Planned Highway Maintenance

Noted Committee 4 papers

Surbiton Neighbourhood Committee noted this item on Wednesday 12 February 2014. Below is the council's own wording, with the papers it was decided on.

Item54

Resolved

RESOLVED that 1. the current status of schemes from the 2013/14 Planned Highway Maintenance programme (ANNEX 1 of the report) is noted. 2. the updated list of schemes to be undertaken as part of the 2014/15 Planned Highways Maintenance programme (ANNEX 2 of the report) is approved. 3. the updated three year indicative list of programmed works (ANNEX 3 of the report) is amended to include the footways on Broomfield Road. Voting: Unanimous. REASON FOR DECISION To enable the annual Planned Highways Maintenance programme for 2014/15 to be further developed, managed and implemented.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Surbiton Neighbourhood Committee

Recommendations

It is RECOMMENDED that

1. The current status of schemes from the 2013/14 Planned Highway Maintenance programme (Annex 1) be noted.

2. The updated list of schemes to be undertaken as part of the 2014/15 Planned Highways Maintenance programme (Annex 2) be approved.

3. The updated three year indicative list of programmed works (Annex 3) be noted

Reason for recommendations

To enable the annual Planned Highways Maintenance programme for 2014/15 to be further developed, managed and implemented.

Background

1. Valued at over £800m, the local authority’s highway network is the most valuable asset for which it is responsible. The main purpose of highway maintenance is to maintain the highway network to a condition that delivers sufficient capacity for the safe and convenient movement of people and goods. It is also important to ensure that the roads remain watertight and that the highway drainage system work efficiently to protect the asset and minimise the risk of flooding. Highway maintenance work is also necessary to reduce the Highway Authority’s risk of exposure to claims for injury and damage caused by defects. Highway maintenance work is identified through a combination of structural assessment and visual inspection.

2. Customer surveys in the borough and elsewhere have consistently shown the importance of the condition of the highway network to residents and businesses. This results in a high demand for works to be carried out to repair and maintain the network.

3. In recent years, funding available for the whole of the borough has enabled 30 to 40 carriageways to be resurfaced and 10 to 20 footways to be reconstructed each year. However, there are over 1000 roads within the borough, and at this rate of repair/reconstruction, carriageways would only be resurfaced once every 25 years and footways reconstructed once every 50 years.

4. ANNEX 1 indicates the current status of the carriageway and footway schemes in the 2013-14 planned highway maintenance programme approved by the committee in February 2013 and any principal road schemes that have been approved for funding by Transport for London.

HIGHWAY MAINTENANCE PROGRAMME DEVELOPMENT

5. This year, a two-stage approach was taken to the development of the Planned Highway Maintenance programme. The first stage, in November, presented a long list of streets, in priority order, for inclusion in the programme. These were prioritised using the factors outlined in paragraphs 7-9. This report is the second stage of the process. Following Member feedback Annex 2 and 3 have been updated (schemes identified for action by members are marked as “NEW”). The cumulative cost of the priority schemes is now included in Annex 2 to take into account the expected budget for the Highway Maintenance Programme.

6. The benefits of the two stage approach were:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Planned Highway Maintenance (ANNEX 1)Appendix 52 KB Download
PDF
Planned Highway Maintenance (ANNEX 2)Appendix 59 KB Download
PDF
Planned Highway Maintenance (ANNEX 3)Appendix 44 KB Download
PDF
Planned Highway MaintenanceReport 83 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
JA
Councillor John AylesMember, present
MB
Councillor Michael BurdenMember, present
JB
Councillor John BurgessVice-Chair, present
KG
Councillor Karen GeorgeMember, present
LG
Councillor Liz GreenMember, present
MH
Councillor Mary HeathcoteMember, present
NH
Councillor Neil HoustonMember, present
RH
Councillor Richard HudsonMember, present
MS
Councillor Malcolm SelfChair, present
BS
Councillor Bob SteedMember, present
YY
Councillor Yogan YoganathanMember, apologies

On this subject at Kingston upon Thames

Search all
  1. Planned Highway MaintenanceThis decision
  2. Planned Highway Maintenance and Street Lighting Capital Programme 2026/27Approved
  3. Planned Highway Maintenance and Street Lighting Capital Programme 2026/27Noted
  4. Planned Highway Maintenance and Street Lighting Capital Programme 2025/26Approved
  5. Planned Highway Maintenance and Street Lighting Capital Programme 2024/25Approved
  6. Planned Highway Maintenance and Street Lighting Capital Programme 2023/24Approved

More from Kingston upon Thames Surbiton Neighbourhood Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Community Grants ProgrammeRESOLVED that: ( i ) the application for a £2,800 Neighbourhood Community Grant from Surbiton Town Centre Partnership... Approved Open
9 Jun 2026 Appointment of Chair and Vice-ChairRESOLVED that: 1. Councillor Tom Reeve be appointed Chair of the Committee for the Municipal Year 2026/27 until the f... Decided Open
9 Jun 2026 Double Yellow Lines on Villiers Avenue - Objections to Traffic Management OrderRESOLVED that: 1. the comments and objections received on the Traffic Management Order (TMO) on conversion of Single ... Noted Open
9 Jun 2026 Planning ApplicationsRESOLVED to PERMIT subject to the conditions set out in the report including such amendments, additions and/or deleti... Decided Open
9 Jun 2026 Councillor Ward Funding Arrangements 2026/27RESOLVED that the Committee’s current working arrangements for the allocation of Councillor Ward Funding, as set out ... Decided Open