RESOLVED that: 1) the forecast outturn position in respect of the General Fund for 2023/24 be noted; 2) the 2023/24 forecast outturn position on the Housing Revenue Account be noted; 3) the forecast in respect of the Schools Budget and the Dedicated Schools Grant (DSG) for 2023/24 be noted; 4) the forecast outturn position in respect of the capital programme for 2023/24 be noted; 5) Subject to approval of proposals in relation to the Main Guildhall/Future Work Programme elsewhere on this agenda, a capital expenditure budget of £1.440m be approved for Main Guildhall Refurbishment to bring the project to RIBA stage 3, as detailed in paragraph 9; 6) Capital expenditure budget of £3.312m for 2023-24 to acquire an additional 104 social homes being developed through the regeneration of the Cambridge Road Estate (CRE) as detailed in paragraph 10 be approved.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
To report the revenue and capital monitoring forecast outturn positions for 2023/24 as at month 9.
Recommendation (s)
The Committee is asked to RESOLVE that: 1. the forecast outturn position in respect of the General Fund for 2023/24 be noted;
2. the 2023/24 forecast outturn position on the Housing Revenue Account be noted;
3. the forecast in respect of the Schools Budget and the Dedicated Schools Grant (DSG) for 2023/24 be noted;
4. the forecast outturn position in respect of the capital programme for 2023/24 be noted;
5. Subject to approval of proposals in relation to the Main Guildhall/Future Work Programme elsewhere on this agenda, a capital expenditure budget of £1.440m be approved for Main Guildhall Refurbishment to bring the project to RIBA stage 3, as detailed in paragraph 9;
6. Capital expenditure budget of £3.312m for 2023-24 to acquire an additional 104 social homes being developed through the regeneration of the Cambridge Road Estate (CRE) as detailed in paragraph 10 be approved.
Benefits to the Community:
This report sets out the forecast year end financial position. The transparent reporting of this position enables the community to carry out greater scrutiny of the use of public funds. Key Points
A. The Council approved its Medium Term Financial Strategy for 2023/24 to 2026/27 and detailed budget for 2023/24 at Budget Council on 2 March 2023. Inflation remains high in the UK in 2023, although it has reduced from its highest level in 40 years in October 2022 (11.1%). For December 2023, inflation was at 4.0%, a small increase of 0.1% from November’s rate of 3.9%. Whilst inflation has fallen since the highs seen in Autumn 2022, it is still twice as high as the Bank of England target of 2%. This continues to affect residents and businesses across the country, with local government significantly impacted too.
B. For Kingston, the impact of high inflation is reflected in the month 9 (31st December 2023) forecast outturn position for both revenue and capital expenditure which is detailed throughout this report. This economic uncertainty and high inflation is not limited to the current year and the ongoing impact on the MTFS will also be significant, although the Bank of England forecast inflation to fall further in 2024 and reach its target by early 2025.
C. The 2023/24 forecast general fund revenue outturn position at month 9 is an overspend of £3.017m, against the budget of £161.296m. This is a small increase in the overspend reported at month 6, which was £2.876m. The reasons for the overspend are set out in detail within the main body of the report, but sector wide demand pressures in adults and children's social care, as well as temporary accommodation are the most significant factors, alongside the conditions in the wider economy - i.e. the impact of continuing high inflation. This has been partly mitigated through higher than budgeted income from interest on cash balances and the release of some bad debt provisions in line with revised estimates of debt collection.
D. In order to more closely monitor the delivery of savings plans in year, and in line with the process used in previous years, budget managers have been asked to provide a Red, Amber or Green (RAG) rating for all savings proposals. At month 9, of the £8.504m planned savings, £6.109m were rated Green (on track to be delivered in full), £2.060m rated Amber (delayed or delivered only in part) and £0.335m rated Red (no longer deliverable).
E. The Council has made good progress in recent years to increase general fund balances from historic lows to a more appropriate level for an authority of this size with the general fund balance expected to be maintained at £19.633m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Council Plan End of Year Report 2025/26RESOLVED that: 1) The End of Year Report for 2025/26, at Annex 1 to the report, be noted. 2) The newly published Loca...
Leader of the Opposition OptionsRESOLVED that: Having considered the options outlined in the report, Option 1 (the status quo) be adopted as the pref...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.