AI summaryKingston's Corporate and Resources Committee has noted the 2025/26 Council Plan end of year report, which records 15 actions completed, 35 ongoing and 10 with new timelines, and has also noted the new Local Outcomes Framework.
Written from the decision and the officer reportPDF Pro
OutcomeNoted15 actions completed, 35 ongoing, 10 with new timelines
MoneyNot stated
What happens nextSeptember Corporate and Resources Committeeperformance update against the Local Outcomes Framework
Who it affectsKingston residents and communitiestransparency on council priorities and progress
What was decided
The Committee noted the End of Year Report for 2025/26, set out in Annex 1 to the report. Report P6
The Committee noted the newly published Local Outcomes Framework and asked for a performance update against its measures to come to the September Corporate and Resources Committee. Report P7
Why
The Council Plan 2023 to 2027 and annual Delivery Plans are the council's main tool for managing business and resources, so an annual progress report lets residents hold the council to account. Report P9, P11, P12
The Government published the Local Outcomes Framework in February 2026 to give central and local government a shared set of 16 outcomes and 147 metrics, and it will be used to assess Kingston's Best Value Duty compliance. Report P14, P15, P55, P56, P72
What happens next
A detailed report on the council's performance against the Local Outcomes Framework, benchmarked against other London boroughs, will be presented to the Corporate and Resources Committee in September 2026. Report P7, P73
The End of Year Report will be published on the council website by the end of July 2026, and work is underway to develop a new Council Plan after 2027. Report P28, P77
A public facing digital tool showing the 16 outcomes and 147 metrics will go live on GOV.UK in summer 2026. Report P15, P71
The money
estimated average saving of £711 on energy bills per home, per year from the completed 66-home retrofit pilot Report P38
65 tonnes of carbon saved across the 66 retrofit pilot properties Report P38
Options considered
Chosen: Note the End of Year Report 2025/26 and the Local Outcomes Framework, with a September performance update. The papers present this as the single recommendation; no alternatives are discussed. Report P4, P5, P6, P7
Implications
Financial: No direct resource implications; Delivery Plan progress in 2025/26 was delivered within the council's approved financial framework and existing resources. Report P79
Legal: No legal implications. The Council Plan and Delivery Plans are not a legal requirement but set the council's strategic framework. Poor Local Outcomes Framework results could trigger government involvement under the Best Value Duty. Report P72, P80
Equalities: An Equalities Relevance Test was carried out and showed no impact, so no Equalities Impact Assessment was undertaken. Report P83
Risk: No significant risks are anticipated; the report is seen as a transparency tool for residents. Report P82
Climate: None anticipated from the report itself, though 2025/26 work included 65 tonnes of carbon saved via retrofit and six schools supported with heat decarbonisation plans. Report P38, P43, P86, P87
Older people and people with learning disabilities, through 45 plus 13 new independent living homes under construction on Acre Road Report P37
Children in care, through a new Children's Home being built in Chamberlain Way, Surbiton Report P39
Council housing tenants and people on the housing waiting list, with 101 new Council homes completed in Phase 1 of the small sites programme Report P33
Voluntary and community sector partners, under the Empowering People, Supporting Communities strategy Report P47
Local businesses and jobseekers, with 673 people supported towards or into employment through the Economic Development Strategy Report P48
Timeline
2023: Council Plan 2023 to 2027 approved in March 2023. Report P11
March 2025: Council Delivery Plan 2025/26 approved by the Corporate and Resources Committee. Report P18
1 April 2025: New waste contract with Veolia went live. Report P41
June 2025: Construction of the new Kingston Leisure Centre commenced, targeting completion by Spring 2027. Report P34
August 2025: New council website went live. Report P51
September 2025: Construction began on the new independent living development on Acre Road (45 homes for older people, 13 for people with learning disabilities) and on the new Children's Home in Chamberlain Way, Surbiton. Report P37, P39
October 2025: New leisure management contract mobilised, supporting the Active Kingston Framework. Report P32
November 2025: Inclusive Kingston 2025 to 2029 Equality, Diversity and Inclusion strategy approved and launched; Economic Development Strategy completed its first year of delivery. Report P31, P48
February 2026: Government published the Local Outcomes Framework; Council approved a balanced budget for 2026/27. Report P14, P50, P55
19 March 2026: Council Delivery Plan 2026/27 approved by the Corporate and Resources Committee. Report P27
25 June 2026: Corporate and Resources Committee noted the End of Year Report 2025/26 and the Local Outcomes Framework. Report P6, P7
End of July 2026: End of Year Report to be published on the council website. Report P77
Summer 2026: Public facing digital tool on GOV.UK for the Local Outcomes Framework expected to go live. Report P15, P71
September 2026: Performance update against the Local Outcomes Framework to be presented to the Corporate and Resources Committee. Report P7, P73
Spring 2027: Target completion of the new Kingston Leisure Centre. Report P34
Plain English for the jargon
Council Plan 2023 to 2027: The council's medium term plan setting out its vision, outcomes, priorities and key performance indicators, delivered through annual Council Delivery Plans.
Council Delivery Plan: An annual plan listing the actions, measures of success and delivery dates used to deliver the Council Plan priorities.
Local Outcomes Framework (LOF): A government framework published in February 2026 with 16 outcomes and 147 metrics, used by central and local government to measure progress and to assess councils' Best Value Duty compliance.
Best Value Duty: The council's duty to deliver economic, efficient and effective services; the Government will use LOF outcomes to assess compliance.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
RESOLVED that: 1) The End of Year Report for 2025/26, at Annex 1 to the report, be noted. 2) The newly published Local Outcomes Framework be noted, with an update on Council performance against these measures to be brought to the September Corporate and Resources Committee.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
To summarise progress in relation to delivering the council’s priorities as set out in the Council Plan 2023 - 2027. This includes:
● The end-of-year position in relation to actions set out in the Council Delivery Plan 2025/26;
● The position in relation to performance indicators as set out in the Council Plan.
Recommendation(s)
The Committee is asked to RESOLVE that:
1. The End of Year Report for 2025/26, at Annex 1 to this report, be noted.
2. The newly published Local Outcomes Framework be noted, with an update on Council performance against these measures to be brought to the September Corporate and Resources Committee.
Benefits to the Community:
The Council Plan and annual Council Delivery Plans are fundamental in ensuring that the council manages its business and resources effectively, with activities aligned to achieving the council’s ambitions for our residents and communities. The End of Year Report summarises progress in relation to the Council Plan priorities and Council Delivery Plan actions. This provides a transparent approach and enables residents to hold the council to account.
Key Points
A. The Council Plan 2023 - 2027, approved in March 2023, sets out the Council’s medium-term vision, outcomes, priorities and key performance indicators1. It is delivered via an annual Council Delivery Plan, which sets out
1 https://www.kingston.gov.uk/policies-statements/council-plan the actions that the council will take to achieve the Council Plan priorities, and the associated measures of success and delivery dates.
B. The End of Year Report 2025/26 shows progress against the outcomes in the Council Plan and the actions in the 2025/26 Council Delivery Plan. This is presented in Annex 1.
C. The Local Outcomes Framework (LOF) was published by the Government in February 2026. It is designed to help both central and local government understand and measure progress across key local outcomes using a shared set of standards.
D. A digital, public-facing tool will be available on GOV.UK in mid-to-late 2026, enabling residents and stakeholders to review the borough’s performance against the 16 outcomes, and the 147 specific metrics within the Local Outcomes Framework.
Context / Programme and Project Progress
1. The Council Plan 2023 - 2027 is organised under the themes of Fairer, Safer, Greener, Together. It also sets out how the council will continue to transform, under the theme of Future Council, building on work to become more efficient and deliver more effectively and in a smarter way, working together with partners. It includes performance indicators for measuring progress in relation to the priorities set out within the plan.
2. The Council Delivery Plan for 2025/26 was approved by the Corporate and Resources Committee in March 20252.
3. The End of Year Report in Annex 1 sets out progress against the Council Delivery Plan actions for 2025/26. An overview of this progress is as follows:
i. 15 actions are marked as delivery completed
ii. 35 actions are updates on an ongoing programme of work
iii. 10 actions will be completed with new timelines
iv. 0 actions will no longer be completed.
4. Details regarding individual actions are included within the report.
5. The End of Year Report in Annex 1 also includes progress against the performance indicators for each of the outcomes in the Council Plan, with notes.
6. An online dashboard of the Council Plan key performance indicators was introduced in summer 2025 and has improved transparency of quarterly performance reporting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Leader of the Opposition OptionsRESOLVED that: Having considered the options outlined in the report, Option 1 (the status quo) be adopted as the pref...
Postal Services and Solutions ContractRESOLVED that 1) a new Postal Services and Solutions contract be procured through participation in the Pan-London Pos...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.