Review of Planning Enforcement Service (Ombudsman Action)
NotedCommittee3 papers
AI summaryKingston Place Committee formally received the Ombudsman's finding of fault over avoidable delays in planning enforcement and approved new timescales and a triaging system in the Local Enforcement Plan.
Written from the decision and the officer reportPDF Pro
OutcomeNotedUpdated Local Enforcement Plan to go live October 2026
MoneyNo new money identified, met from existing budgets
What happens nextPlan goes live October 2026Final report back to LGSCO required by 7 September 2026
Who it affectsResidents and developersAnyone reporting or subject to planning enforcement action
What was decided
The Committee formally received the LGSCO final decision statement finding fault causing injustice through avoidable delay in planning enforcement. Report P4, P15
Changes to the Local Enforcement Plan were approved, including new site visit timescales of 5 days for Priority 1, 15 days for Priority 2 and 30 days for Priority 3, plus a 28 day compliance window. Report P6, P64
Authority to amend the Plan was delegated to the Executive Director Place in consultation with the relevant Portfolio Holder. Report P7
Why
The LGSCO found fault causing injustice after a resident's 2024 complaint about delay and lack of communication on a Priority 3 enforcement case was escalated. Report P14, P15, P37
The Council's historical approach kept all cases live indefinitely without consistent triaging, leaving lower priority cases open for long periods and frustrating residents. Report P13, P19, P42
A backlog of open cases had reached c.800 and the Planning Peer Review by PAS in September 2025 also called for urgent triaging of enforcement cases. Report P22, P32, P55, P56
What happens next
The Local Enforcement Plan will be updated through summer 2026 and is expected to go live from October 2026. Report P65
The Council must send the Committee report, minutes and decisions to the LGSCO by 7 September 2026, six months after the 5 March 2026 decision statement. Report P51, P52, P53
An overall target is set to close 60% of enforcement cases within 20 weeks of receiving a complaint. Report P64
Options considered
Chosen: Approve the suggested changes to the Local Enforcement Plan and delegate amendments to the Executive Director Place. Responds to LGSCO findings, sets clearer timescales, and retains the existing triaging approach while adding new stages. Report P6, P7, P22, P64
Chosen: Note the LGSCO Focus Report on Planning Enforcement. Required as part of receiving the Ombudsman referral. Report P5, P44
Chosen: Note the actions already taken to reduce the active caseload from c.800 to 200 cases. Acknowledges progress made through recruiting two senior enforcement officers and triaging historic cases. Report P8, P20, P57, P58
Implications
Risk: Risk that the remaining LGSCO action to review the Plan is not completed within the timeframe; the review is programmed to comply with the September 2026 date. Report P51, P70, P71
Staffing: Two senior enforcement officers recruited into previously vacant posts and have undertaken the case triage. Report P20, P57
Equalities: An Equalities Relevance Test indicated no impact, so no Equalities Impact Assessment was carried out. Report P72
Legal: Officers identified no legal implications; planning enforcement remains discretionary under the Town and Country Planning Act 1990. Report P11, P24, P25, P69
Other: Where a breach is identified, site owners or developers will be given 28 days to comply, which may include confirming intent to submit a retrospective planning application. Report P64
Developers and site owners subject to enforcement action Report P64
Planning Enforcement staff within Development Management Report P20, P57
The Royal Borough of Kingston upon Thames as Local Planning Authority Report P11, P24
Timeline
2024: Resident reported planning breach concerns that led to the LGSCO complaint. Report P14, P32
December 2024: The Council's current Local Enforcement Plan was adopted. Report P12, P27
September 2025: Planning Advisory Service peer review recommended urgent triage of enforcement cases. Report P55
5 March 2026: Council received the LGSCO final decision finding fault causing injustice. Report P15, P37
24 March 2026: Written apology provided to the resident within 20 days. Report P16, P38
23 April 2026: Enforcement investigations completed and outcome written to the resident within 4 months. Report P17, P39
16 June 2026: Place Committee considered the Ombudsman referral and approved Plan changes. Report P18, P40
By 7 September 2026: Council must report the Committee outcome to the LGSCO. Report P51, P66
Summer 2026: Local Enforcement Plan to be updated. Report P65
October 2026: Updated Local Enforcement Plan expected to go live. Report P65
Plain English for the jargon
LGSCO: Local Government and Social Care Ombudsman, the body that investigates complaints about councils.
LPA: Local Planning Authority, the council body responsible for planning decisions and enforcement.
Expedient: Considered appropriate and in the public interest, the test for taking formal enforcement action.
NPPF and NPPG: National Planning Policy Framework and National Planning Practice Guidance, central government planning policy and guidance.
Triaging: Sorting incoming enforcement cases into priority bands so the highest harm cases are dealt with first.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17
Resolved
RESOLVED that: 1. the final decision statement by the Local Government & Social Care Ombudsman (LGSCO) regarding avoidable delays and failures in planning enforcement of the Council, at Annex 1 of the report, be formally received; 2. the Focus Report on Planning Enforcement by the LGSCO, at Annex 2 of the report, be noted; 3. the suggested changes to the Local Enforcement Plan as set out in paragraphs 23-27 of the report be approved; 4. authority be delegated to the Executive Director Place, in consultation with the relevant Portfolio Holder to make the necessary amendments to the Local Enforcement Plan; and 5. the actions outlined in paragraphs 20-22 to reduce the active caseload of reported breaches awaiting investigation be noted.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
To formally receive the Local Government and Social Care Ombudsman (LGSCO)’s final decision regarding avoidable delays and failures in planning enforcement of the Council, and to consider the proposals regarding the Planning Enforcement process in response to the decision.
Recommendation(s)
The Committee is asked to RESOLVE that:
1. the final decision statement by the Local Government & Social Care Ombudsman (LGSCO) regarding avoidable delays and failures in planning enforcement of the Council, at Annex 1 of the report, be formally received;
2. the Focus Report on Planning Enforcement by the LGSCO, at Annex 2 of the report, be noted;
3. the suggested changes to the Local Enforcement Plan as set out in paragraphs 23-27 of the report be approved;
4. authority be delegated to the Executive Director Place, in consultation with the relevant Portfolio Holder to make the necessary amendments to the Local Enforcement Plan; and
5. the actions outlined in paragraphs 20-22 to reduce the active caseload of reported breaches awaiting investigation be noted.
Benefits to the Community:
Reviewing and updating the Council's Planning Enforcement policy and associated processes provides residents and the local community with greater clarity regarding reported planning breaches. It also establishes whether it is expedient and in the public interest to investigate a reported planning breach and provides timeframes for investigations that are pursued. Key Points
A. Planning enforcement is the process by which Local Planning Authorities (LPAs) investigate and remedy breaches of planning control. Governed primarily by the Town and Country Planning Act 1990, taking formal enforcement action is entirely at the discretion of the LPA based on whether it is “expedient” and in the public interest.
B. The Council receives c.200 enforcement complaints/requests a year. The Council’s approach to Planning Enforcement is enshrined within a Local Enforcement Plan which was adopted in December 2024. In line with best practice, the Council operates a three tier prioritisation system to dictate its response to enforcement complaints. The highest priority is given to cases that relate to listed buildings, conservations areas and protected trees or where there is likely to be risk to the public through pollution, highways safety or through occupation.
C. Whilst the Council’s policy highlights the non-statutory nature of Planning Enforcement and makes clear that the Council may not take enforcement action against an identified breach where it is not considered appropriate to do so, the Council has not historically applied a triaging approach to manage reported breaches. Instead, the Council’s approach has typically been to record all cases and hold them as live pending review. Whilst action has subsequently been taken against the higher priority breaches, under this approach those in the lower - and especially the lowest - category have remained open and unactioned for a considerable period of time.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.