Maldens and Coombe Neighbourhood decided this item on Wednesday 16 January 2008. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the confirmed budget be split equally between footways and carriageways and that the priority of the schemes to be included in the 2008/09 planned maintenance programme be as contained in the Annex to these Minutes (which is the amended Annex to the report), with the exception of Kneller Road carriageway which will be priority number 10. Reason for the decision So that the planned maintenance schemes for 2008/09 can be determined and Officers proceed with the management and implementation of the highway maintenance programme.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
This report updates the Committee on the progress being made to reduce the backlog of carriageway and footway maintenance works. It includes information regarding the relevant Best Value Performance Indicators (BVPI’s) for the Borough as a whole and for each Neighbourhood. The prescribed method of surveys and analysis to be used is UKpms (United Kingdom pavement management system). This information is being used to identify the needs, priorities and type of the works necessary to achieve the Borough’s required performance targets. Although progress has been made with regard to carriageways, the extent and rate of progress in dealing with footways is less encouraging. The report also lists, in Annex 1, the footway and carriageway works, within each Neighbourhood, where it is recommended funding is allocated. The Committee is asked to select the works they wish to be included in the 2008/09 planned maintenance programme.
Recommendation
It is RECOMMENDED that the Committee approve,from the prioritised list in ANNEX 1, the footway and carriageway works they wish to be included in the planned maintenance programme for 2008/2009.
Reason for recommendation
So that the planned maintenance schemes for 2008/09 can be determined and Officers proceed with the management and implementation of the highway maintenance programme.
Background
1. Due to budget constraints, from the mid 1980’s to the late 1990’s, a large backlog of maintenance works developed for both carriageways and footways. In order, initially, to address this situation the Council is taking advantage of Prudential Borrowing to enable an additional capital investment of £2m per year.
APPORTIONMENT OF CAPITAL BUDGETS
2. The 2001 District Audit of Highways Maintenance, the Transport and Infrastructure Overview Panel annual scrutiny of Highway Maintenance and the 2004 CPA Audit Commission Inspection of Transportation, all questioned the sustainability of addressing the unequal backlog in the Neighbourhoods by allocating equal budgets. To address this weakness, the works backlog in each Neighbourhood is being measured, using BVPI/UKpms methods, and this is used to inform the amount of capital funding allocated to each Neighbourhood. E2
3. The following table shows the current situation:
Carriageways Busy Footways 2007/08 2008/09 2007/08 2008/09 Borough-wide 9% 8% 34% 30% Kingston Town 6% 6% 21% 21% Maldens & 13% 11% 43% 34% Coombe South of the 9% 8% 36% 28% Borough Surbiton 5% 8% 42% 40%
4. The capital budget is split 50% to carriageways and 50% to footways. Each half is then apportioned on the basis of the defective length in each Neighbourhood, compared with the total defective length in the borough as a whole. The two amounts will then be added together to determine the total capital apportionment for each Neighbourhood.
Anticipated Budget for Neighbourhood Allocation
5. Although the Council has not set its overall budget for 2008/2009, the anticipated planned maintenance budgets for next year are:
Revenue
Neighbourhood revenue budget for planned maintenance = £107,200
Capital
Neighbourhood Capital = £616,000
Total £723,200
Best Value Performance Indicators (BVPI’s)
6. The Council is obliged to publish national BVPI’s (Best Value Performance Indicators) for Principal (223), Non-principal Classified and Unclassified Roads (224 a & b) and for Class 1 & 2 Footways (187). The prescribed method of surveys and analysis to be used is the UKpms (United Kingdom pavement management system). BVPI 223, for Principal Road carriageways, is based upon the London- wide SCANNER survey commissioned and paid for by TfL. For BVPI 224 a & b and BVPI 187, UKpms surveys are commissioned and funded by the Borough.
7. The results for the past years for the whole Borough are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Maldens and Coombe Neighbourhood at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Appointment of the Chair and Vice-ChairRESOLVED that Councillor Simon Edwards be appointed Chair and Councillor Lesley Heap be appointed Vice-Chair for the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.