AI summaryCabinet reviewed the Q3 2025-2026 performance report, with 77% of Corporate Strategy projects on track; growth and prosperity was the weakest area at 69%.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedCabinet noted and commented on delivery against the Corporate Strategy
MoneyNot stated
What happens nextQ4 project actions to be deliveredDetailed actions set out for each priority
Who it affectsBorough residents and council servicesCovers all four corporate priorities
What was decided
Cabinet reviewed the Performance Management Report and commented on delivery against the 2023-2027 Corporate Strategy.
Why
So Cabinet can satisfy itself that performance is at an acceptable level and seek further information where progress is behind schedule.
What happens next
Q4 project actions are listed across the priorities, including taking the new Climate Change Strategy and Action Plan to Cabinet in April 2026 and continuing the Asset Management Plan work. Report P89
The rebranded LGR Readiness Programme continues with work on data, ICT, finance, HR, contracts and assets in preparation for Local Government Reorganisation. Report 1.4, P120, P123
A further budget monitoring report is due to Cabinet on 3 March 2026, providing a forecast of spend against budget and the savings and efficiency plan. Report P140
Options considered
Chosen: No alternative options considered. The report records that no options were considered for this performance review item. Report 3.1
Implications
Financial: No direct financial implications; delivery is through existing services, programmes and budget provisions already in place. Report 5.1
Risk: Progress against corporate strategy actions will feed into updates of corporate, directorate and project risk registers. Report 10.1
Equalities: Each project or workstream has had its own Equality Impact Assessment completed; the report itself raises no direct equality considerations. Report 9.1
Climate: Protecting the environment is a corporate priority, delivered through the climate change strategy and the emerging Local Plan. Report 7.1, P85
Other: Q3 project status: Protect our environment 84% on target, Support our communities 83%, Efficient and effective delivery 75%, Promoting growth and prosperity 69%. Report 2.4, P9, P10, P11, P12
Who and where
Residents of the Borough of King's Lynn and West Norfolk Report 1.1
Council staff involved in the Transformation and LGR Readiness Programme Report 1.4, P120
Timeline
Late March 2026: Government decision on Local Government Reorganisation for Norfolk expected. Report P134
23 April 2026: Cabinet scheduled to consider the new Climate Change Strategy and Action Plan. Report P89
May 2028: Mayoral elections postponed from May 2026 under the devolution programme. Report P131
Dec 2028: Target date for adoption of the new Local Plan. Report P105
Plain English for the jargon
LGR: Local Government Reorganisation, the programme to create unitary authorities in place of existing district and county councils.
KPI: Key Performance Indicator, a measurable value used to track progress against targets.
MTFS: Medium Term Financial Strategy, the council's multi-year financial planning document.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB136
Resolved
The Cabinet reviewed the Performance Management Report and comment on the delivery against the Corporate Strategy. REASON FOR DECISION: Cabinet should use the information within the management report to review progress on the agreed actions and indicators and satisfy themselves that performance is at an acceptable level. Where progress is behind schedule members can seek additional information to explain variances.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
1.1The Council’s 2023-2027 Corporate Strategy was approved by Council on 23 November 2023, it sets out the broad framework for the period of the administrative term 2023-2027. In July 2025, Cabinet adopted the 2025-2027 Action Plan covering the final period of the Corporate Strategy. It outlines how key activities have been prioritised to deliver our Corporate Strategy and meet the needs of the residents of the borough.
1.2The priority areas are: • Promote growth and prosperity to benefit West Norfolk • Protect our environment • Efficient and effective delivery of our services • Support our communities
1.3These priorities are further defined in objectives and actions reflected in the Executive Team Plans. These actions define what the council will do to achieve the high-level aspirations set out within the corporate strategy.
1.4In addition to the corporate priorities, the rebranded Transformation Programme launched on 1st April 2025 now known as the LGR Readiness Programme, will be an additional key area to monitor. A quarterly update is included in the Performance Management Report and will cover: • Organisational development • Service innovation and digital transformation • Enterprising our assets
2. Management Report
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.