RESOLVED that – 1. The updated Phase 1 Business Plan is noted; 2. Authority be delegated to the Executive Director of Place to finalise and sign a Supplemental Agreement to record the terms agreed by the Council and the Limited Liability Partnership (LLP) that reflect the change of tenure of 104 homes in phase 1 from private sale to social rent. Voting: Unanimous
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
The governance for the CRE regeneration project requires that major changes to the Business Plan are reported to the relevant Committee. The Council’s decision in December 2023 to change 104 private sale homes to Council social rent is a major change and the updated Business Plan is therefore being reported to the Committee to reflect this change.
Recommendation(s)
The Committee is asked to RESOLVE that:
1. The updated Phase 1 Business Plan is noted;
2. Authority be delegated to the Executive Director of Place to finalise and sign a Supplemental Agreement to record the terms agreed by the Council and the Limited Liability Partnership (LLP) that reflect the change of tenure of 104 homes in phase 1 from private sale to social rent.
Benefits to the Community:
The swap of 104 homes that were originally identified for private sale to social rent will help relieve some of the acute housing pressures that are being experienced by residents in the Borough. These homes will be allocated to households who are not currently residents of CRE. The tenure swap also reduces the LLP’s sales exposure to a weakened private sales market. This means that the programme for the delivery of new homes, including affordable homes for social rent and sub-market sale, can be maintained. Key Points
A. The regeneration of Cambridge Road Estate (CRE) is a key Council priority. It will transform Kingston’s largest estate and, when completed, will provide 2,170 new homes. Of these, 767 homes are planned to be for social rent, 174 will be for rent/sale at below market prices and 1,229 are planned for private sale. The regeneration will provide modern, energy efficient homes that are safe, secure and accessible across all tenures.
B. The LLP has made significant progress - phases 1a and 1b are on site and progressing well. The first homes are expected to be completed towards the end of 2024.
C. The Business Plan is updated on an annual basis and the last Business Plan was agreed at the Corporate & Resources Committee in September 2023. This Committee granted delegated authority to the Executive Director for Place (in consultation with the Chief Executive, S151 officer and the Portfolio Holders for Finance and Housing) to agree additional mitigation measures for Phase 1.
D. Facing a challenging economic climate, in particular, a slowing down in private sales activity, the LLP was considering options for phase 1c. Options were to delay the commencement of phase 1c or consider swapping private sale homes to another tenure to reduce the sales exposure.
E. As a result of this opportunity in December 2023, the Council used its delegated authority and agreed mitigation measures whereby the Council will acquire 104 additional properties for social rent from the Cambridge Road (RBK) LLP ( the LLP). These homes were originally planned for private sale. This means that the total number of homes for social rent increases to 871 and the number of homes for private sale reduces to 2,066.
F. The governance arrangements for the project require that variations to the Business Plan are approved by the respective members of the LLP. This paper notes the change to the tenure split as described in paragraph B and updates the Phase 1 Business Plan. As the decision to acquire the homes has already been taken by the Council and the business plan has simply been updated to reflect this decision, the Committee is asked to note the updated business plan.
G. The Council and the LLP will enter into a Supplemental Agreement to record this variation. Context/ Programme and Project Progress
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Council Plan End of Year Report 2025/26RESOLVED that: 1) The End of Year Report for 2025/26, at Annex 1 to the report, be noted. 2) The newly published Loca...
Leader of the Opposition OptionsRESOLVED that: Having considered the options outlined in the report, Option 1 (the status quo) be adopted as the pref...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.