RESOLVED that 1. the position be noted; 2. the changes to the Capital Programme as detailed in paragraphs 15 to 17 and annexes 4 and 5 of Appendix G of the agenda be noted; and 3. the action being taken by the Strategic Leadership Team (formerly CDT) to ensure that the budget is not overspent be endorsed. Reason for decision To ensure that the Council’s expenditure remains within the approved budget.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
1. The Council approved the budget for 2008/09 at its meeting on 27 February 2008. In doing so, it took account of continuing pressure on some demand and needs-led budgets and increased the budget in those areas for 2008/09 budget accordingly. It also included some of the savings which had been achieved during 2007/08 through restraint on recruitment and non-staff expenditure to reduce the Council’s budget. To prepare for the financial challenges identified in the medium term plan “destination Kingston 2011” and to facilitate some of the budget reductions which will be required in 2009/10 and beyond, restraint on recruitment and non-staff expenditure continue to be in place, and these will deliver in-year budget savings during 2008/09. G2
2. On 22 July 2008, the Executive considered an initial summary of the position for 2008/09, informed by the financial/budget risk analysis which formed part of the supporting information to the medium term plan “destination Kingston 2011”. This work concentrated on large income and expenditure budgets, those which are demand-led and also those areas where the outturn for 2007/08 had indicated that there could be significant budget pressures in 2008/09. The risk analysis continues to be used as part of the process for carrying out detailed budget monitoring.
3. The initial analysis (22 July 2008) reported pressures totalling approximately £0.75 million, offset in part by additional income of £0.25 million.
4. The position at month 4 (reported to the Executive on 30 September 2008) indicated that there was a potential net overspending of £72,000.
5. The position at month 6 (reported to the Executive on 9 December 2008) indicated that there was a potential net underspending of £157,000.
LATEST POSITION
6. The position at month 8 is that a potential net underspending of £276,000 is now forecast. This is summarised at Annex 1. The main variations are detailed in Annex 2 and explained in the following paragraphs.
7. Community Services
(i) Community Care Services
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.