QUARTER 3 PERFORMANCE MANAGEMENT REPORT

Agreed Executive 1 paper

AI summaryCabinet reviewed the Q3 2025-2026 performance report, with 77% of Corporate Strategy projects on track; growth and prosperity was the weakest area at 69%.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCabinet noted and commented on delivery against the Corporate Strategy
MoneyNot stated
What happens nextQ4 project actions to be deliveredDetailed actions set out for each priority
Who it affectsBorough residents and council servicesCovers all four corporate priorities

What was decided

Cabinet reviewed the Performance Management Report and commented on delivery against the 2023-2027 Corporate Strategy.

Why

So Cabinet can satisfy itself that performance is at an acceptable level and seek further information where progress is behind schedule.

What happens next

Q4 project actions are listed across the priorities, including taking the new Climate Change Strategy and Action Plan to Cabinet in April 2026 and continuing the Asset Management Plan work. Report P89

The rebranded LGR Readiness Programme continues with work on data, ICT, finance, HR, contracts and assets in preparation for Local Government Reorganisation. Report 1.4, P120, P123

A further budget monitoring report is due to Cabinet on 3 March 2026, providing a forecast of spend against budget and the savings and efficiency plan. Report P140

Options considered

  • Chosen: No alternative options considered. The report records that no options were considered for this performance review item. Report 3.1

Implications

  • Financial: No direct financial implications; delivery is through existing services, programmes and budget provisions already in place. Report 5.1
  • Risk: Progress against corporate strategy actions will feed into updates of corporate, directorate and project risk registers. Report 10.1
  • Equalities: Each project or workstream has had its own Equality Impact Assessment completed; the report itself raises no direct equality considerations. Report 9.1
  • Climate: Protecting the environment is a corporate priority, delivered through the climate change strategy and the emerging Local Plan. Report 7.1, P85
  • Other: Q3 project status: Protect our environment 84% on target, Support our communities 83%, Efficient and effective delivery 75%, Promoting growth and prosperity 69%. Report 2.4, P9, P10, P11, P12

Who and where

  • Residents of the Borough of King's Lynn and West Norfolk Report 1.1
  • Council staff involved in the Transformation and LGR Readiness Programme Report 1.4, P120

Timeline

  • Late March 2026: Government decision on Local Government Reorganisation for Norfolk expected. Report P134
  • 23 April 2026: Cabinet scheduled to consider the new Climate Change Strategy and Action Plan. Report P89
  • May 2028: Mayoral elections postponed from May 2026 under the devolution programme. Report P131
  • Dec 2028: Target date for adoption of the new Local Plan. Report P105

Plain English for the jargon

  • LGR: Local Government Reorganisation, the programme to create unitary authorities in place of existing district and county councils.
  • KPI: Key Performance Indicator, a measurable value used to track progress against targets.
  • MTFS: Medium Term Financial Strategy, the council's multi-year financial planning document.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB136

Resolved

The Cabinet reviewed the Performance Management Report and comment on the delivery against the Corporate Strategy. REASON FOR DECISION: Cabinet should use the information within the management report to review progress on the agreed actions and indicators and satisfy themselves that performance is at an acceptable level. Where progress is behind schedule members can seek additional information to explain variances.
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Cabinet

Background

1.1The Council’s 2023-2027 Corporate Strategy was approved by Council on 23 November 2023, it sets out the broad framework for the period of the administrative term 2023-2027. In July 2025, Cabinet adopted the 2025-2027 Action Plan covering the final period of the Corporate Strategy. It outlines how key activities have been prioritised to deliver our Corporate Strategy and meet the needs of the residents of the borough.

1.2The priority areas are: • Promote growth and prosperity to benefit West Norfolk • Protect our environment • Efficient and effective delivery of our services • Support our communities

1.3These priorities are further defined in objectives and actions reflected in the Executive Team Plans. These actions define what the council will do to achieve the high-level aspirations set out within the corporate strategy.

1.4In addition to the corporate priorities, the rebranded Transformation Programme launched on 1st April 2025 now known as the LGR Readiness Programme, will be an additional key area to monitor. A quarterly update is included in the Performance Management Report and will cover: • Organisational development • Service innovation and digital transformation • Enterprising our assets

2. Management Report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
QUARTER 3 PERFORMANCE MANAGEMENT REPORTReport 605 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 11 attended
AB
Councillor Alistair BealesChair, present
KB
Kate BlakemoreOfficer, present
JC
Jemma CurtisCouncil Staff, present
MD
Councillor Michael de WhalleyCommittee Member, present
EH
Emma HoddsOfficer, present
SL
Councillor Susanne LinternCommittee Member, present
JM
Councillor Jim MoriartyCommittee Member, present
CM
Councillor Chris MorleyCommittee Member, present
SR
Councillor Simon RingVice-Chair, present
JR
Councillor Jo RustCommittee Member, present
SS
Councillor Sandra SquireCommittee Member, present

On this subject at King's Lynn and West Norfolk

Search all
  1. QUARTER 3 PERFORMANCE MANAGEMENT REPORTThis decision
  2. Corporate performance monitoring quarter 2Decided
  3. Cabinet Report - Corporate Performance Monitoring Quarter 2Decided
  4. Corporate performance monitoring - quarter 1 2026-2027Agreed
  5. Cabinet Report - Corporate Performance Monitoring Quarter 1Decided
  6. Quarter 2 - 2025-2026 - performance managementAgreed

More from King's Lynn and West Norfolk Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 ApologiesAn apology for absence was received from Councillor Moriarty. Decided Open
17 Nov 2026 MINUTESThe minutes from the previous meeting were agreed as a correct record. The minutes from the previous meeting were agr... Agreed Open
17 Nov 2026 Urgent businessNone. Decided Open
17 Nov 2026 Declarations of interestNone. Decided Open
17 Nov 2026 Chair's correspondenceNone. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies