, present
TB
Councillor Thomas BarclayCommittee Member, present
AB
Councillor Alistair BealesCommittee Member, present
SB
Councillor Steven BearshawVice-Chair, present
JB
Councillor Jim BhondiCommittee Member, present
PB
Councillor Paul BlandCommittee Member, present
RB
Councillor Richard BluntCommittee Member, present
FB
Councillor Francis BoneCommittee Member, apologies
AB
Councillor Anthony BubbCommittee Member, present
AB
Councillor Andy BullenChair, present
RC
Councillor Richard CoatesCommittee Member, present

All 55 on the meeting page

On this subject at King's Lynn and West Norfolk

Search all
  1. RECOMMENDATIONS FROM CABINET ON 3 FEBRUARY 2026 ON BUDGET ASSOCIATED MATTERSThis decision
  2. Recommendations from Council Bodies - Cabinet 8 February 2023Approved

More from King's Lynn and West Norfolk Council

All decisions
MeetingDecisionOutcome
29 Oct 2026 MINUTESThe minutes from the meeting held on 24 th September 2026 were agreed as a correct record. Agreed Open
29 Oct 2026 Appointment of honorary alderman and presentation of the engrossments of the resolution and badge of officeThat the title of Honorary Alderman was conferred on former Councillors Carol Bower, Colin Manning, Lesley Bambridge ... Decided Open
24 Sep 2026 MINUTESThe minutes from the meeting held on 29 th July were agreed as a correct record. Agreed Open
24 Sep 2026 Review of proportionalityThat the Membership of the Audit Committee be increased from five Members to Seven Members. 2. That the proportional ... Decided Open