RESOLVED that the predicted overspend be met from a combination, as appropriate, of the following: 1. Scheme Amount to be saved Library Discretionary Fund £650 Neighbourhood Ranger £2,350 Christmas Lights £1,200 Management and Operations £1,500 Community Engagement £2,745 Neighbourhood Action Days £500 Community Pay Back £2,850 Total to be saved £11,795 2. the sum of £4,500 be allocated from the Neighbourhood Discretionary and Environmental Initiative budget for 2009/10 to provide hanging baskets in Surbiton Town Centre during summer 2009; and 3. a contingency of £3,000 be allocated from the Neighbourhood Discretionary and Environmental Initiative budget for 2009/10 to meet the potential shortfall in the funding for the Information Board to be provided at Surbiton Station Forecourt, in the event that sponsorship for the board be not forthcoming. REASON FOR DECISION To manage the current year’s revenue budgets and to ensure that the 2008/09 budget is not overspent and to ensure that funding for projects to be implemented in 2009/10 which, for practical reasons, need to be considered before the new financial year starts, is agreed.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Surbiton Neighbourhood Committee has identified an overspend since the beginning of the financial year 2008/09. The latest position, reported to this Committee on 11th February 2009, showed the predicted outturn to be an overspend of £7,850. As required under the Neighbourhood Budgeting Code of Practice, the Neighbourhood is required to contain its expenditure against its overall budget. This report identifies expenditure which remains uncommitted and can be used to offset the predicted overspendings and to bring the budget back into a break even position.
Recommendations
It is RECOMMENDED that the Committee identifies which schemes and projects should be put on hold until the budget is brought back into a break even position.
Reason for recommendations
To manage the current year’s revenue budgets and to ensure that the 2008/09 budget is not overspent.
Background
1. Due to the pressures within the Library Services budget, there has been, since the start of the year, a projected overspend for this Neighbourhood Committee’s overall budget.
2. In accordance with the Neighbourhood Budgeting Code of Practice, the Neighbourhood is required to contain any overspend within it’s overall budget. At the last meeting of this Neighbourhood Committee, the following advice was given:
“Tight financial control is being exercised by all budget holders in order to minimise the overspend. In addition, the list of projects approved by the Neighbourhood Committee to be funded from its Discretionary and Environmental Initiative Budget has been reviewed as part of the on-going expenditure monitoring process. A number of items, not yet implemented, have been identified as potential savings that could be put forward either entirely or in part. These include:
• the provision of new cycle racks - £3,000 • community pay back - £3,000 • neighbourhood action days - £500 and • the replacement of street tree grills with fixed gravel covers in Victoria Road – £2,700.”
3. If the Committee had agreed the officer recommendation to put the identified projects on hold, it would have generated savings of £9,200 which would have covered the projected overspends. These have remained ‘on hold’ pending the decision of this Committee.
4. However, the Committee asked that: “further details on areas where the budget may have been allocated but not fully spent be considered at the next meeting on 11 March 2009 to determine proposals to meet the forecast overspend”
5. Budget holders have once again reviewed their budgets which have not been contractually committed, and have identified the following which total £20,640:
Library Services
1. Discretionary Fund £650 Out of the full £4,500 allocated, £1,250 has already been handed back as part of the budget restraint in Month 6 monitoring. Currently, there is still £857 uncommitted, although the libraries Manager would like to retain £200 for plants for the new planters at the front of Surbiton Library in March when spring bulbs and plants will be available and complete the improvements works. 2. Book Fund £3,600 This uncommitted amount is mainly from the Children's book fund budget, and would have been spent on non-fiction for the Surbiton Homework Club and spoken word for the teenage collection at Tolworth. In terms of impact on the service, at this stage in the financial year it will mean that there will be fewer new items of stock for children and young people to borrow at Surbiton and Tolworth libraries. The two main children’s publishing peaks are in the run up to Christmas and spring which will coincide with the beginning of the new financial year.
Environmental Services
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Surbiton Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Appointment of Chair and Vice-ChairRESOLVED that: 1. Councillor Tom Reeve be appointed Chair of the Committee for the Municipal Year 2026/27 until the f...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.