RESOLVED that: 1) The proposed procurement strategy as set out in paragraphs 8-13 of this report be noted and that, subject to the successful outcome of the procurement of the main contractor for the Kingston Riverside refurbishment works, a further report will be brought back to Committee in due course to award the contract. 2) The combined external public grant allocation of £2.2M be approved, to be added to the Council’s Capital Programme 2022-24 under the project. 3) Approval be given to enter into Head Leases with John Lewis Partnership across the three areas; the workspace use (in two parts) and the creative performance space ( Undercroft ) under the terms set out in paragraph 7 of the report. 4) Approval be given to permit the grant of a sub-lease of the Workspace areas based on criteria set out in paragraph 8 of the report and to delegate authority to the Assistant Director for Property, Development and Investment to negotiate and conclude the detailed terms of the Lease. 5) Approval be given to permit the grant of a sub-lease of the Undercroft area to Creative Youth on terms set out in paragraph 9 of the report and to delegate authority to the Assistant Director for Property, Development and Investment to negotiate and conclude the detailed terms of the Lease.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
The Council has successfully obtained £2.2m of public grant funding from the Government to support the delivery of Kingston Town Centre recovery programme. The majority of this is to support the Kingston riverside regeneration and enterprise projects which will see the refurbishment and new occupation of 3 vacant units at the John Lewis Partnership (JLP) building in Kingston Town Centre to provide affordable workspace on the ground floor units (former restaurant and nightclub) and a community/ arts/ performance space in the basement (Undercroft) area for Creative Youth charity, together with improvements to the public space along the adjacent section of the Thames riverside.
This external grant funding is time limited, with all related services and works to be completed by 31st March 2022. The purpose of this report is to minimise the financial risk to the Council by setting out the commissioning intentions for the main construction works and seek approval for the project grant allocation to be added to the Council’s Capital Programme 2022-24. The report seeks approval for the council to enter into a 10 year (with landlord breaks on or after 3 years) lease agreement with JLP to enable the occupation of affordable workspace enterprise at ground floor level and the provision of creative and cultural performance arts activity in the basement undercroft spaces. The report also seeks approval to the grant of subleases to the Council's preferred workspace operator and to Creative Youth for the Undercroft project.
Recommendation(s)
The Committee is asked to RESOLVE that:
1. The proposed procurement strategy as set out in paragraphs 8-13 of this report be noted and that, subject to the successful outcome of the procurement of the main contractor for the Kingston Riverside refurbishment works, a further report will be brought back to Committee in due course to award the contract.
2. The combined external public grant allocation of £2.2M be approved, to be added to the Council’s Capital Programme 2022-24 under the Kingston Riverside Workspace project.
3. Approval be given to enter into Head Leases with John Lewis Partnership across the three areas; the workspace use (in two parts) and the creative performance space (Undercroft) under the terms set out in paragraph 7 of the report. 4. Approval be given to permit the grant of a sub-lease of the Workspace areas based on criteria set out in paragraph 8 of the report and to delegate authority to the Assistant Director for Property, Development and Investment to negotiate and conclude the detailed terms of the Lease.
5. Approval be given to permit the grant of a sub-lease of the Undercroft area to Creative Youth on terms set out in paragraph 9 of the report and to delegate authority to the Assistant Director for Property, Development and Investment to negotiate and conclude the detailed terms of the Lease.
Benefits to the Community:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Council Plan End of Year Report 2025/26RESOLVED that: 1) The End of Year Report for 2025/26, at Annex 1 to the report, be noted. 2) The newly published Loca...
Leader of the Opposition OptionsRESOLVED that: Having considered the options outlined in the report, Option 1 (the status quo) be adopted as the pref...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.