PLANNED HIGHWAY MAINTENANCE 2012/2013

Agreed Committee 3 papers

Kingston Town Neighbourhood Committee agreed this item on Tuesday 7 February 2012. Below is the council's own wording, with the papers it was decided on.

Item48

Resolved

RESOLVED that 1. the following works are undertaken as part of the 2012/13 maintenance programme: Carriageway Schemes: Priority Location Details Estimated cost 1 Eden Street Brook Street to Lady Booth Road - deep plane and resurface £62,630 2 Beresford Road Whole road - plane and resurface £23,500 3 St Georges Road Whole road - plane and resurface £11,500 4 Park Rd/Tudor [name removed] sealing £10,000 Sub Total: £107,630 Footway Schemes: Priority Location Details Estimated cost 1 Fife Road North side - Replace existing blocks with “perfecta” small element paving £58,630 2 Fife Road South side - Replace existing blocks with “perfecta” small element £62,000 3 Cambridge Road Gloucester Road to eastern end of Cambridge Gardens - reconstruct bitmac. 120m of kerbing £41,000 4 Cambridge Road Remaining bitmac area to London Road - reconstruct bitmac £27,500 5 Eden Street No. 4 to St James Road - Replace existing blocks with York stone paving £32,500 SubTotal: £221,600 Total: £329,260 2. the reserve planned maintenance schemes are those listed: carriageways nos 5-8 and footways nos 6-8. REASON FOR DECISION To agree the maintenance works programme for 2012/13 to enable the programme to be prepared, managed and implemented.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Kingston Town Neighbourhood Committee

Recommendations

It is RECOMMENDED that the Committee determine, within budgetary limits, the works they wish to be to be undertaken as part of the 2012/13 maintenance programme and to nominate reserve schemes, as appropriate, from the prioritised lists in Annex 1.

Reason for recommendations

To determine the maintenance works programme for 2011/12 to enable the programme to be prepared, managed and implemented.

Background

2011/2012 Programme

1. The following schemes, funded by the Neighbourhood’s Planned Maintenance Budget, have been completed as part of the 2011/2012 planned maintenance programme:-

Footway

Priority Location Details 1. Dysart Avenue Both sides – relay/replace slabs 2. Queens Road Relay/replace slabs where required 3. Portsmouth Road South Lane to Wight House – reconstruct bitmac

Carriageway

Priority Location Details 4. Latchmere Road Staunton Road to Roundabout – plane and resurface incl. replacement speed hump. 5. Barnfield Avenue Each end for 100m – plane and resurface 6. East Road Whole road – plane and resurface 7. St James Road Part funding to plane and resurface 2. The following are additional schemes, funded on a Boroughwide priority within the Neighbourhood:

Footway

Priority Location Details 8. Bath Passage Reconstruct 9. Ely Court/ Contribution to Neighbourhood Engineer’s access Washington Road improvements footpath

Carriageway

Priority Location Details 10. Barnfield Avenue Contribution to enable whole of road to be planed and resurfaced 11. St James Road Contribution to enable whole road to be planed and resurfaced

3. The following carriageway resurfacing schemes were funded by TfL as part of the LIP settlement:

Priority Location Details 1. A2043 Malden Road Cancelled due to pending Gas Main replacement 2. A2043 Malden Road Idmiston Road to Station Approach 3. Kingston Road Dickerage Road to South Lane - patching 4. Kingston Road Fountain Roundabout to South Lane – patching, part resurfacing, joint sealing 5. Kingston Road Short length at junction with St Johns Road 6. Cambridge Road Outside Cambridge Court (Pedestrian Crossing) 7. London Road Park Road Roundabout and to railway bridge

National Performance Indicators

4. Prior to 2008/09 the Council was obliged to publish Best Value Performance Indicators (BVPI’s) for Principal (223), Non-principal Classified and Unclassified Roads (224 a and b) and for Class 1 & 2 Footways (187). The prescribed method to use for the surveys and analysis was UKpms (United Kingdom pavement management system). BVPI 223, for Principal Road carriageways, was based upon the London-wide SCANNER survey commissioned by Transport for London (TfL) as part of the Road 2000 Project. BVPI 224 a & b and BVPI 187 UKpms surveys were commissioned and funded by the Borough.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PLANNED HIGHWAY MAINTENANCE 2012/2013Report 78 KB DownloadRead as text
PDF
axPlanned Highway Maintenance: Annex 2Appendix 120 KB Download
PDF
axPlanned Highway Maintenance: Annex1Appendix 52 KB Download

At this meeting

Whole meeting

Who was there

11 of 12 attended
GA
Councillor Geoff AustinMember, present
SB
Councillor Stephen BristerMember, present
AC
Councillor Andrea CraigMember, present
DC
Councillor David CunninghamMember, present
TD
Councillor Tim DennenMember, present
DD
Councillor Dennis DoeMember, present
CH
Councillor Chrissie HitchcockVice-Chair, present
BO
Councillor Barry O'MahonyMember, present
DR
Councillor David Ryder-MillsChair, present
PS
Councillor Penny SheltonMember, present
FT
Councillor Frank ThompsonMember, present
MW
Councillor Marc WoodallMember, apologies

On this subject at Kingston upon Thames

Search all
  1. PLANNED HIGHWAY MAINTENANCE 2012/2013This decision
  2. Planned Highway Maintenance and Street Lighting Capital Programme 2026/27Approved
  3. Planned Highway Maintenance and Street Lighting Capital Programme 2026/27Noted
  4. Planned Highway Maintenance and Street Lighting Capital Programme 2025/26Approved
  5. Planned Highway Maintenance and Street Lighting Capital Programme 2024/25Approved
  6. Planned Highway Maintenance and Street Lighting Capital Programme 2023/24Approved

More from Kingston upon Thames Kingston Town Neighbourhood Committee

All decisions
MeetingDecisionOutcome
8 Mar 2022 MinutesRESOLVED that the minutes of the meeting held on 26 January 2022 be signed as a correct record. Decided Open
8 Mar 2022 GrantsRESOLVED to award a Neighbourhood Community Grant of £3,000.00 to the BRaG Residents Association towards the costs of... Decided Open
26 Jan 2022 MinutesRESOLVED that the minutes of the meetings held on 2 November 2021 and 2 December 2021 be signed as a correct record. Decided Open
26 Jan 2022 Neighbourhood GrantsRESOLVED to award a Neighbourhood Community Grant of £2,700.00 to the Hogsmill Community Garden towards the costs of ... Decided Open
26 Jan 2022 Making Princes Road and Alexandra Road School Streets PermanentRESOLVED that: 1. Princes Road School Street and Alexandra Road School Street experimental Traffic Management Orders ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies