PlayZones Project - Contract Award

Decided Committee 1 paper

AI summaryKingston's Place Committee awarded a £1,293,070.57 contract to McArdle Sport Tec Limited for four PlayZone multi-sport facilities in borough greenspaces, as a direct award under the Football Foundation framework.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedDirect award call-off under Football Foundation PlayZones Framework
Money£1,293,070.57 (excluding VAT)Council contributes 25%, Football Foundation 75%
What happens nextPlanning determination then constructionAll four sites expected to be completed during 2027
Who it affectsResidents across the BoroughFour sites in public parks and greenspaces

What was decided

The Committee resolved to award the supply and installation contract for PlayZone facilities to McArdle Sport Tec Limited for £1,293,070.57 excluding VAT, as a direct award call-off under the Football Foundation's PlayZones Framework. Report P3

Why

The Football Foundation's framework appoints a single supplier, so a direct award is required to access the 75% grant funding of £975,000 awarded to the Council. Report P8, P9, P11, P24

Officers state the framework is compliant with the Public Contract Regulations 2015 and that legal review found no risk to the Council. Report P12, P32, P57, P58

The programme targets inequalities in physical activity, with the four sites selected to address gaps identified in the Active Kingston Framework 2023, including a MUGA shortfall in the New and Old Malden area. Report P6, P15, P16, P19

What happens next

Planning applications for all four sites were submitted on 11th May 2026; construction is anticipated during 2026/27 once determinations and any conditions are resolved. Report P22, P50, P51, P52

A Preliminary Ecological Appraisal has been completed and each site is expected to deliver 10% biodiversity net gain through 1,100m² of neutral grassland planting. Report P66

The Council's Contract Register should be updated once a written call-off contract is entered into. Report P59

The money

  • £1,293,070.57 Total contract value excluding VAT for supply and installation of PlayZone facilities Report P3
  • £975,000 Football Foundation grant funding covering 75% of total project cost Report P9
  • £325,000 Required Council contribution of 25% of total project cost Report P9
  • £323,268 Council contribution described as 25% of total expenditure Report P54
  • £969,802 Football Foundation contribution described as 75% of total expenditure Report P54

Options considered

  • Rejected: Do nothing (reject grant funding). Would result in loss of £975,000 grant funding for the four sites Report P27
  • Rejected: Run a competitive tender. Grant conditions require delivery through the Football Foundation's Framework Alliance Contract Report P28
  • Chosen: Direct award call-off under the Football Foundation PlayZones Framework. Framework has a single appointed supplier (McArdle Sport Tec Limited) and is the required route to access grant funding; value for money is demonstrated through original tendered rates and supply chain tendering Report P29, P30, P31, P33, P34

Implications

  • Financial: Funding is available within the capital programme; 75% of cost is met by the Football Foundation, with 25% from the Council as agreed at Budget Council 2026. Report P10, P54
  • Legal: Award is made under the Football Foundation's Framework Alliance Contract, governed by the Public Contract Regulations 2015; framework documentation has been reviewed by Legal Services with no risk identified. Report P32, P55, P56, P57, P58
  • Equalities: An Equalities Relevance Test was undertaken and indicated no negative impact, so no Equalities Impact Assessment was completed; the programme targets lower socio-economic groups, women and girls, disabled people and people with long-term health conditions, and ethnically diverse communities. Report P15, P16, P62
  • Climate: Each site is expected to achieve 10% biodiversity net gain via 1,100m² of neutral grassland planting (4,400m² total); a Preliminary Ecological Appraisal has been completed under CIEEM (2018 V1.2 Updated 2022). Report P66
  • Risk: The main risk is the delivery programme: until planning permission is granted and any conditions discharged for each site, the construction programme cannot be finalised. Report P60, P61
  • Other: Engagement in 2024 received approximately 461 responses (304 formal and 157 in-person), showing boroughwide support and demand for multi-sport, youth-focused and inclusive provision. Report P44, P46, P48

Who and where

  • Residents of Beverley Park area (addressing a MUGA shortfall in the New and Old Malden Analysis Area) Report P18, P19
  • Users of Churchfields Recreation Ground, Kingston Road Recreation Ground and Manor Park Report P18
  • Underrepresented groups in physical activity: lower socio-economic groups, women and girls, disabled people and people with long-term health conditions, and ethnically diverse communities Report P15, P16

Timeline

  • 2024: Community engagement on the PlayZones concept carried out by the Fulham Football Foundation Report P44
  • 11th May 2026: Planning applications for all four sites submitted Report P51
  • 2026/27: Construction currently anticipated, subject to planning determinations Report P22, P52
  • During 2027: All four PlayZones anticipated to be completed (subject to planning approval and programme sequencing) Report P52

Plain English for the jargon

  • PlayZone: A floodlit, multi-use games area (MUGA) roughly the size of one or two tennis courts, designed for football and other sports such as basketball and netball
  • MUGA: Multi-Use Games Area
  • Direct award call-off: Procurement route where a single supplier is appointed under an existing framework, without running a further competition
  • PZP: Playzone Provider, the appointed supplier under the Football Foundation framework
  • PCR2015: Public Contract Regulations 2015, under which the framework is governed
  • PEA: Preliminary Ecological Appraisal, completed under CIEEM (2018 V1.2 Updated 2022)
  • EcIA: Ecological Impact Assessment, the final assessment supporting a planning application
  • CIEEM: Chartered Institute of Ecology and Environmental Management, referenced for the PEA standard
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16

Resolved

RESOLVED that the contract for the supply and installation of the PlayZone facilities be awarded to McArdle Sport Tec Limited for the sum of £1,293,070.57 (excluding VAT), as a direct award call-off under the Football Foundation’s PlayZones Framework.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Place Committee

Purpose of report

To seek approval to award a contract to McArdle Sport Tec Limited for the provision and installation of PlayZone facilities at four greenspace locations within the Borough.

Recommendation(s)

The Committee is asked to RESOLVE that the contract for the supply and installation of the PlayZone facilities be awarded to McArdle Sport Tec Limited for the sum of £1,293,070.57 (excluding VAT), as a direct award call-off under the Football Foundation’s PlayZones Framework.

Benefits to the Community:

PlayZones are safe, inclusive and accessible outdoor facilities that bring communities together through recreational football and a range of other sports, delivered through multi use game areas. The four PlayZones will be located within public parks and greenspaces to maximise access for residents across the Borough.

The programme is aimed at tackling inequalities in physical activity and access to quality recreational facilities by investing in community-led spaces that respond to local needs. By creating welcoming and accessible places to be active, the PlayZones will support residents’ long-term health, wellbeing and encourage positive social interaction.

Key Points

A.​ PlayZones is a Football Foundation capital grant funding operating across England. It provides up to 75% grant funding to local authorities for the installation of PlayZones, multi-use games areas designed to support a range of sports and recreational activities.

B.​ The Council was awarded grant funding covering 75% of the total project cost to deliver four PlayZone sites. This equates to £975,000 in grant funding, with a required Council contribution of £325,000.

C.​ The Council’s financial contribution, and approval to allocate this funding, was agreed at Budget Council 2026. D.​ As a condition of the grant, the Council is required to access delivery through the Football Foundation’s Framework Alliance Contract. The Council will join this existing framework as an Additional Client.

E.​ The Football Foundation’s procurement process has appointed a single Supplier to the Framework Alliance Contract. Accordingly, the Council is required to make a direct award to deliver the projects. The appointed supplier is McArdle Sport Tec Limited.

F.​ A framework compliance checklist has been completed. Legal advice confirms that the Council can access the framework with no identified risk.

Context / Programme and Project Progress

1.​ The Football Foundation’s national PlayZones programme aims to deliver 240 PlayZones through an investment of £92 million, funded by the Premier League, The FA and the Government via Sport England.

2.​ The programme prioritises Target Groups: The initiative is designed to focus investment in communities with the greatest need, focusing on specifically targeting four key groups experiencing inequalities in physical activity levels, including:

●​ Lower socio-economic groups ●​ Women and girls ●​ Disabled people and people with long-term health conditions ●​ Ethnically diverse communities

3.​ The Football Foundation typically provides 65-70% of project costs through grant funding, with the remaining contribution met locally. The Council secured funding at the higher level of 75%.

4.​ The Council was awarded funding for four PlayZone sites: Beverley Park, Churchfields Recreation Ground, Kingston Road Recreation Ground and Manor Park.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PlayZones Project: Contract AwardReport 148 KB DownloadRead as text

At this meeting

Whole meeting

More from Kingston upon Thames Place Committee

All decisions
MeetingDecisionOutcome
23 Sep 2026 Coombe Lane West Proposed Zebra Crossing - Objections to Traffic Management OrderRESOLVED that: ( i ) the objections received in response to the published Traffic Management Order (TMO) for replacin... Decided Open
23 Sep 2026 Highway Infrastructure Asset Management PlanRESOLVED that the Highway Infrastructure Asset Management Plan and associated appendices, as set out in Annex 1 of th... Approved Open
23 Sep 2026 Seething Wells - Annual UpdateThe recommendations on page D1 of the agenda pack were not approved. The reporting requirements agreed under resoluti... Approved Open
23 Sep 2026 Motion referred by Council - “Every Councillor for Every Kind”After debate and amendments, the following motion was put to the vote and CARRIED . “ Council notes the “Every Counci... Decided Open
16 Jun 2026 Local Plan - Final Draft of the Local Plan (Regulation 19)RECOMMENDED TO COUNCIL that: 1. the ‘publication document’ for Regulation 19 statutory public consultation be approve... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies