Soft FM (Cleaning and Porterage) - Contract Award

Approved Committee 1 paper

AI summaryKingston Council approves £7.51m Soft FM contract for cleaning, pest control, fire alarm testing and porterage across its corporate estate, starting 1 October 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor 3 years with possible 2 year extension
Money£7.51m excluding VAT£9.01m including VAT over full term
What happens nextContract starts 1 October 2026Award in July, mobilisation August to September 2026
Who it affects36 corporate buildingsIncluding Guildhall complex offices

What was decided

The committee approved awarding a Soft FM contract to the named bidder in Exempt Annex 1 for 3 years with a possible 2 year extension. Report P4, P11

The total contract value is £7.51m excluding VAT (£9.01m including VAT) for cleaning, pest control, fire alarm testing and porterage services across corporate property. Report P4

The new contract also introduces a new Computer Aided Facility Management system for planned and reactive work. Report P23

Why

The current Soft FM contract reaches the end of its term on 30 September 2026 and contains no provision for further extensions, so a new contract is required. Report P15, P8

Routine cleaning, pest control, fire alarm testing and porterage are needed to keep corporate buildings clean, safe and compliant for staff and visitors. Report P6, P18, P19

The procurement was carried out via the Crown Commercial Service Dynamic Purchasing System framework following strategy approval in March 2026, with bids received on 15 May 2026. Report P9

What happens next

Contract award is scheduled for July 2026, with mobilisation from August to September 2026 and commencement on 1 October 2026. Report P28, P29, P30

The Facilities Management team, led by the Workplace Manager, will monitor contract performance through progress meetings, scorecards and monthly financial monitoring. Report P22

The new supplier will set up a Computer Aided Facility Management system to track planned and reactive work and produce asset verification reports. Report P23

The money

  • £7.51m Total contract value excluding VAT for 3 years plus optional 2 years Report P4
  • £9.01m Total contract value including VAT for 3 years plus optional 2 years Report P4
  • £1.10m Current annual budget for Soft FM cleaning services Report P12, P32

Options considered

  • Chosen: Award a new contract for 3 years with an option to extend for a further 2 years. Identified supplier after compliant procurement; ensures consistent service at end of current contract Report P21
  • Rejected: Do nothing. Routine cleaning, fire alarm testing, pest control and porterage are all required; none can be provided in-house Report P18, P19
  • Rejected: Bring services in house. Cleaning requires a high number of staff and the Royal Borough of Kingston FM team lacks resources to manage them Report P20

Implications

  • Financial: The anticipated cost is higher than the current annual budget of £1.10m, creating pressure on the Facilities Management budget, but is broadly in line with historic spend and is expected to be contained within existing wider Property and Projects budgets. Report P12, P32, P33
  • Legal: The contract value exceeds £5m over the full term and therefore required approval from the Corporate and Resources Committee under the council's contract standing orders. Report P10
  • Equalities: An Equalities Relevance Test was undertaken and indicated no impact, so no full Equalities Impact Assessment was carried out. Report P40
  • Staffing: The council is a London Living Wage accredited employer and expects the contractor to pay staff at least the London Living Wage rate. Report P41
  • Climate: The supplier must use electric vehicles, concentrated products to reduce plastic, and report on energy, waste and recycling performance, with a route tracker to reduce mileage. Report P44, P46
  • Risk: Key risks identified are delay to contract, committee approval not being forthcoming, and insufficient budget; mitigations include a 12 month procurement programme, possible direct award via framework, and monthly financial monitoring. Report P37, P38, P39

Who and where

  • Staff and visitors using the Royal Borough of Kingston's 36 corporate buildings Report P6, P16
  • Council services that rely on Facilities Management porters for moving items, setting up meeting rooms and events Report P19
  • Service areas recharged for some Soft FM services and election support work delivered through the contract Report P16, P17
  • Polling stations and count venues that will receive logistics support from the new contract Report P16

Timeline

  • 19 March 2026: Corporate and Resources Committee approved the Soft FM procurement strategy Report P9
  • 15 May 2026: Bids received under the CCS Dynamic Purchasing System framework Report P9
  • 4 June 2026: Commissioning and Governance Board gave Gateway 2 approval Report P10, P26
  • 25 June 2026: Corporate and Resources Committee decision on contract award Report P27
  • July 2026: Contract award Report P28
  • August to September 2026: Contract mobilisation Report P29
  • 30 September 2026: Current Soft FM contract ends Report P15
  • 1 October 2026: New contract commences for an initial 3 years Report P11, P30

Plain English for the jargon

  • Soft FM: Soft Facilities Management: non-core building services such as cleaning, porterage, pest control and fire alarm testing.
  • CAFM: Computer Aided Facility Management system used to track planned and reactive facilities work.
  • CCS DPS Framework: Crown Commercial Service Dynamic Purchasing System, a government framework used to buy services.
  • LLW: London Living Wage, the minimum hourly rate the council expects contractors to pay staff.
  • GW2: Gateway 2, a stage in the council's commissioning governance process.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

RESOLVED that: The award of a contract to the named bidder in Exempt Annex 1 for a contract period of 3 years with a possible extension of 2 years, for a total value of £7.51m excluding VAT (£9.01m Inc VAT) to provide Soft FM services to include cleaning, pest control, fire alarm testing and porterage services for corporate property be approved.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Corporate and Resources Committee

Purpose of report

To award a contract for the provision of Soft FM services to the successful bidder named in the Exempt Annex part 1. To ensure the provision of cleaning services for the corporate estate. The services also include, fire alarm testing, pest control and porterage.

Recommendation(s)

The Committee is asked to RESOLVE that:

The award of a contract to the named bidder in Exempt Annex 1 for a contract period of 3 years with a possible extension of 2 years, for a total value of £7.51m excluding VAT (£9.01m Inc VAT) to provide Soft FM services to include cleaning, pest control, fire alarm testing and porterage services for corporate property be approved.

Benefits to the Community:

The provision of cleaning services, pest control, fire alarm testing ensures that corporate property is a clean, safe and hygienic environment for staff and visitors to the Council’s buildings.

Key Points

A.​ The Council maintains a commitment to provide clean, safe and hygienic environments for its staff and visitors. The provision of cleaning services, pest control, porterage and fire alarm testing falls under the remit of Soft FM services. This is an outsourced service and the current contract term will end on the 30 October 2026. The contract contains no provision for further extensions.

B.​ The Corporate & Resources Committee (C&R) approved the Soft FM procurement strategy at its meeting on 19 March 2026 to go out to tender via the CCS DPS Framework. Bids were received on 15 May 2026 and an evaluation and moderation exercise has since taken place resulting in a recommendation to award a contract.

C.​ The outcome of the tender evaluation and recommendation to award is summarised in the Exempt Annex 1 and was approved by the Commissioning Governance Board on 4 June 2026. The contract value for the full five years is over £5m and therefore requires approval from the C&R Committee under the Council’s contract standing orders.

D.​ The new contract will commence on 1 October 2026 for an initial duration of three years with an option to extend by two further years.

E.​ It is noted that the anticipated cost of the services is higher than the annual budget of £1.10m which presents a pressure to the Council’s FM budget. However, the total cost of the new contract is broadly in line with the historic cost of the services which has been contained within the wider Property and Projects Service budgets. It is therefore assumed that the cost of the services can be contained within existing budgets.

Context / Programme and Project Progress

1.​ The Facilities Management Team within the Property and Projects Department of the Place Directorate are responsible for the provision of cleaning services. They are also responsible for pest control, fire alarm testing and porterage. These services are currently delivered on behalf of the Council by an external contractor.

2.​ The contract for the provision of these services comes to an end on 30 September 2026, and with no options for further extension, a new contract is required. Therefore a procurement exercise to appoint a suitable contractor for the delivery of these services has been undertaken.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Soft FM (Cleaning and Porterage): Contract AwardReport 133 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Kingston upon Thames

Search all
  1. Soft FM (Cleaning and Porterage) - Contract AwardThis decision
  2. Contract for the provision of Soft Facilities Management - Cleaning & SecurityDecided

More from Kingston upon Thames Corporate and Resources Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 Council Plan End of Year Report 2025/26RESOLVED that: 1) The End of Year Report for 2025/26, at Annex 1 to the report, be noted. 2) The newly published Loca... Noted Open
25 Jun 2026 Changes to Health GovernanceRECOMMENDED to Council that: 1) a separate Health and Wellbeing Board be re-established for Kingston, and the propose... Approved Open
25 Jun 2026 Revenue and Capital Outturn Report 2025/26RESOLVED that: 1) The outturn position of a £0.62m underspend in respect of the General Fund for 2025/26 be noted; 2)... Noted Open
25 Jun 2026 Housing Management System Implementation: Request for Additional FundingRESOLVED that: 1) the progress made to date on the implementation of the NEC Housing Management System be noted; 2) t... Noted Open
25 Jun 2026 Leader of the Opposition OptionsRESOLVED that: Having considered the options outlined in the report, Option 1 (the status quo) be adopted as the pref... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies