1) That approval be given to the Dewsbury Riverside Masterplan and Masterplan Framework in order to ensure that Dewsbury Riverside is developed in a sustainable manner, enhancing the North Kirklees area. 2) That it be noted that two current grant bid submissions (£4.6m Local Growth Fund and £22.5m Housing Infrastructure Fund) will support the delivery of the vision set out within the Masterplan and Masterplan Framework. 3) That it be noted that, in accordance with Financial Procedure Rules, the Chief Finance Officer, in consultation with the Service Director – Legal, Governance and Commissioning, and the relevant Strategic Director, is authorised to approve the acceptance of any subsequent Grant Agreement for the two bids, if successful. 4) That authority be delegated to the Service Director – Legal Governance and Commissioning, to enter into and execute any Grant Agreement with the Combined Authority for the Local Growth Fund Grant, and also to enter into and execute any ancillary documents relating to the Grant Agreement. 5) That it be noted that (2) above will ensure that funding can be obtained in order to deliver the vision set out within the Masterplan and Masterplan Framework.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
Title of report: Dewsbury Riverside Masterplan & Masterplan Framework
Purpose of report: This report seeks:
1. Endorsement of the Masterplan and Masterplan Framework for development of the Kirklees Local Plan housing allocation at Dewsbury Riverside 2. Authority for the Council to enter into an agreement with the Combined Authority to accept Local Growth Fund grant to facilitate infrastructure delivery at Dewsbury Riverside
Key Decision - Is it likely to result in Yes spending or saving £250k or more, or to If yes give the reason why: have a significant effect on two or more Affects more than 1 ward electoral wards? Key Decision - Is it in the Council’s Forward Yes Plan (key decisions and private reports?) If yes also give date it was registered:
The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director & Karl Battersby - 7.03.2019 name
Is it also signed off by the Service Director Eamonn Croston - 7.03.2019 for Finance?
Is it also signed off by the Service Director Julie Muscroft - 8.03.2019 for Legal Governance and Commissioning? Cabinet member portfolio Cllr Peter McBride - Economy
Electoral wards affected: Dewsbury South/Mirfield
Ward councillors consulted: Cllr Ahmed, Cllr Asif, Cllr Dad (Dewsbury South); Cllr Bolt, Cllr Lees-Hamilton, Cllr Taylor (Mirfield)
Public or private: Public
(Have you considered GDPR?) Check
Yes - No Personal Data
GDE-GOV-REPORTTEMPLATE-v3-02/17 NEW 1. Summary
1.1Dewsbury Riverside is a key site within the North Kirklees Growth Zone which is identified as a spatial priority area for housing growth in the Leeds City Region Strategic Economic Plan. The site is allocated for housing in the recently adopted Kirklees Local Plan with capacity for up to 4000 homes, of which approximately 1869 are proposed to be developed within the Local Plan period up to 2031.
1.2The vision for Dewsbury Riverside is to create a sustainable urban extension that will deliver social, environmental and economic benefits, provide a mix of high quality homes of different tenures together with community infrastructure to create a sustainable, vibrant mixed community; and to retain, expand and enhance existing green infrastructure, connecting new and existing communities to healthy lifestyle opportunities. The scale of the development is intended to be large enough to allow a degree of “market repositioning” and thereby to act as a catalyst for the regeneration of the wider area.
1.3The masterplan and masterplan framework together set out the ‘what and where’ for the development of the allocation. The masterplan framework brings together a significant amount of technical and design work that has been undertaken, it explains the context for the masterplan and sets out the high level phasing of development across the site. The masterplan sets out the distribution of and inter-relationship between land uses across the allocation, the points of access into the site from the local highway network and the internal layout of the site.
1.4The masterplan has been designed around a series of neighbourhoods radiating from a central urban park, new local centre and primary school, phased to be delivered early in the development to act as a catalyst and driver for the early development of the scheme and that form the heart of the urban village centre. It seeks to retain existing green infrastructure in the form of woodland belts, copses and hedgerows with incursions for highway access being minimised. Green spaces are connected by green routes that are aligned to and accommodate existing public rights of way and bridleways across the site. Additional green infrastructure will be provided through the adoption of green streets and SUDS principles within the masterplan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.