RESOLVED that: 1. the forecast outturn position in respect of the General Fund for 2024/25 be NOTED ; 2. the management actions that have been implemented to help mitigate the in year forecast overspend be NOTED ; 3. the 2024/25 forecast outturn position on the Housing Revenue Account be NOTED ; 4. the forecast in respect of the Schools Budget and the Dedicated Schools Grant (DSG) for 2024/25 be NOTED ; 5. the forecast outturn position in respect of the capital programme for 2024/25 be NOTED ; 6. a total increase of £5.348m for the New Kingston Leisure Centre budget funded from Prudential Borrowing as outlined in paragraph 42 of the report be APPROVED ; and 7. an increase of £0.822m in the CCTV Budget Funded from GLA Grant (£0.150m) and Prudential Borrowing (£0.672m) for 2025-26 as detailed in paragraph 38a of the report be APPROVED .
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Revenue and Capital Budget Monitoring 2024/25 as at Month 9
Report by Sue Cuerden, Executive Director of Corporate Services (S151 Officer)
elevant Portfolio Holder: Councillor Richard Thorpe, Portfolio Holder for Finance, Assets R & Governance
Purpose of Report
o report the revenue and capital monitoring forecast outturn positions for 2024/25 as at T month 9 (31 December 2024).
Recommendation(s)
The Committee is asked to RESOLVE that:
1. the forecast outturn position in respect of the General Fund for 2024/25 be NOTED;
2. the management actions that have been implemented to help mitigate the in year forecast overspend beNOTED;
3. the 2024/25 forecast outturn position on the Housing Revenue Account be NOTED;
4. the forecast in respect of the Schools Budget and the Dedicated Schools Grant (DSG) for 2024/25 beNOTED;
5. the forecast outturn position in respect of the capital programme for 2024/25 be NOTED;
6. total increase of £5.348m for the New Kingston Leisure Centre budget funded a from Prudential Borrowing as outlined in paragraph 42 of the report be APPROVED; and
7. n increase of £0.822m in the CCTV Budget Funded from GLA Grant (£0.150m) a and Prudential Borrowing (£0.672m) for 2025-26 as detailed in paragraph 38aof the report beAPPROVED.
Benefits to the Community:
his report sets out the forecast year end financial position for 2024/25. The transparent T reporting of this position enables the community to carry out greater scrutiny of the use of public funds. Key Points
A. he Council approved its Medium Term Financial Strategy for 2024/25 to 2027/28 T and detailed budget for 2024/25 at Budget Council on 29 February 2024.
B. he 2024/25 forecast general fund revenue outturn position at month 9, 31 T December 2024, is an overspend of £6.4m, against the budget of £178.38m. The reasons for the overspend are set out in detail within the main body of the report, but sector wide demand pressures in adults and children's social care, as well as temporary accommodation are the most significant factors, alongside the conditions in the wider economy.
C. elivery of planned savings during the year is essential to support the monitoring D position. As such, these are reviewed as part of the monthly process and budget managers are asked to provide a Red, Amber or Green (RAG) rating for all savings proposals. In a change for the presentation at month 9, a category of Blue has been added to represent savings which have been fully delivered in year. At month 9, of the £8.23m planned savings, £5.43m is now classed as being fully delivered, with a further £0.88m on track to be delivered by the end of the year. There are savings totalling £1.69m which are classed as Amber, where savings have been delayed but are still achievable, with £0.23m savings classed as undelivered.
D. he Council has made significant progress in recent years to augment general fund T balances from historically low levels to a more sustainable position for an authority of this scale. The general fund balance currently stands at £19.63 million. Whilst mitigations, as detailed later in the report have been put in place, with further consideration being given of how to further reduce the in year position, it should be noted that the risks associated with the projected overspend position may necessitate the utilisation of appropriate reserves or this balance if the outturn position does not demonstrate a substantial reduction. Any use of reserves or the general fund balance will need to be reinstated over the medium term to ensure the ongoing financial sustainability of the authority.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Council Plan End of Year Report 2025/26RESOLVED that: 1) The End of Year Report for 2025/26, at Annex 1 to the report, be noted. 2) The newly published Loca...
Leader of the Opposition OptionsRESOLVED that: Having considered the options outlined in the report, Option 1 (the status quo) be adopted as the pref...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.