RESOLVED that: 1. the current status of schemes from the 2021/22 planned highway works as detailed in Annex 1 of the report , be noted; 2. subject to any comments from the Neighbourhood Committees, the prioritised planned highway and street lighting capital maintenance programme for 2022/23, as detailed in Annexes 2 and 3 of the report , be approved; 3. authority be delegated to the Assistant Director Highways, Transport, and Regulatory Services to deal with any in-year changes that may prove necessary in consultation with the Portfolio Holder and affected ward members; and 4. Authority be delegated to the Assistant Director, Highways, in consultation with the Portfolio Holder for Environment & Sustainable Transport, to action as considered appropriate any comments arising from the Maldens and Coombe Neighbourhood Committee meeting on 17 March 2022. Voting: For – Councillors Davey, Archer, Cunningham, Davis, Gander, Heap, Hughes, Thayalan , Wehring , Yoganathan (10) Against – Nil (0) Abstain – Councillor George (1)
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
To detail highway (carriageway, footway and street lighting) planned maintenance works carried out during 2021/22 and present a proposed planned highway and street lighting maintenance programme for 2022/23.
Recommendation(s)
The Committee is asked to RESOLVE that:
1. the current status of schemes from the 2021/22 planned highway works as detailed in Annex 1, be noted;
2. subject to any comments from the Neighbourhood Committees, the prioritised planned highway and street lighting capital maintenance programme for 2022/23, as detailed in Annexes 2 and 3, be approved;
3. authority be delegated to the Assistant Director Highways, Transport, and Regulatory Services to deal with any in-year changes that may prove necessary in consultation with the Portfolio Holder and affected ward members; and
4. Authority be delegated to the Assistant Director, Highways, in consultation with the Portfolio Holder for Environment & Sustainable Transport, to action as considered appropriate any comments arising from the Maldens and Coombe Neighbourhood Committee meeting on 17 March 2022.
Benefits to the Community:
Planned highway and street lighting maintenance programmes are developed to ensure that the highway network is safe and keeps people and goods moving.
Key Points
A. An update on the progress of 2020/21 carriageway and footway schemes is provided in Annex 1. The street lighting column replacement programme has been delayed, as explained in paragraph 7 below, but arrangements are in place for funding to be carried forward.
B. The Annual Highway Investment Programme has traditionally been made up of the Council’s capital funding to deliver the planned maintenance programme for non-principal roads, and funding from Transport for London (TfL) for maintenance of principal roads, the TfL allocation for 2022/23 at this time is nil although there may be an opportunity later in the year to bid for funds. During 2021/22 there was a TfL allocation of £200,000 for Ewell Road from Hollyfield Road to the hospital entrance (past Oak Hill Crescent) and the scheme is planned to be implemented in March 2022.
C. Kingston Council’s highway network comprising carriageways, footways and street lighting is the most visible, well used and valuable physical asset which the Council is responsible for. Achieving the Council’s strategic outcome of “a sustainable approach to new homes, development and infrastructure which benefits our communities, in a well maintained borough”, requires continuous investment in the heavily used highway assets to maintain them in a serviceable condition. The highway maintenance needs are being reviewed continuously and prioritised on a Borough-wide basis.
D. The Committee is asked to approve the following programmes for 2022/23, as set out in Annexes 2 and 3:
- planned footway and carriageway maintenance to the value of £1.75m; (indicative value of footways £750,000 and carriageways £1,000,000)
- street lighting column replacement to the value of £440,000.
Context
1. The funding for the management of highway assets is under continuous scrutiny, with increasing pressure from government and the public for transparency, accountability and more efficient use of the limited resources available.
2. It is important to ensure borough roads and street lighting assets remain in a good condition to ensure their longevity. Highway maintenance work is also necessary to reduce the Council`s exposure, as Highway Authority, of the risk of claims for personal injury and damage. The need for footway and carriageway maintenance is identified through a combination of structural assessments, visual inspections and reporting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.