Maldens and Coombe Neighbourhood decided this item on Wednesday 16 January 2008. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the remaining funding in the housing discretionary budget be allocated to: (i) additional communal glazing works to be concentrated at locations in the Sheephouse Way / South Lane area and on the Kingsnympton Estate; and (ii) the upgrade of CCTV equipment at Norton and Martin House, Charnwood Close (funding in the region of £2,500). Reason for the decision To allow the discretionary budget allocated to the Committee to be spent on works which will be deliverable within the programme budget and time constraints and which reflect the needs of local residents.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
At its meeting of 13 June, the Committee’s views were sought on how its housing discretionary funding of £42,500 could best be allocated to schemes for the improvement of housing estates in the neighbourhood. The Committee identified that priority should be given to glazing and lighting in communal areas, and repaving pathways to prevent accidents and facilitate access. At its meeting on 27 November the Committee received an information report listing schemes and current estimated costs for those schemes. The current cost of one of the schemes (parking at Norton and Martin House) exceeds the cost previously estimated and could therefore not be afforded within the budget for the programme of works. It is therefore proposed to exclude that scheme, and Members are requested to identify an alternative scheme(s) to which the resulting funding (£13,300) could be allocated.
Recommendation
It is RECOMMENDED that the Committee advises which scheme(s) it wishes to see progressed (ref para.5 of the report).
Reason for recommendation
To allow the discretionary budget allocated to the Committee to be spent.
Background
1. At is June meeting the Committee considered a report requesting that they allocate £42,500 of Housing Revenue Account funds to schemes to contribute to the improvement of the Council’s Housing stock in their neighbourhood.
2. Attached at ANNEX 1 is a list of the schemes reported to the Committee at its meeting on 27 November, which has been updated with current costings and with the progress of the works to date.
UPDATE
3. Members will note that considerable progress has been made to date in completing several of these schemes, although several remain outstanding. In particular, areas of resurfacing are delayed, as these works have been allocated to RJ Dance, the Council’s highways contractor, in order to give better value for money. However, as the housing work is of a small scale and are not in the overall highways programme, the work is carried out on an as-and-when basis. If progress has not been achieved by the end of January, the work will instead be allocated to Mears to progress. It is hoped that this will have only a marginal impact on costs. J2
4. Members will also note that, whilst it has an available budget of £42,500, the cost of all the works identified now amounts to a total of £54,200. This is primarily due to the cost of proposal to use the redundant drying area to the rear of Norton and Martin Houses for additional parking at a cost of £25,000. This is clearly a very expensive scheme and, whilst it gives benefits to the local residents, its costs may be out of proportion to its benefits. In addition, the site is one that will be considered as part of an overall review of Council assets as it has some development potential.
5. If the works to the Norton and Martin redundant drying area are excluded, the Committee would have a total of £13,300 to allocate to alternative projects. Listed below are locations previously prioritised by the Committee at its meeting on 13 June where works are required, together with updated costings. Alternatively, since Members in June gave significant priority to reglazing projects in the neighbourhood, the £13,000 could be allocated to additional communal glazing works, which works would be deliverable within the programme budget and time constraints.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Maldens and Coombe Neighbourhood at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Appointment of the Chair and Vice-ChairRESOLVED that Councillor Simon Edwards be appointed Chair and Councillor Lesley Heap be appointed Vice-Chair for the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.