RESOLVED that: 1) the contract for the provision of Main Construction Works be awarded to Morgan Sindall for a contract term up to 22 months from 24 July 2023 to 31 May 2025, plus 12 months latent defect period at a total anticipated contract value of £23,543,173.00; 2) the Executive Director of Place, in consultation with the Portfolio Holders for Assets, Commissioning and Waste and Children’s Services including Education be authorised to agree final terms on price and contract terms and be satisfied that there are no material changes to the proposed solution or commercial terms set out in this report; and 3) the variation of the total value of the programme costs, including the provision of an additional capital budget allocation of £13.5m, funded by DFE Basic Need Grant, be approved.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Purpose of Report To approve the award of the main construction contract for the rebuilding/expansion of Burlington Junior School and the remedial works required at Burlington Infant School
The Committee is asked to RESOLVE that: 1. the contract for the provision of Main Construction Works be awarded to Morgan Sindall for a contract term up to 22 months from 24 July 2023 to 31 May 2025, plus 12 months latent defect period at a total anticipated contract value of £23,543,173.00; 2. the Executive Director of Place, in consultation with the Portfolio Holders for Assets, Commissioning and Waste and Children’s Services including Education be authorised to agree final terms on price and contract terms and be satisfied that there are no material changes to the proposed solution or commercial terms set out in this report; and 3. the variation of the total value of the programme costs, including the provision of an additional capital budget allocation of £13.5m, funded by DFE Basic Need Grant, be approved.
Benefits to the Community: The Council has a statutory responsibility to provide school places where they are needed, and in doing so to provide educational environments that meet health and safety, environmental and building standards. This development will replace a defective building with a safe and more energy-efficient building. The project includes the construction of a new Sports Hall for the school. The Sports Hall will be subject to a Community Use Agreement which will allow the local community use of the Sports Hall outside of school hours.
The realisation of social value benefits to be derived from this contract have been a key part of the commissioning process and benefits include apprenticeships for local people, support for volunteering, the encouragement and involvement of community groups in improving the local environment.
Key Points
A. Rated as ‘Good’ by Ofsted, Burlington Junior School is located in New Malden. The school currently extends to four forms of entry, accommodating approximately 480 pupils covering year 3 pupils aged 7-8 to year 6 pupils aged 10-11. The same site also contains Burlington Infant School and a Nursery. The schools are segregated but share lunchtime dining facilities and staff parking.
B. Population growth in the local area has generated a need for 120 new school places. In November 2019, the former Children, Adults and Education Committee approved the expansion of Burlington Junior School from four to five forms of entry to take account of this planned/anticipated population growth. Accordingly, in July 2021 the Corporate & Resources Committee approved the adoption of a two stage design and build delivery model procured through the Southern Construction Framework to support this requirement.
C. The current main building at the Junior School is known as the CLASP building. CLASP (Consortium of Local Authorities Special Programme) buildings are constructed through a modular system with steel frames and typically clad with concrete panels. These buildings mainly date from the 1960’s and 1970’s and are now life-expired. Early in the programme light movement was detected within the CLASP building which upon investigation was identified as being as a result of corrosion of the structure. The decision was therefore taken to seek to replace the CLASP building with a new school building, expanding provision at the same time.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Council Plan End of Year Report 2025/26RESOLVED that: 1) The End of Year Report for 2025/26, at Annex 1 to the report, be noted. 2) The newly published Loca...
Leader of the Opposition OptionsRESOLVED that: Having considered the options outlined in the report, Option 1 (the status quo) be adopted as the pref...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.