AI summaryKingston Place Committee approves use of existing capital budget for cost increases on three council building decarbonisation projects, and delegates contract award authority to officers to meet March 2027 funding deadline.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFunding and delegated authority for contract award
Money£9.71m approved decarbonisation budget, £8.78m remainingWhole programme 2024/25 to 2028/29
What happens nextTendering from July/August 2026Start on site by November 2026
Who it affectsNot stated
What was decided
Increased costs for the Dukes Centre, Surbiton Library and Tolworth Recreation Centre decarbonisation projects will be funded from the existing capital budget allocated to decarbonisation of the council's assets. Report P4
Authority to award contracts for the planned projects, where tender returns are within existing approved budgets, is delegated to the Executive Director Place, in consultation with the relevant Portfolio Holder for Climate and the relevant Portfolio Holder for Assets, and with recommendation by the Commissioning Governance Board. Report P5
Why
The council has a target of reaching Net Zero carbon emissions from its own operations by 2030, and the largest contributor is gas use in council buildings. Report P9
The three buildings are priorities because they make a significant contribution to the council's carbon footprint, are certain to be retained in the longer term, and have end of life gas boilers that would otherwise require replacement. Report P12
Funding must be spent by the March 2027 external funding deadline, and delegated authority would shorten the procurement period and allow a longer construction and installation window. Report P25
What happens next
Finalise costed RIBA Stage 3 to 4 designs, produce the tender pack, and obtain any necessary governance approvals for contractor appointment, with mobilisation to site by November 2026. Report P22, P33
For the four solar PV sites, tender in June to July 2026, appoint a contractor in August 2026 and reach practical completion in September 2026. Report P35
A milestone decision report will be brought back on Tolworth Recreation Centre before progressing to tender, to inform scope, cost viability and direction. Report P24
The money
£9.71m Approved decarbonisation budget for the entire programme from 2024/25 to 2028/29 Report P19, P37
£8.78m Remaining budget from the approved £9.71m Report P37
£1.06m Confirmed Salix funding towards PSDS 4 Report P37
£0.60m-£0.80m Expected contribution from the Carbon Offset Fund Report P37
Options considered
Chosen: Proceed with delivery based upon updated decarbonisation programme. Projects deliver significant carbon reductions towards the Net Zero 2030 target, benefit key community buildings, and continuing now avoids inflation and ongoing repair or replacement of ageing gas boilers. Report P27
Rejected: Proceed with delivery based upon original decarbonisation programme. Lack of funding available to develop the full number of pilot assets originally reviewed. Report P27
Rejected: Reduce scope of decarbonisation programme. Would lead to loss of external funding secured, create abortive work and costs of completed detailed design, and reduce decarbonisation of corporate assets. Report P27
Rejected: Halt decarbonisation programme. Would not fulfil council objectives and climate targets, would not deal with end of life asset infrastructure, would maximise loss of external funding, and would require alternate gas boiler replacement projects. Report P27
Implications
Financial: Estimated project costs have risen significantly due to additional works identified through detailed investigations, age and condition of assets, inflationary and market pressures, contingencies and assumed product and logistics costs. Completion of the three larger projects will require the remainder of the council's capital budget allocated to decarbonisation of its buildings. Report P14, P15
Climate: The programme is expected to deliver estimated annual carbon savings of 73,315 kg at Tolworth Recreation Centre, 73,315 kg across Surbiton Library and the Dukes Centre, and 8,465 kg for the four solar PV sites. Report P52
Risk: Key project risks include further cost increases through design and construction, lack of compliant tender returns, reputational risk of poor retrofit, benefits not fully materialising, unforeseen construction or structural issues, and withdrawal of funding. Report P43, P44
Legal: The report states there are no legal implications. Report P40
Equalities: An Equalities Relevance Test was undertaken and indicated no impact, so no Equalities Impact Assessment was carried out. Report P45
Other: Removing fossil fuel systems and promoting on-site clean energy generation is expected to improve local air quality and reduce the risk of respiratory conditions, and improved insulation and lighting should enhance Indoor Environmental Quality. Report P48, P49
Who and where
Users of the Dukes Centre, Surbiton Library and Tolworth Recreation Centre Report P12, P21
Users of Kingsnympton Youth and Community Centre, Kingston Town Children's Centre, Rose Car Park, and School Lane Youth and Community Centre (four PV sites) Report P25
Places Leisure, the leisure centre operator, in respect of Tolworth Recreation Centre Report P24, P30
Local construction supply chain, with potential demand for solar panel installation, LED lighting and energy efficiency skills Report P54
Timeline
June 2026: Budget allocation noted and delegated authority approved at Place Committee Report P33
July 2026: Procurement strategy preparation for PSDS 3c projects Report P33
June - July 2026: Tendering for the four multi-site PV installations Report P35
July / August 2026: Tendering for PSDS 3c projects (Surbiton Library and Dukes Centre) Report P33
August 2026: Contract award preparation, contractor appointment and start on site for the four PV sites Report P35
September 2026: Contract award preparation for PSDS 3c Report P33
September 2026: Practical completion of the four PV sites Report P35
October 2026: Contract award decision delegated to officers, with contractor appointment Report P33
November 2026: Start on site for PSDS 3c projects Report P33
March 2027: Practical completion of PSDS 3c and PSDS 4 (Tolworth Recreation Centre) and PSDS 4 Salix funding expended Report P33
Plain English for the jargon
PSDS: Public Sector Decarbonisation Scheme, a government grant programme administered by Salix to fund heat decarbonisation in public sector buildings.
PSDS 3c and PSDS 4: Rounds 3c and 4 of the Public Sector Decarbonisation Scheme funding.
Salix: Government-backed body that provides funding to public sector organisations for energy efficiency and low carbon heat projects.
RIBA Stage 2, 3 and 4: Design stages set by the Royal Institute of British Architects, covering concept design, spatial coordination and technical design.
PV: Photovoltaic, referring to roof-mounted solar panels that generate electricity from sunlight.
Carbon Offset Fund: Council fund financed through developer contributions, used to pay for carbon reduction measures.
Cenergist: Contractor previously appointed to develop the programme, which was placed under administration, ending that appointment.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19
Resolved
RESOLVED that: 1. increased costs from the planned projects at the Dukes Centre, Surbiton Library and Tolworth Recreation Centre be funded from the existing capital budget allocated towards the decarbonisation of the Council’s assets; and 2. authority be delegated to the Executive Director Place, in consultation with the relevant Portfolio Holder for Climate and the relevant Portfolio Holder for Assets, and with recommendation by the Commissioning Governance Board, to proceed with contract award of the planned projects, where tender returns are within existing approved budgets, in order to deliver projects in line with external funding requirements.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
To report on progress of, and changes to, the previously approved ‘Retrofit Accelerator - Workplaces’ programme - a decarbonisation programme relating to the council’s operational assets.
Recommendation(s)
The Committee is asked to RESOLVE that:
1. increased costs from the planned projects at the Dukes Centre, Surbiton Library and Tolworth Recreation Centre be funded from the existing capital budget allocated towards the decarbonisation of the Council’s assets; and
2. authority be delegated to the Executive Director Place, in consultation with the relevant Portfolio Holder for Climate and the relevant Portfolio Holder for Assets, and with recommendation by the Commissioning Governance Board, to proceed with contract award of the planned projects, where tender returns are within existing approved budgets, in order to deliver projects in line with external funding requirements.
Benefits to the Community:
Improving the energy efficiency and on site renewable energy generation of the council’s assets will improve their overall performance and life expectancy and reduce carbon emissions. It will reduce the local environmental impact, improve air quality and help mitigate the impacts of climate change. Lower running costs allow for the reallocation of funds towards essential local infrastructure, ultimately benefiting the community. Furthermore, these upgrades will improve indoor environmental conditions, comfort and well being for those using the buildings.
Key Points
1. The Council has set a target of reaching a Net Zero position in carbon emissions from its own operations by 2030. The largest contributor to this is emissions from gas use in council buildings. 2. The last update to the Committee, setting out an approach to the decarbonisation of council buildings, in June 2025, provided an update on the work undertaken through the externally funded Retrofit Accelerator - Workplaces programme to scope requirements. It also sought to agree the appointment of Cenergist to further develop and deliver works at selected buildings. The approach was to deliver the programme using funding from the Public Sector Decarbonisation Scheme (PSDS) to supplement the Council’s own capital budget allocated to the programme.
3. However, shortly after the appointment of Cenergist they were placed under administration and the Council could not continue with the award. Shortly after this, the Government announced that the PSDS was to cease, although existing allocated funding would be honoured.
4. Council officers have since been reviewing options for the replacement of the previous programme. While further plans will be considered inline with the proposed corporate asset strategy, it is recommended that the projects funded by the PSDS awards to date are progressed.
5. This includes works to the Dukes Centre, Surbiton Library and Tolworth Recreation Centre. These buildings are priorities for decarbonisation interventions as they make a significant contribution to the Council’s carbon footprint, are certain to be retained in the longer term and have end of life gas boilers that would otherwise require replacement.
6. Additionally, four of the previously proposed ten sites will receive smaller scale improvements, funded by Carbon Offset contributions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.