Cabinet, Tuesday 19 March 2019 at 4.00pm

10

Approved Executive 3 papers

Cabinet approved this item on Tuesday 19 March 2019. Below is the council's own wording, with the papers it was decided on.

Item10:

Resolved

1) That approval be given to the Dewsbury Riverside Masterplan and Masterplan Framework in order to ensure that Dewsbury Riverside is developed in a sustainable manner, enhancing the North Kirklees area. 2) That it be noted that two current grant bid submissions (£4.6m Local Growth Fund and £22.5m Housing Infrastructure Fund) will support the delivery of the vision set out within the Masterplan and Masterplan Framework. 3) That it be noted that, in accordance with Financial Procedure Rules, the Chief Finance Officer, in consultation with the Service Director – Legal, Governance and Commissioning, and the relevant Strategic Director, is authorised to approve the acceptance of any subsequent Grant Agreement for the two bids, if successful. 4) That authority be delegated to the Service Director – Legal Governance and Commissioning, to enter into and execute any Grant Agreement with the Combined Authority for the Local Growth Fund Grant, and also to enter into and execute any ancillary documents relating to the Grant Agreement. 5) That it be noted that (2) above will ensure that funding can be obtained in order to deliver the vision set out within the Masterplan and Masterplan Framework.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet

Name of meeting: Cabinet

Date: 19 March 2019

Title of report: Dewsbury Riverside Masterplan & Masterplan Framework

Purpose of report: This report seeks:

1. Endorsement of the Masterplan and Masterplan Framework for development of the Kirklees Local Plan housing allocation at Dewsbury Riverside 2. Authority for the Council to enter into an agreement with the Combined Authority to accept Local Growth Fund grant to facilitate infrastructure delivery at Dewsbury Riverside

Key Decision - Is it likely to result in Yes spending or saving £250k or more, or to If yes give the reason why: have a significant effect on two or more Affects more than 1 ward electoral wards? Key Decision - Is it in the Council’s Forward Yes Plan (key decisions and private reports?) If yes also give date it was registered:

The Decision - Is it eligible for call in by Yes Scrutiny?

Date signed off by Strategic Director & Karl Battersby - 7.03.2019 name

Is it also signed off by the Service Director Eamonn Croston - 7.03.2019 for Finance?

Is it also signed off by the Service Director Julie Muscroft - 8.03.2019 for Legal Governance and Commissioning? Cabinet member portfolio Cllr Peter McBride - Economy

Electoral wards affected: Dewsbury South/Mirfield

Ward councillors consulted: Cllr Ahmed, Cllr Asif, Cllr Dad (Dewsbury South); Cllr Bolt, Cllr Lees-Hamilton, Cllr Taylor (Mirfield)

Public or private: Public

(Have you considered GDPR?) Check

Yes - No Personal Data

GDE-GOV-REPORTTEMPLATE-v3-02/17 NEW 1. Summary

1.1Dewsbury Riverside is a key site within the North Kirklees Growth Zone which is identified as a spatial priority area for housing growth in the Leeds City Region Strategic Economic Plan. The site is allocated for housing in the recently adopted Kirklees Local Plan with capacity for up to 4000 homes, of which approximately 1869 are proposed to be developed within the Local Plan period up to 2031.

1.2The vision for Dewsbury Riverside is to create a sustainable urban extension that will deliver social, environmental and economic benefits, provide a mix of high quality homes of different tenures together with community infrastructure to create a sustainable, vibrant mixed community; and to retain, expand and enhance existing green infrastructure, connecting new and existing communities to healthy lifestyle opportunities. The scale of the development is intended to be large enough to allow a degree of “market repositioning” and thereby to act as a catalyst for the regeneration of the wider area.

1.3The masterplan and masterplan framework together set out the ‘what and where’ for the development of the allocation. The masterplan framework brings together a significant amount of technical and design work that has been undertaken, it explains the context for the masterplan and sets out the high level phasing of development across the site. The masterplan sets out the distribution of and inter-relationship between land uses across the allocation, the points of access into the site from the local highway network and the internal layout of the site.

1.4The masterplan has been designed around a series of neighbourhoods radiating from a central urban park, new local centre and primary school, phased to be delivered early in the development to act as a catalyst and driver for the early development of the scheme and that form the heart of the urban village centre. It seeks to retain existing green infrastructure in the form of woodland belts, copses and hedgerows with incursions for highway access being minimised. Green spaces are connected by green routes that are aligned to and accommodate existing public rights of way and bridleways across the site. Additional green infrastructure will be provided through the adoption of green streets and SUDS principles within the masterplan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Dewsbury Riverside Masterplan and Masterplan FrameworkReport 599 KB DownloadRead as text
PDF
Item 10a P0-MP-SPS-IL-P3565-1000-09S-PR-Masterplan_ (002) :Report 3.2 MB Download
PDF
Item 10b -0013-0003-C-Masterplan-Framework :Report 163 MB Download

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open